Site History

  • 2026-06-15 — Confirmed on Colovore's capacity roadmap (shared with Baxtel) as site ORD01, with one data hall in service December 2026.

Project Profile

  • Developer/operator: Colovore (King Street Capital-backed), building on spec
  • Building: ~45,000 sqft, one data hall (~15,000 sqft)
  • Fully liquid-cooled high-density design
  • Site code: ORD01

Map and Nearby Locations

4235 Meridian Parkway
Colovore Sites
Nearby Facilities

Colovore: Aurora ORD01 Power Growth Over Time

Operational
Construction
Planned
Prospective
In Doubt
Withdrawn
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Colovore: Aurora ORD01

Distance Site About
0.03 miles Colovore: Aurora ORD04
Colovore's fourth Chicago-area facility, a purpose-built liquid-cooled colocation building in Aurora's Meridian Business Campus, adjacent to the company's ORD01 site. Two-hall design with service dates in late 2028 and early 2029.
0.11 miles 4267 Meridian Pkwy: Lincoln Rackhouse
The facility was acquired when Lincoln Rackhouse acquired Bytegrid in 2019.
0.12 miles DataBridge: Aurora, IL
DataBridge Sites is the new name for ESite Systems, a company with two decades of history in the industry.
0.22 miles Colovore: Aurora ORD03
Colovore's third Chicago-area facility, a purpose-built liquid-cooled colocation building in Aurora's Meridian Business Campus. Two-hall design with service dates in 2028.
2.06 miles CyrusOne Chicago Aurora CME
In 2016, CyrusOne acquired the CME data center for $130 million. CME hosts its electronic trading platform CME Globex on site. Globex will continue to be hosted on site as part of the 15-year lease agreement between CyrusOne and CME.
2.09 miles DataCanopy: Chicago, IL
2.11 miles CyrusOne: CHI2 DC2
CyrusOne's CHI2 second building is located at 2805 Diehl Road, Aurora, IL.
2.12 miles CyrusOne: Aurora CHI2
The CyrusOne CHI2 data center is located on 16 acres, 45 minutes southwest of Chicago O'Hare International Airport.
2.45 miles Edged Energy: Chicago ORD03
This facility will be part of Edged Energy's Aurora TechPark in Chicago.
2.50 miles CyrusOne: Aurora III (CHI3)
CyrusOne is developing a pair of new data centers in Aurora, Illinois, a project that will also include the construction of three 350-foot telecommunication towers.
2.51 miles CyrusOne: CHI3 DC2
CyrusOne is developing a pair of new data centers in Aurora, Illinois, a project that will also include the construction of three 350-foot telecommunication towers.
2.58 miles Edged Energy: Chicago ORD02
The new data center campus, Aurora TechPark, will offer facilities built to handle dense AI-driven workloads that are transforming the IT industry.
2.62 miles Edged Energy: Aurora ORD01
The new data center campus, Aurora TechPark, will offer facilities built to handle dense AI-driven workloads that are transforming the IT industry.
2.91 miles NetSource Chicago
3.71 miles Summit: Naperville
4.36 miles Karis: Naperville (INEOS)
Real estate developer Karis Critical is in early-stage exploratory discussions to potentially acquire the 168-acre former BP/INEOS campus at in Naperville, Illinois, within the Suburban Chicago market.
4.41 miles Cogent Naperville
5.74 miles Karis: Naperville, IL
The Naperville City Council officially denied Karis Critical’s proposal for a "boutique data center campus" at 1960 Lucent Lane in January 2026.
6.47 miles Hut 8: Batavia, IL
HPC and cryptomine data center developer Hut 8 is developing a 120,000 sq ft (11,148 sqm) data center nearby Batavia, Kane County.
6.72 miles Centersquare: Lisle CHI1
Centersquare's cloud-enabled Lisle data center is situated approximately 20 miles from O’Hare International airport.
7.28 miles Colovore: West Chicago ORD02
ORD02 is Colovore's second Chicago-area facility, located in West Chicago and extending the company's distributed footprint across the metro. The liquid-cooled, HVDC-ready site is under construction and pre-leasing for edge AI and high-performance colocation workloads.
7.29 miles SBA Edge: 603 Discovery
Former New Continuum site that was acquired in 2019
8.29 miles CloudCenters: Lisle, IL
The Cloud Centers data center project aims to transform the 18 acre former Lockformer superfund site in Lisle, Illinois, into a two story, 256,000 square foot facility.
10.92 miles Connect Data Centers: Chicago
Oppidan is developing Carol Stream’s first data center in Chicago, Illinois.
11.09 miles CyrusOne: Lombard CHI5
9 MW of critical capacity Both a 1.5MW and a 2MW transformer
12.07 miles 360TCS-Lombard
12.07 miles Digital Fortress: Chicago Lombard
12.98 miles Equinix Chicago CH7
13.87 miles Project Cardinal
Pioneer Development, LLC has filed an application for Project Cardinal, a sprawling data center campus planned for over 1,000 acres in Yorkville, Kendall County.
14.16 miles Project Cardinal Expansion
14.21 miles Prologis: Project Steel
Project Steel involves developing a 540-acre campus featuring 24 two-story data center buildings, totaling over 9 million square feet (836,125 sqm), along with three substations.
14.28 miles Prologis: Project Steel Expansion
14.66 miles CyrusOne: Yorkville 8
This data center is a part of CyrusOne's Little Rock Township Campus in Illinois.
14.70 miles CyrusOne: Yorkville 9
This data center is a part of CyrusOne's Little Rock Township Campus in Illinois.
14.81 miles CyrusOne: Yorkville 7
This data center is a part of CyrusOne's Little Rock Township Campus in Illinois.
14.85 miles CyrusOne: Yorkville 6
This data center is a part of CyrusOne's Little Rock Township Campus in Illinois.
14.95 miles CyrusOne: Yorkville 5
This data center is a part of CyrusOne's Little Rock Township Campus in Illinois.
15.04 miles South HubInterested in this information?Contact us
Microsoft acquired 500 acres of land around Eldamain and Corneils roads from three landowners in Plano, Illinois.
15.07 miles CyrusOne: Yorkville 4
This data center is a part of CyrusOne's Little Rock Township Campus in Illinois.
15.12 miles NYI Chicago (Oak Brook)
15.13 miles CyrusOne: Yorkville 3
This data center is a part of CyrusOne's Little Rock Township Campus in Illinois.
15.17 miles CyrusOne: Yorkville 2
This data center is a part of CyrusOne's Little Rock Township Campus in Illinois.
15.26 miles Verizon: (Oak Brook)
15.26 miles US Signal Oakbrook IL01
800a 480V 3 phase 450kW diesel generator with 24 hour run time at full load 500kVa UPS capacity with battery backup
15.26 miles Server Farm Oak Brook
The campus was originally built as the corporate headquarters of the Chicago Bridge & Iron Company (CB&I).
15.30 miles CyrusOne: Yorkville Campus
CyrusOne is building a huge data center campus on 228 acres in Kendall County outside of Chicago, Illinois. The data center campus will have up to nine (9) two-story buildings and a centralized 800,000-square-foot electric substation.
16.10 miles WhiteRose: South Elgin, IL
Whiterose Partners LLC is proposing a 200,000-square-foot data center on nine acres in South Elgin, Illinois, located roughly 40 miles west of Chicago.
16.34 miles LexusNexis Oak Brook
16.34 miles Verizon: Swift Dr
16.34 miles DataBank (ORD4) Oak Brook
16.77 miles Savion: Plano, Illinois
Savion, the company developing the massive 250MW Plano Skies Energy Center solar project in Kendall County, Illinois, is now proposing to add a large data center campus to the development.
17.08 miles Savion: Plano Expansion
18.27 miles Aligned ORD-02
Aligned's ORD-02 is a data center located in Northlake, IL near downtown Chicago. Part of Aligned's 18.5-acre hyperscale campus.
18.33 miles Aligned Chicago ORD-01
Aligned's ORD-01 data center is a state-of-the-art facility located in Northlake, IL, just outside of downtown Chicago. At full build, Aligned’s Chicago campus covers 520,000 sq. ft. and offers ~ 100 MW of critical load.
18.35 miles NTT: CH3
This facility is a part of NTT's Chicago data center campus in Illinois.
18.43 miles NTT Chicago CH1
NTT acquired its Chicago site in 2018 through its RagingWire subsidiary. Launched in 2021, the first two-story data center, CH1, spans 126,000 sq ft (11,705 sqm) of data floor space.
18.49 miles NTT: CH2
This facility is a part of NTT's Chicago data center campus in Illinois.
18.53 miles Plaza PlusInterested in this information?Contact us
18.57 miles NTT: Chicago CH4
NTT has acquired two office buildings in Chicago, Illinois, and plans to replace them with data centers.
18.60 miles NTT: Chicago CH5
In November 2023, NTT Global Data Centers in November paid $27.5 million for the building.
18.76 miles 505 N Railroad Ave - Digital Realty
The Digital Chicago Campus covers 21 acres of land with access to major fiber networks and can support up to 8 MW of IT load at N+1 redundancies.
18.86 miles Nexstar: Elk Grove
As of January 2026, the Nexstar/WGN data center project has expanded from its original 35-acre, three-building plan to a four-building campus utilizing a larger portion of the 102-acre transmitter site.
18.88 miles Nexstar: Elk Grove Bldg 2
This facility is part of Nexstar's Elk Grove data center campus in Illinois.
18.94 miles Nexstar: Elk Grove Bldg 3
This facility is part of Nexstar's Elk Grove data center campus in Illinois.
18.97 miles Nexstar: Elk Grove Bldg 4
This facility is part of Nexstar's Elk Grove data center campus in Illinois.
18.99 miles Element Critical CH2
Element Critical acquired the site in January 2019 from Sungard. The facility was previously known as SunGard Wood Dale (341).
19.15 miles T5: Chicago lll
T5@Chicago III will be build-to-suit, with the company spending more than $500 million to develop a three-story, 250,000 sq ft facility for multi-tenant or single-tenant operations.
19.17 miles Element Critical CH1
Element Critical acquired the site in January 2019 from Sungard. The facility was previously known as SunGard Wood Dale (711).
19.35 miles Carrier-Neutral Data CenterInterested in this information?Contact us
CyrusOne is developing a 62-acre campus in Wood Dale, Illinois, with plans to construct six data center buildings encompassing approximately 1.4 million square feet.
19.41 miles Lumen Broadview
19.75 miles DigiCo: Chicago
The facility sits on a ten-acre site and will serve as a flagship asset in HMC Capital's newly established DigiCo Infrastructure REIT.

Operating Company

Operated by:

Colovore is a Bay Area's colocation provider

0
Facilities
0
Markets

News See all

Read Colovore To Develop a 9MW Liquid-Cooled Data center in Santa Clara
Colovore To Develop a 9MW Liquid-Cooled Data center in Santa Clara

Colovore To Develop a 9MW Liquid-Cooled Data center in Santa Clara

November 04, 2022 Colovore

Colovore has announced its plans to build a new data center in Santa Clara, California. The US data center company revealed that it would be developing its second facility in the city at 3060 Raymond Street. The data center is located adjacent to its existing facility at 1101 Space Park Drive....

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts

Ready to Level up Your
Data Center Strategy?