The Nashville data center market is located in the state of Tennessee within Americas. Nashville has 20 facilities with 2,160,440 sqft and 168 megawatts.
The top providers in Nashville are Meta (4 sites) and Csquare with 1 facility . The most popular facilities are Lumen Nashville 2 and Meta: Gallatin 5.
| Name | Company | Size | Status | Type | |
|---|---|---|---|---|---|
|
Lumen Nashville 2 | Lumen Technologies | Extra Small | Operational | Carrier |
|
North Park | Meta | Large | Construction | Hyperscale |
|
Lumen Nashville 1 | Lumen Technologies | Extra Small | Operational | Carrier |
|
Tierpoint Nashville NSH | TierPoint | Extra Small | Operational | Carrier-Neutral |
|
H5 Nashville | H5 Data Centers | Small | Operational | Carrier-Neutral |
|
Flexential Cool Springs | Flexential | Small | Operational | Carrier-Neutral |
|
RadiusDC: Nashville, TN | RadiusDC | Small | Construction | Carrier-Neutral |
|
365 Nashville (NA1) | 365 Data Centers | Extra Small | Operational | Carrier-Neutral |
|
Flexential Franklin TN | Flexential | Small | Operational | Carrier-Neutral |
|
Verizon: 101 Molloy | Verizon Enterprise | Extra Small | Operational | Carrier |
|
Flexential Brentwood | Flexential | Extra Small | Operational | Carrier-Neutral |
|
Centersquare: Gallatin (NAS) | Csquare | Small | Land Bank, Operational | Carrier-Neutral |
|
Compass Franklin I | Compass Datacenters | Small | Operational | Carrier-Neutral |
|
Point | Meta | Medium | Planned | Hyperscale |
|
North Hub | Meta | Large | Operational | Hyperscale |
|
Mapletree: 402 Franklin | Mapletree Redwood Data Centre Trust | Small | Operational | Real Estate |
|
Nexus Group Nashville | The Nexus Group | Operational | Carrier-Neutral | |
|
Plaza Ultra | Meta | Large | Operational | Hyperscale |
|
Station Three | Meta | Large | Operational | Hyperscale |
|
EdgeConneX Nashville | EdgeConneX | Extra Small | Operational | Carrier-Neutral |
| Location | Total SqFt | Gross SqFt | Power (MW) |
|---|---|---|---|
| Park Beta |
485,000 SqFt |
NN Request Dataset | |
| Global Hub |
500,000 SqFt |
NN Request Dataset | |
| Central |
485,000 SqFt |
NN Request Dataset | |
| Mapletree: 402 Franklin |
347,515 SqFt |
NN Request Dataset | |
| Compass Franklin I | NN Request Dataset |
| Location | Building SqFt | Power (MW) | Estimated Launch |
|---|---|---|---|
| Prime | 278,000 SqFt | 40 Megawatts | Q1 2027 |
| RadiusDC: Nashville, TN | 102,500 SqFt | 12 Megawatts | Q4 2026 |
| Centersquare: Gallatin (NAS) | SqFt | 0 Megawatts | Q1 2026 |