Hut 8: Batavia, IL

Latest Podcast 1780 Hubbard Ave
Planned
Future facility in planning stage
Operated by:

Hut 8: Batavia, IL

Site planned for 2027 and has expansions through 2031
Utility Provider: City of Batavia (municipal), PJM

HPC and cryptomine data center developer Hut 8 is developing a 120,000 sq ft (11,148 sqm) data center nearby Batavia, Kane County. The City Council approved a services agreement with Hut affiliate Batavia DC Corp. in July 2025. The data center is expected to begin operations in 2027, and it is projected to reach full capacity in phases through to 2031.

Map and Nearby Locations

1780 Hubbard Ave
Hut 8 Corp Sites
Nearby Facilities

Hut 8: Batavia, IL Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Hut 8: Batavia, IL

Distance Site About
1.58 miles SBA Edge: 603 Discovery
Former New Continuum site that was acquired in 2019
2.22 miles Colovore: West Chicago ORD02
ORD02 is Colovore's second Chicago-area facility, located in West Chicago and extending the company's distributed footprint across the metro. The liquid-cooled, HVDC-ready site is under construction and pre-leasing for edge AI and high-performance colocation workloads.
3.85 miles Edged Energy: Aurora ORD01
The new data center campus, Aurora TechPark, will offer facilities built to handle dense AI-driven workloads that are transforming the IT industry.
3.91 miles Edged Energy: Chicago ORD02
The new data center campus, Aurora TechPark, will offer facilities built to handle dense AI-driven workloads that are transforming the IT industry.
4.03 miles CyrusOne: CHI3 DC1
CyrusOne is developing a pair of new data centers in Aurora, Illinois, a project that will also include the construction of three 350-foot telecommunication towers.
4.04 miles Edged Energy: Chicago ORD03
This facility will be part of Edged Energy's Aurora TechPark in Chicago.
4.06 miles CyrusOne: CHI3 DC2
CyrusOne is developing a pair of new data centers in Aurora, Illinois, a project that will also include the construction of three 350-foot telecommunication towers.
4.45 miles CyrusOne: CHI2 DC1
The CyrusOne CHI2 data center is located on 16 acres, 45 minutes southwest of Chicago O'Hare International Airport.
4.46 miles DataCanopy: Chicago, IL
4.48 miles CyrusOne: Aurora CME (CHI1)
In 2016, CyrusOne acquired the CME data center for $130 million. CME hosts its electronic trading platform CME Globex on site. Globex will continue to be hosted on site as part of the 15-year lease agreement between CyrusOne and CME.
4.52 miles CyrusOne: CHI2 DC2
CyrusOne's CHI2 second building is located at 2805 Diehl Road, Aurora, IL.
5.04 miles NetSource Chicago
5.69 miles Raeden: Naperville (1415 W Diehl)
The former Tellabs headquarters at 1415 West Diehl Road in Naperville, a mostly-office building with a legacy data center, planned for AI data center redevelopment.
6.47 miles Colovore: ORD04
Colovore's fourth Chicago-area facility, a purpose-built liquid-cooled colocation building in Aurora's Meridian Business Campus, adjacent to the company's ORD01 site. Two-hall design with service dates in late 2028 and early 2029.
6.53 miles Colovore: ORD03
Colovore's third Chicago-area facility, a purpose-built liquid-cooled colocation building in Aurora's Meridian Business Campus. Two-hall design with service dates in 2028.
6.55 miles 4267 Meridian Pkwy: Lincoln Rackhouse
The facility was acquired when Lincoln Rackhouse acquired Bytegrid in 2019.
6.55 miles US Signal: IL02 Aurora
US Signal's Aurora, Illinois data center at 4267 Meridian Parkway in the Meridian Business Campus, acquired in December 2025. The 70,000 sq ft facility carries about 33,000 sq ft of white space and is being upgraded in phases with new UPS, cooling and generator capacity, with liquid-cooled high-density space planned. It connects to US Signal's Oak Brook site and national fiber backbone and hosts the company's OpenCloud platform.
6.56 miles DataBridge: Aurora, IL
DataBridge Sites is the new name for ESite Systems, a company with two decades of history in the industry.
6.57 miles Colovore: ORD01
Colovore's first Chicago-area facility, a purpose-built liquid-cooled colocation building in Aurora's Meridian Business Campus. Single data hall slated for service in late 2026.
6.89 miles Karis: Naperville (INEOS)
Real estate developer Karis Critical is in early-stage exploratory discussions to potentially acquire the 168-acre former BP/INEOS campus at in Naperville, Illinois, within the Suburban Chicago market.
7.50 miles Cogent Naperville
8.35 miles Karis: Naperville, IL
The Naperville City Council officially denied Karis Critical’s proposal for a "boutique data center campus" at 1960 Lucent Lane in January 2026.
8.70 miles Connect Data Centers: Chicago
Oppidan is developing Carol Stream’s first data center in Chicago, Illinois.
9.78 miles Centersquare: Lisle CHI1
Centersquare's cloud-enabled Lisle data center is situated approximately 20 miles from O’Hare International airport.
9.95 miles WhiteRose: South Elgin, IL
Whiterose Partners LLC is proposing a 200,000-square-foot data center on nine acres in South Elgin, Illinois, located roughly 40 miles west of Chicago.
11.34 miles CloudCenters: Lisle, IL
The Cloud Centers data center project aims to transform the 18 acre former Lockformer superfund site in Lisle, Illinois, into a two story, 256,000 square foot facility.
12.35 miles CyrusOne: Lombard CHI5
9 MW of critical capacity Both a 1.5MW and a 2MW transformer
13.48 miles Digital Fortress: Chicago Lombard
13.48 miles 360TCS-Lombard
13.88 miles Pioneer: Project Cardinal 1
First building of the northeast phase of Pioneer Development's Project Cardinal campus in Yorkville, Illinois. Planned as a two-story data center of about 1.36 million sq ft beside the campus ComEd switchyard and customer substation.
14.04 miles Pioneer: Project Cardinal Expansion
The other 13 planned buildings of Pioneer Development's Project Cardinal campus in Yorkville, Illinois, built in northeast, south and west phases after the first building.
14.73 miles Magnolia Hill: Yorkville Corneils Road
Proposed data center site of about 143 acres at Corneils Road and IL Route 47 near Bristol, Illinois, east of Yorkville, linked to Orlando family office Magnolia Hill Partners. Yorkville logged it as a site inquiry in 2025; no petition has been filed.
14.94 miles Prologis: Project Steel Expansion
Future Phases 2 and 3 of Prologis's Project Steel campus in Yorkville, Illinois: twelve two-story buildings and two substations at Galena and Eldamain roads, planned over the 2030s and 2040s.
15.06 miles Compass Hoffman Estates
Located in Cook County, the campus will feature five buildings and represents a total planned investment of $10 billion.
15.18 miles Prologis: Project Steel 1
Phase 1 of Prologis's Project Steel campus in Yorkville: four two-story data center buildings of about 425,000 sq ft each and two substations, east of the ComEd corridor off Corneils and Beecher roads. Construction is planned to start in 2027.
15.59 miles Equinix Chicago CH7
Equinix CH7 is a single-story colocation data center at 111 Plaza Drive in Westmont, Illinois, built in 1999 and acquired from Verizon, where it was ORD1, in 2017.
15.60 miles Green Door: Yorkville Hagemann
Green Door Capital land-bank data center tract of about 138 acres on Eldamain Road in Yorkville, Illinois, held by Yorkville Nexus III LLC. Annexed and rezoned M-2 in 2024; no end user or site plan has been filed. Borders Prologis Project Steel near ComEd's Plano substation.
15.74 miles Karis: Hoffman Estates Campus
Karis Critical and site owner Hoffman Estates Holdings officially withdrew their rezoning application for the proposed data center project in Hoffman Estates, Illinois, in June 2026, putting all active approvals on hold.
15.86 miles Nexstar: Elk Grove Bldg1
As of January 2026, the Nexstar/WGN data center project has expanded from its original 35-acre, three-building plan to a four-building campus utilizing a larger portion of the 102-acre transmitter site.
15.90 miles Nexstar: Elk Grove Bldg2
This facility is part of Nexstar's Elk Grove data center campus in Illinois.
15.97 miles Nexstar: Elk Grove Bldg4
This facility is part of Nexstar's Elk Grove data center campus in Illinois.
15.99 miles Nexstar: Elk Grove Bldg3
This facility is part of Nexstar's Elk Grove data center campus in Illinois.
16.09 miles NTT: Chicago CH3
CH3 is a data center under construction at 235 Pierce Road on NTT's Itasca campus in Itasca, Illinois, with four data vaults.
16.17 miles NTT: Chicago CH1
The first building on NTT's Itasca campus: a two-story data center at 255 Pierce Road with six data vaults and four primary 34.5 kV ComEd feeds plus one alternate.
16.20 miles NTT: Chicago CH2
CH2 is a two-story data center at 275 Pierce Road on NTT's Itasca campus in Itasca, Illinois, with six data halls.
16.21 miles Green Door: Yorkville 50 Acres
Green Door Capital land-bank data center tract of about 50 acres at Eldamain and Corneils roads in Yorkville, Illinois, held by Yorkville Nexus LLC. Zoned M-2 for data center use; no end user or site plan has been filed. Lies just north of CyrusOne's Yorkville campus.
16.31 miles NTT: Chicago CH4
CH4 is a planned data center at 1200 N. Arlington Heights Road on NTT's Itasca campus, on the site of two office buildings NTT bought and cleared.
16.32 miles Park UltraInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
16.33 miles CyrusOne: Yorkville 8
Building 11H of CyrusOne's Yorkville Technology Campus (CHI11) at Eldamain and Faxon roads in Yorkville, Illinois. A planned single-story data center of about 246,000 sq ft on the campus's east edge along Beecher Road.
16.34 miles CyrusOne: Yorkville 9
Former ninth building of CyrusOne's 2024 Yorkville Technology Campus plan in Yorkville, Illinois. CyrusOne cut the campus to eight buildings in 2026, so this building is no longer planned.
16.35 miles DMYF: Yorkville Daniels North
Land-bank data center tract of about 54 acres between the BNSF railroad and Faxon Road at Beecher Road in Yorkville, Illinois, owned by the Daniels Malinski Yorkville Family partnership. Rezoned M-2 in 2025, next to CyrusOne's campus. No end user or site plan filed.
16.44 miles Central PointInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
16.46 miles Valley ProInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
16.48 miles CyrusOne: Yorkville 7
Building 11G of CyrusOne's Yorkville Technology Campus (CHI11) at Eldamain and Faxon roads in Yorkville, Illinois. A planned single-story data center of about 246,000 sq ft at the east end of the south row, south of the on-site substation.
16.49 miles CyrusOne: Yorkville 2
Building 11B of CyrusOne's Yorkville Technology Campus (CHI11) at Eldamain and Faxon roads in Yorkville, Illinois. A planned single-story data center of about 129,000 sq ft, the campus's smallest building, beside Building 11A in the northwest section.
16.50 miles NTT: Chicago CH5
CH5 is a planned three-story data center on the former Marino Court subdivision east of Arlington Heights Road, the fifth and final building on NTT's Itasca campus.
16.53 miles CyrusOne: Yorkville 4
Building 11D of CyrusOne's Yorkville Technology Campus (CHI11) at Eldamain and Faxon roads in Yorkville, Illinois. A planned single-story data center of about 246,000 sq ft in the campus's middle row, just west of the on-site substation.
16.53 miles CoreInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
16.53 miles CyrusOne: Yorkville 1
Building 11A of CyrusOne's Yorkville Technology Campus (CHI11) at Eldamain and Faxon roads in Yorkville, Illinois. A planned single-story data center of about 246,000 sq ft in the campus's northwest section. CyrusOne plans to build it first.
16.61 miles CyrusOne: Yorkville 6
Building 11F of CyrusOne's Yorkville Technology Campus (CHI11) at Eldamain and Faxon roads in Yorkville, Illinois. A planned single-story data center of about 246,000 sq ft in the middle of the campus's south row.
16.66 miles CyrusOne: Yorkville 3
Building 11C of CyrusOne's Yorkville Technology Campus (CHI11) at Eldamain and Faxon roads in Yorkville, Illinois. A planned single-story data center of about 246,000 sq ft at the west end of the campus's middle row.
16.71 miles PointInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
16.74 miles CyrusOne: Yorkville 5
Building 11E of CyrusOne's Yorkville Technology Campus (CHI11) at Eldamain and Faxon roads in Yorkville, Illinois. A planned single-story data center of about 246,000 sq ft at the west end of the campus's south row, near Faxon Road.
16.75 miles Brennan Investment: Barrington, IL
The Brennan Investment Group has officially withdrawn its ambitious plans for a $2 billion data center project in Barrington Hills, a village located roughly 40 miles northwest of Chicago, Illinois.
16.84 miles Green Door: Yorkville Kelaka
Green Door Capital land-bank data center tract of about 154 acres south of Faxon Road in Yorkville, Illinois, held by Yorkville Nexus IV LLC. Yorkville approved its annexation and rezoning; no end user or site plan has been filed. Lies just south of CyrusOne's Yorkville campus.
16.87 miles NYI Chicago (Oak Brook)
16.98 miles Verizon: (Oak Brook)
16.98 miles US Signal Oakbrook IL01
800a 480V 3 phase 450kW diesel generator with 24 hour run time at full load 500kVa UPS capacity with battery backup
16.98 miles Server Farm Oak Brook
The campus was originally built as the corporate headquarters of the Chicago Bridge & Iron Company (CB&I).
17.08 miles Complete Source Schaumburg
17.33 miles DMYF: Yorkville Daniels South
Land-bank data center tract of about 268 acres at the northwest corner of US 34 and Beecher Road in Yorkville, Illinois, owned by the Daniels Malinski Yorkville Family partnership. Yorkville annexed and rezoned it M-2 in 2025. No end user or site plan has been filed.
17.40 miles Kelaka: Yorkville Hamman
Kelaka LLC land-bank data center tract of about 112 acres in Yorkville, Illinois, in two pieces: south of Faxon Road beside Kylyn's Ridge, and at US 34 and Eldamain Road. Yorkville annexed and rezoned it M-2 in 2025. No end user or site plan has been filed.
17.46 miles Element Critical CH2
Element Critical acquired the site in January 2019 from Sungard. The facility was previously known as SunGard Wood Dale (341).
17.62 miles Element Critical CH1
Element Critical acquired the site in January 2019 from Sungard. The facility was previously known as SunGard Wood Dale (711).
17.70 miles Savion: Plano 1
Plano 1 is the first building in Savion's proposed data center campus beside the Plano Skies Energy Center north of Plano, Illinois.
17.77 miles DigiCo: Chicago
The facility sits on a ten-acre site and will serve as a flagship asset in HMC Capital's newly established DigiCo Infrastructure REIT.
17.78 miles Carrier-Neutral Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
17.92 miles LexusNexis Oak Brook
17.93 miles DataBank (ORD4) Oak Brook
17.93 miles Verizon: Swift Dr
17.95 miles Savion: Plano Expansion
18.26 miles 1400 E Devon Ave (CH3) DRT
18.35 miles CoreWeave: US Central ORD1
18.36 miles HostPapa CH1
Formerly known as "ColoCrossing CH1"
18.36 miles Deft: Elk Grove DF-CH1
18.37 miles Rackspace Elk Grove ORD1
18.39 miles 2200 Busse Rd (CH1) DRT
18.45 miles Aligned: ORD-02
Aligned's ORD-02 is a data center located in Northlake, IL near downtown Chicago. Part of Aligned's 18.5-acre hyperscale campus.
18.50 miles Centersquare: Chicago ORD2
Cyxtera's CH3 Elk Grove site is across the street from the Digital Realty Chicago campus (former Dupont Fabros) and close to Equinix CH3.
18.50 miles Aligned: ORD-01
Aligned's ORD-01 data center is a state-of-the-art facility located in Northlake, IL, just outside of downtown Chicago. At full build, Aligned’s Chicago campus covers 520,000 sq. ft. and offers ~ 100 MW of critical load.
18.53 miles 2299 Busse (CH2) Digital Realty
18.57 miles Prime ValleyInterested in this information?Contact us
18.64 miles Stack: CHI01B
Two-story data center at 1301 Touhy Avenue, built by STACK next to CHI01A on the same parcel, with four data halls and diverse underground ComEd feeds.
18.70 miles Stream Chicago II
Stream Data Centers' Chicago II data center in Elk Grove Village, Illinois is a 226,000 square foot facility.
18.71 miles Stack: CHI01A
Single-story data center at 1441 Touhy Avenue in Elk Grove Village. Forsythe Technology broke ground on it in 2014, T5 bought it in 2016, and IPI Partners made it part of STACK. It adjoins CHI01B on a shared 14-acre parcel.
18.84 miles 505 N Railroad Ave - Digital Realty
The Digital Chicago Campus covers 21 acres of land with access to major fiber networks and can support up to 8 MW of IT load at N+1 redundancies.
18.88 miles T5: Chicago lll
T5@Chicago III will be build-to-suit, with the company spending more than $500 million to develop a three-story, 250,000 sq ft facility for multi-tenant or single-tenant operations.
18.92 miles T5 Chicago II
T5 Chicago II campus is located at 200 Innovation Drive in the Elk Grove area.
18.92 miles Equinix Chicago CH3
Equinix CH3 is a three-story colocation data center at 1905 Lunt Avenue in Elk Grove Village, Illinois, that Equinix opened in 2007 and expanded in five more phases through 2020.
18.98 miles Equinix: CH5
Equinix has started construction on a new 195,000-square-foot, two-story data center in Elk Grove, Chicago. This new facility is being built right next to their existing CH3 data center.
19.03 miles EdgeConneX CHI02
19.04 miles South CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
19.05 miles Aligned: ORD-03
Aligned is building a datacenter campus after acquiring an assemblage of beleaguered office properties near O’Hare International Airport.
19.09 miles EdgeConneX CHI01
CHI01 is EdgeConneX's first Chicago data center, a 132,000 sq ft retrofit at 1800 Nicholas Blvd in Elk Grove Village, Illinois.
19.10 miles NorthInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
19.11 miles Stream Chicago I
Free-Standing, Data Center Designed to Tier III Standards
19.12 miles Station AlphaInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
19.12 miles EdgeConneX: CHI03
EdgeConneX CHI03 is a new 167,000 sq ft, two-story data center building on its Elk Grove Village campus near Chicago.
19.18 miles Aligned: ORD-04
This facility will be part of Aligned's ORD-03 campus in Elk Grove Village, a suburb of Chicago.
19.19 miles EdgeConneX: CHI04
CHI04 is a two-story, 164,000 sq ft EdgeConneX data center under construction at 901 Busse Road in Elk Grove Village, Illinois, near O'Hare Airport.
19.26 miles EdgeConneX: CHI05
CHI05 is EdgeConneX's planned second data center on Busse Road in Elk Grove Village, Illinois, on the parcel next to CHI04.
19.39 miles Carrier-Neutral Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
19.39 miles Stack: CHI02
Data center firm Stack Infrastructure is expanding its footprint in Chicago, Illinois with a new data center in Elk Grove Village, known as CHI02.
19.42 miles Prime: ORD01-02
Building B will be another three-story construction, offering 279,360 gross square feet of space.
19.45 miles Stream: Chicago ORDC2
Stream DC aims to demolish around 55 Elk Grove residential properties to develop a three-building data center campus with an on-site substation. The three buildings will total more than 2 million sq ft.
19.47 miles Prime: ORD01-01
Prime Data Centers is building a 750,000 square foot hyperscale data center campus in Elk Grove Village (Chicago), Illinois, which will comprise an investment of around $1 billion.
19.48 miles Stream: Chicago ORDC3
Stream DC aims to demolish around 55 Elk Grove residential properties to develop a three-building data center campus with an on-site substation. The three buildings will total more than 2 million sq ft.
19.52 miles Prime: ORD01-03
Building C will be another three-story construction, offering 294,429 gross square feet of space.
19.75 miles TA Realty: Elk Grove
TA Realty is constructing a 45-acre data center campus at the corner of Elmhurst Road and Old Higgins Road. The development includes four two-story buildings and an electrical substation.
19.91 miles T5: Chicago V
T5 Data Centers has secured land in Elk Grove Village to build its upcoming CHI V data center. The planned 220,000 square foot (20,438 sqm) facility is expected to be operational by 2028.

Operating Company

Operated by:

Hut 8 is one of North America's oldest, largest and most innovative digital asset miners in the world. Hut has one of the highest installed capacity rates in the industry and is the largest holder of self-mined Bitcoin of publicly traded companies globally.

0
Facilities
0
Markets
0MW
Megawatts

News See all

Read 12-Story Chicago Office Building Eyed for Data Center Conversion
An office building in Chicago, Illinois, is being considered for conversion into a data center. Local media, including ABC, report that the Permit Review Committee of the Commission on Chicago Land...

12-Story Chicago Office Building Eyed for Data Center Conversion

August 10, 2026 Chicago

An office building in Chicago, Illinois, is being considered for conversion into a data center. Local media, including ABC, report that the Permit Review Committee of the Commission on Chicago Landmarks has given initial approval to plans to convert part of the 300 West Adams Building into a data...

Read more
Read Closed Chicago-area incinerator Being Explored for Data Center Development
A shuttered incinerator in Robbins, near Chicago, is attracting interest from multiple data center developers. According to NBC and the Chicago Tribune, at least five potential buyers have approach...

Closed Chicago-area incinerator Being Explored for Data Center Development

June 26, 2026 Chicago

A shuttered incinerator in Robbins, near Chicago, is attracting interest from multiple data center developers. According to NBC and the Chicago Tribune, at least five potential buyers have approached owner Paul Duggan this year about acquiring the 16-acre Robbins Resource Recovery Center site at...

Read more
Read New Firm Announces Plans for 20MW Liquid-Cooled Data Center
New Firm Announces Plans for 20MW Liquid-Cooled Data Center

New Firm Announces Plans for 20MW Liquid-Cooled Data Center

September 12, 2025 Chicago

A new liquid-cooled data center is being developed in downtown Chicago, Illinois by HydraVault, a new data center developer. The developer says the facility will be “designed from the ground up” for AI and financial systems.The 20MW two-story facility, located at 2538 South Wabash Avenue, will...

Read more
Read Hut 8 Announces Four Data Center Projects across US
Hut 8 Announces Four Data Center Projects across US

Hut 8 Announces Four Data Center Projects across US

August 28, 2025 Hut 8 Corp

HPC and cryptomine data center developer Hut 8 this week announced plans to develop four new sites across the United States, totaling 1.53GW of capacity under development. The expansion sites range in scale from 50MW to 1GW of utility capacity across Louisiana, Texas, and Illinois. Hut 8 said it...

Read more
Read Hut 8 Awarded Five-Year Capacity Contract for 310MW of Natural Gas Power in Ontario
Hut 8 Awarded Five-Year Capacity Contract for 310MW of Natural Gas Power in Ontario

Hut 8 Awarded Five-Year Capacity Contract for 310MW of Natural Gas Power in Ontario

July 03, 2025 Hut 8 Corp

Cryptomining and HPC firm Hut 8 has been awarded a five-year capacity contract with the Ontario Independent Electricity System Operator (IESO) for 310MW of natural gas generation assets. The portfolio is owned and operated by Far North Power Corp, a partnership between Hut 8 and Macquarie...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts

Ready to Level up Your
Data Center Strategy?