Aligned is about to build a datacenter campus after acquiring an assemblage of beleaguered office properties near O’Hare International Airport.

  • The company’s plan for the 36-acre site calls for a pair of two-story, 520,000-square-foot data centers to house servers, wires and other equipment.
  • Aligned acquired 50 Northwest Point Boulevard in Elk Grove Village in March from Franklin Street Properties for $29 million in 2023. The five-story, 177,000 sq ft (16,450 sqm) office building, was built around 2000 and sits on 10 acres.
  • The company aims to demolish existing office buildings located at 50, 100, 101, and 150 Northwest Point Boulevard and construct a data center campus with two two-story data center buildings.
  • Construction of the first data center is scheduled to commence by the end of 2024, with an estimated completion in late 2028. The timeline for the second building will span from 2026 to 2029.

Map and Nearby Locations:

50 NW Point Boulevard
Click Map to begin Search

Sites within 15 miles of Aligned: ORD-03

Show SqM
Distance Site About
0.86 miles T5 Chicago II
1.32 miles Prime Elk Grove
1.53 miles CenturyLink: Arlington Heights
1.58 miles CloudHQ Mount Prospect ORD3
2.05 miles STACK CHI01B
STACK INFRASTRUCTURE CHI01B Chicago Data Center is located at 1441 Touhy Avenue, Elk Grove Village, IL, which currently offers 24 MW of critical power and 221,000 square feet of space.
2.12 miles STACK Chicago CHI01
2.18 miles CoreWeave: US Central ORD1
2.69 miles Equinix Chicago CH3
2.71 miles Stream Chicago I
2.73 miles Stream Chicago II
Stream Data Centers' Chicago II data center in Elk Grove Village, Illinois is a 226,000 square foot facility providing 32 MW of critical capacity.
2.75 miles EdgeConneX CHI02
2.83 miles Edgeconnex Chicago Campus
The first Chicago site was leaked to the press in Oct 2016. Microsoft is expected to be the anchor tenant with the site supporting up to 25-30 MWs.
2.84 miles Skybox Chicago I
2.84 miles EdgeConneX CHI01
2.91 miles 1450 E Devon Ave (CH3) DRT
2.94 miles Digital Elk Grove Village Campus
Digital Realty Trust's Chicago campus is massive and is split among 3 buildings. The campus was acquired from Dupont Fabros in September 2017.
2.94 miles ServerCentral CH1
2.94 miles HostPapa CH1
Formerly known as "ColoCrossing CH1"
2.95 miles 2200 Busse Rd (CH1) DRT
2.95 miles Rackspace Elk Grove ORD1
3.03 miles 2299 Busse (CH2) Digital Realty
3.17 miles Cyxtera Elk Grove CH3
Cyxtera's CH3 Elk Grove site is across the street from the Digital Realty Chicago campus (former Dupont Fabros) and close to Equinix CH3.
3.26 miles NTT: 1250 N Arlington Heights (Planned)
In November 2023, NTT Global Data Centers in November paid $27.5 million for the building
3.31 miles NTT: 1200 N Arlington Heights (Planned)
Expansion site acquired in November 2023.
3.51 miles NTT Chicago CH1
RagingWire’s Chicago CH1 Data Center is under construction and in the pre-leasing stage. It will be a 654,000 square foot, 52 megawatt facility on a 19-acre fenced campus near Chicago.
4.15 miles Element Critical CH1
Element Critical acquired the site in January 2019 from Sungard. The facility was previously known as SunGard Wood Dale (711).
4.27 miles Colocation America CH3
4.27 miles DataBank ORD3 Mount Prospect
4.28 miles Element Critical CH2
Element Critical acquired the site in January 2019 from Sungard. The facility was previously known as SunGard Wood Dale (341).
4.68 miles Complete Source Schaumburg
5.48 miles Iron Mountain Chicago
First announced in 2018, the former Hart Schaffner Marx suit factory started construction in 2024.
7.72 miles T5 Northlake IL
8.33 miles Microsoft Hoffman Estates 1
8.34 miles Microsoft Hoffman Estates 2
8.45 miles Microsoft Chicago Northlake
8.73 miles 505 N Railroad Ave - Digital Realty
The Digital Chicago Campus covers 21 acres of land with access to major fiber networks and can support up to 8 MW of IT load at N+1 redundancies.
8.99 miles Aligned Chicago ORD-01
Aligned's ORD-01 data center is a state-of-the-art facility located in Northlake, IL, just outside of downtown Chicago. At full build, Aligned’s Chicago campus covers 520,000 sq. ft. and offers ~72 MW of critical load.
9.02 miles Aligned ORD-02
Aligned's ORD-02 is a data center located in Northlake, IL near downtown Chicago. Part of Aligned's 18.5-acre hyperscale campus, ORD-02 offers exceptional connectivity at the convergence of over 12 metro/long-haul networks. At full build, ORD-02 building will provide 36MW of critical load capacity expandable to ~52 MW.
9.67 miles Digital Chicago Franklin Park Campus on Grand Ave - Digital Realty
Digital Chicago is a master-planned 40-acre campus in the Village of Franklin Park. The campus has 3 existing buildings, totaling 574,994 sqft
9.69 miles 9377 Grand Ave
9.72 miles 9355 Grand Ave
9.77 miles SingleHop Chicago
9.77 miles 9333 Grand Ave (DRT)
9.80 miles Tierpoint Chicago West
12.63 miles Compass Hoffman Estates
12.85 miles LexusNexis Oak Brook
12.85 miles DataBank (ORD4) Oak Brook
12.85 miles XO (Swift Dr)
12.90 miles Digital Fortress: Chicago Lombard
12.90 miles 360TCS-Lombard
12.99 miles CyrusOne Chicago Lombard
9 MW of critical capacity Both a 1.5MW and a 2MW transformer
13.16 miles Server Farm Oak Brook
The campus was originally built as the corporate headquarters of the Chicago Bridge & Iron Company (CB&I).
13.16 miles US Signal Oakbrook
800a 480V 3 phase 450kW diesel generator with 24 hour run time at full load 500kVa UPS capacity with battery backup
13.16 miles XO: (Oak Brook)
13.23 miles NYI Chicago (Oak Brook)
13.96 miles Lumen Broadview
15.31 miles Equinix Chicago CH7
15.31 miles Verizon Chicago (Downers Grove)
16.99 miles Evoque Lisle CH1
17.49 miles New Continuum: 603 Discovery
17.95 miles Cogent Naperville
18.88 miles NetSource Chicago
19.71 miles Metro Edge: Illinois Medical District (IMD)
19.74 miles Lumen Chicago 2
19.85 miles Lumen Chicago 4

Aligned: ORD-03 Data Center Photos

Operating Company

Aligned Data Centers is an infrastructure technology company that offers colocation and build-to-scale solutions to cloud, enterprise, and managed service providers.

In early 2022, Aligned Energy was rebranded to Aligned Data Centers.

22 Facilities Owned
7 Markets Served
779.0 Megawatts
View Company

News

Read More News