CyrusOne and Kansai Electric Power Company have [topped out OSK1](https://www.facebook.com/CyrusOne/posts/cyrusone-keps-first-data-center-in-japan-designed-to-deliver-48-mw-of-it-capacit/1631891085...

CyrusOne and KEP Top Out 48MW OSK1 Data Center in Japan

Abdul-Rahman Oladimeji

Abdul-Rahman Oladimeji

November 20, 2026

CyrusOne and Kansai Electric Power Company have topped out OSK1, the first data center under their Japanese joint venture, at a planned 48MW of IT capacity. CyrusOne and KEP marked the structural completion this week with a traditional Jōtōshiki ceremony. CyrusOne KEP, the 50:50 joint venture the two formed in 2023, develops and will operate the buildindatacenterdynamics.comFeatured: Architectural rendering of the 48MW CyrusOne KEP OSK1 data center facility in Keihanna, Kyoto Prefecture.g. No customer for the capacity has been named.

OSK1 occupies a 19,693 sqm plot in Seika Town in Kyoto Prefecture, inside the Keihanna Availability Zone that CyrusOne markets as its Osaka site. The four-story building is designed around six 8MW data halls and 11,562 sqm of technical space. KEPCO's project filing lists 70MW of total incoming power against 48MW of IT capacity, and CyrusOne's project page describes a 70MVA supply at 77kV from a new grid connection and a dedicated substation.

Gold and silver bolts were driven into the final steel beam at the ceremony, according to Data Center Dynamics, which reported ground was broken on the site in September 2024. CyrusOne said cumulative work hours across the building, mechanical, and electrical trades passed 330,000 as of Aug. 25.

"We are delighted to celebrate today's topping out," said Takashi Mishima, co-CEO of CyrusOne KEP. Tetsuichi Shoda of Kajima Corporation described OSK1 as "important infrastructure supporting the advancement of digitalization and AI utilization in society." CyrusOne's announcement names Kajima, Nikken Sekkei, Sekisui House, Kinden and Shinryo among the project partners.

CyrusOne and KEPCO announced the joint venture in May 2023 with plans to invest at least ¥1 trillion ($7 billion) over the next decade and reach 900MW of total incoming power, of which 600MW would be IT capacity. Baxtel covered the venture at launch. KKR owns CyrusOne, which operates or is developing more than 40 data centers in the United States and Europe.

Baxtel tracks 76 data center facilities in Osaka, 12 of them under construction, with NTT the largest provider at 8 sites and KDDI's Sakai site the largest at 50MW.

The first 16MW at OSK1 is scheduled to come online in the first quarter of 2028.