CyrusOne: DFW8

Latest Podcast 9501 Asphalt Dr
Under Construction
New facility under construction
Operated by:

CyrusOne: DFW8

Short Code: DFW8
Year Planned: 2027
Utility Provider: Oncor

DFW8 is the second building under way on CyrusOne's Fort Worth campus on Asphalt Drive, about seven miles northwest of downtown Fort Worth, beside DFW7. The single-story data center has a two-story office component. CyrusOne scheduled core and shell construction from mid-2025 to late 2026, and data hall fit-out, including generators in a service yard, through October 2027.

Site History

  • 2026: CyrusOne files the data hall fit-out.
  • July 2025: Construction starts.

Map and Nearby Locations

9501 Asphalt Dr
CyrusOne Sites
Nearby Facilities

CyrusOne: DFW8 Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of CyrusOne: DFW8

Distance Site About
0.15 miles CyrusOne: DFW7
DFW7 is the first building on CyrusOne's Fort Worth campus on Asphalt Drive, on land bought from energy developer Eolian beside its Chisholm Grid battery plant.
0.23 miles CyrusOne: Fort Worth Expansion
Later phases of CyrusOne's Fort Worth campus on Asphalt Drive, planned with energy developer Eolian beyond the DFW7 and DFW8 buildings.
0.45 miles ACS: Hicks Field DFW12
ACS DFW12 is a planned two-story data center of about 283,000 sq ft on ACS Group's Hicks Field campus in far north Fort Worth, Texas.
0.53 miles ACS: Hicks Field DFW13
ACS DFW13 is a planned two-story data center of about 283,000 sq ft at 10059 Hicks Field Rd on ACS Group's Hicks Field campus in far north Fort Worth, Texas.
0.59 miles ACS: Hicks Field Expansion
0.74 miles ACS: Hicks Field DFW11
ACS DFW11 is the first building of ACS Group's Hicks Field data center campus in far north Fort Worth, Texas: a two-story facility of about 251,000 sq ft.
8.73 miles Colovore: Fort Worth DFW02
Colovore's second Dallas-market facility, a purpose-built liquid-cooled colocation building on Heritage Parkway in north Fort Worth. Four-hall design following Colovore's standard high-density spec-build template, with service dates running late 2027 through 2028.
9.62 miles QTS: FTW1 Expansion
QTS is expanding its Fort Worth data center campus for the third time with a $300 million, 147,946-square-foot addition at 14100 Park Vista Boulevard.
9.65 miles Prime CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.75 miles Tierpoint Fort Worth
TierPoint's Dallas-Fort Worth data center occupies the former Alliance Gateway / AIG facility on Independence Parkway in north Fort Worth. The site is built for high-density AI and HPC workloads, with direct-to-chip liquid cooling in production alongside air and chilled-water cooling. TierPoint is expanding the utility supply to the site and has room for further phases along the existing building line.
9.77 miles QTS: FTW1-DC2
FTW1-DC2 is the second building on QTS's Fort Worth campus near AllianceTexas, a two-story, $220 million data center completed in 2026.
9.78 miles STACK Fort Worth Alliance
STACK's expansion Alliance campus in Fort Worth
9.83 miles QTS: FTW1-DC1
FTW1-DC1 is the original building on QTS's Fort Worth campus near AllianceTexas, a former Health Care Service Corporation data center that QTS bought in 2017.
10.05 miles PowerHouse: Circle T Campus
PowerHouse Data Centers is expanding its Texas footprint with plans for the Circle T Data Center, a campus spanning nearly 88 acres in Westlake, just north of Fort Worth.
10.13 miles TowerInterested in this information?Contact us
10.61 miles Campus MaxInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
10.71 miles Lumen For Worth 3
10.72 miles Carrier-Neutral Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
10.80 miles Lumen Fort Worth 2
10.85 miles LOGIX Fort Worth
In 2018 LOGIX Communications acquired Alpheus Communications and this site.
11.19 miles Lumen Fort Worth 1
11.22 miles Citigroup Fort Worth
12.67 miles Prime CampusInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
12.76 miles CoreInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
15.60 miles Edged Energy: Ft. Worth DFW02
Edged is developing a two-building, 196 MW data center campus on 186 acres in Fort Worth's Veale Ranch area, at I-20 and Chapin School Road.
15.75 miles Edged Energy: DFW02 Expansion
Second building and second phase of Edged's 186-acre data center campus in Fort Worth's Veale Ranch area, at I-20 and Chapin School Road.
16.03 miles Prime: DFW04-03
Prime Data Centers is building a $1.6 billion campus near Benbrook. The project includes three, two-story structures being built near Aledo and Chapin School roads. The site is slated for completion by January 2026.
16.34 miles Prime: DFW04-02
Prime Data Centers is building a $1.6 billion campus near Benbrook. The project includes three, two-story structures being built near Aledo and Chapin School roads. The site is slated for completion by January 2026.
16.43 miles Prime: DFW04-01
Prime Data Centers is building a $1.6 billion campus near Benbrook. The project includes three, two-story structures being built near Aledo and Chapin School roads. The site is slated for completion by 2026.
16.75 miles Rackspace Grapevine DFW1
17.65 miles Novartis
18.88 miles 5CDC: Dallas DFW01
The facility encompasses eight data halls (PODs) optimized to accommodate average densities of over 400W per square foot.
19.23 miles Black Mountain: Fort Worth, TX
Black Mountain has filed to rezone 141 acres at the intersection of Lon Stephenson Road and Forest Hill Drive to develop a data center.

Operating Company

Operated by:

CyrusOne is a data center owner, operator, and developer that manages more than 50 facilities, with its footprint concentrated in the U.S. and Europe. The company is based in Dallas and was taken private in March 2022 by funds managed by KKR and Global Infrastructure Partners in a transaction valued at approximately 15 billion dollars including debt.

Its portfolio centers on hyperscale and enterprise colocation across multi-building campuses. CyrusOne has also pursued international growth initiatives alongside its core North American and European markets.

CyrusOne History:

  • March 2022: Taken private by funds managed by KKR and Global Infrastructure Partners in an approximately 15 billion dollar all-cash transaction including debt.
  • July 2015: Acquired Cervalis, adding four data centers and two disaster recovery sites in the New York metro.
  • July 2014: Acquired Cervalis
  • January 2013: Completed initial public offering on NASDAQ as a carve-out of Cincinnati Bell’s data center business.
  • June 2010: Cincinnati Bell acquired CyrusOne for approximately 525 million dollars.
  • 2000: Founded by David Ferdman.
0
Facilities
0
Markets

News See all

Read Fireworks Reserves $94.4M Nvidia B300 Capacity at Forum Edge AI Dallas Site
Fireworks has reserved three years of Nvidia B300 GPU capacity at Forum Edge AI's powered data center in Dallas. The 36-month agreement carries a combined total contract value of approximately $94....

Fireworks Reserves $94.4M Nvidia B300 Capacity at Forum Edge AI Dallas Site

October 26, 2026 Dallas

Fireworks has reserved three years of Nvidia B300 GPU capacity at Forum Edge AI's powered data center in Dallas. The 36-month agreement carries a combined total contract value of approximately $94.4 million, Forum Edge AI said on Oct. 26, reflecting GPU capacity and associated CPU management...

Read more
Read 2026 Is the Year Texas Passes Virginia in Data Center Capacity
[Texas](https://baxtel.com/data-center/texas) now has more data center capacity operating and under construction than [Virginia](https://baxtel.com/data-center/virginia). Baxtel tracks 28.3 GW buil...

2026 Is the Year Texas Passes Virginia in Data Center Capacity

October 13, 2026 Texas

Texas now has more data center capacity operating and under construction than Virginia. Baxtel tracks 28.3 GW built or building in Texas, against 17.8 GW in Virginia. On capacity already online, Virginia still leads, 12.3 GW to 11.1 GW. If projects scheduled for this year deliver on time, Texas...

Read more
Read PowerHouse Files Plans for 300MW Data Center Campus Near Dallas-Fort Worth
PowerHouse Data Centers is planning a new campus near Fort Worth, Texas. First reported by NBC, engineering firm Kimley-Horn has filed plans for a data center on about 88 acres in Westlake, north o...

PowerHouse Files Plans for 300MW Data Center Campus Near Dallas-Fort Worth

August 07, 2026 Dallas

PowerHouse Data Centers is planning a new campus near Fort Worth, Texas. First reported by NBC, engineering firm Kimley-Horn has filed plans for a data center on about 88 acres in Westlake, north of Fort Worth. The proposed site is at 13580 Denton Highway, near US Highway 377 and Westport...

Read more
Read CyrusOne Files Plans for Three-Building, $1.5bn Data Center Campus in Fairfield, Texas
CyrusOne has filed plans for three buildings at a new data center campus in Fairfield, Texas, located adjacent to Calpine’s Freestone natural gas power plant. The project, on FM 488 in Freestone Co...

CyrusOne Files Plans for Three-Building, $1.5bn Data Center Campus in Fairfield, Texas

August 01, 2026 CyrusOne

CyrusOne has filed plans for three buildings at a new data center campus in Fairfield, Texas, located adjacent to Calpine’s Freestone natural gas power plant. The project, on FM 488 in Freestone County, about 90 miles (144.8km) south of Dallas, is part of a 760MW data center development being...

Read more
Read CyrusOne Begins Construction on 380MW Data Center in Texas
CyrusOne has begun construction on a new data center campus in Texas, breaking ground last week in Freestone County, about 90 miles (144 km) south of Dallas. Full details of the planned development...

CyrusOne Begins Construction on 380MW Data Center in Texas

June 08, 2026 CyrusOne

CyrusOne has begun construction on a new data center campus in Texas, breaking ground last week in Freestone County, about 90 miles (144 km) south of Dallas. Full details of the planned development have not yet been disclosed. CyrusOne has partnered with Constellation on a 380MW agreement to...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.