2.55 miles
|
Ridge UltraInterested in this information?Contact us
|
Amazon Web Services' plans to build a 220,000-square-foot data center at the intersection of Blackwell Road and Lee Highway in Warrenton.
|
|
6.14 miles
|
Vint Hill Corners
|
The Vint Hill Corners data center campus proposal, submitted by a company called Vint Hill Corners LLC, which owns about 80 acres on Brookside Parkway, seeks to develop two one-story data centers on about 50 acres of property at 4295 Aiken Drive in Vint Hill.
|
|
6.66 miles
|
OVH: Vint Hill Bldg 2
|
OVHcloud currently plans an expansion of its existing data center, which currently calls the Vint Hill Business Park home.
|
|
6.74 miles
|
OVH US East Vint Hill
|
This facility, situated on the grounds of a former Army base in Vint Hill, became OVHcloud's first U.S. data center and officially began operations in 2017.
|
|
7.06 miles
|
CyrusOne: Vint Hill
|
CyrusOne LLC, a data center developer and operator, submitted its first site plan to the county in March for an 870,000-square-foot data center campus.
|
|
8.14 miles
|
Headwaters: Catlett, VA
|
The Headwaters Site Development was a proposed $400 million data center project planned for a 67-acre site in the Catlett Station area of Fauquier County, Virginia.
|
|
10.02 miles
|
Convergent Technology Park
|
Convergent VA has submitted revised conceptual plans for the Convergent Technology Park in Remington, Fauquier County, Virginia.
|
|
10.04 miles
|
Data Center Edge District
|
The House family has submitted an application to modify their property's designation in the county's Comprehensive Plan from agricultural estate to the proposed Data Center Edge District (DCED).
|
|
10.20 miles
|
SAMX data center campus
|
SAMX Data LLC submitted an application in October 2023 to rezone approximately 55.26 acres of property at 11825 Remington Road.
|
|
10.64 miles
|
PointOne: Remington Expansion
|
|
|
10.79 miles
|
PointOne: Remington Technology Park
|
In March 2018, Alberta-based PointOne Holdings Inc. received approval to rezone 234 acres on Lucky Hill Road, Remington, for a data center project.
|
|
10.79 miles
|
Point UltraInterested in this information?Contact us
|
|
|
10.86 miles
|
Valley PrimeInterested in this information?Contact us
|
|
|
10.92 miles
|
EdgeInterested in this information?Contact us
|
|
|
10.96 miles
|
CloudInterested in this information?Contact us
|
|
|
11.07 miles
|
Gigaland: Remington, VA
|
Gigaland has scrapped its initial plans for an 800MW data center campus in Fauquier County, Virginia, after facing local opposition. However, the company now plans to propose a smaller project for the site.
|
|
11.16 miles
|
Gardner Property Project
|
A developer files plans for an 82-acre data center campus on the site of the Hillwood Camping Park in Gainesville.
|
|
11.27 miles
|
Prime PointInterested in this information?Contact us
|
The Village Place Technology Park project comprises four two-story data centers, ranging from 114,330 sq ft to 132,750 sq ft, built on the site.
|
|
11.32 miles
|
Plaza ThreeInterested in this information?Contact us
|
The Village Place Technology Park project comprises four two-story data centers, ranging from 114,330 sq ft to 132,750 sq ft, built on the site.
|
|
11.33 miles
|
CoreInterested in this information?Contact us
|
The Village Place Technology Park project comprises four two-story data centers, ranging from 114,330 sq ft to 132,750 sq ft, built on the site.
|
|
11.33 miles
|
Prime StationInterested in this information?Contact us
|
The Village Place Technology Park project comprises four two-story data centers, ranging from 114,330 sq ft to 132,750 sq ft, built on the site.
|
|
11.36 miles
|
JK Land: Hunter Trust
|
JK Land Holdings has submitted a site plan for a property within the Data Center Overlay, allowing for buildings up to 75 feet in height.
|
|
11.36 miles
|
8217 Linton Hall (VA4) Digital Realty
|
|
|
11.59 miles
|
NTT: VA13
|
VA13 will be the fourth building of NTT's Gainesville Data Center Campus. The campus is named "Grove at Gainesville" or "NTT VA10" in some of the planning documents.
|
|
11.63 miles
|
John Marshall Commons Tech Park
|
CTP-II LLC plans to rezone 22.72 acres at the intersection of Catharpin Road and John Marshall Highway from business and light industrial to office mid-rise to construct the data center.
|
|
11.63 miles
|
NTT: VA12
|
VA12 will be the third building of NTT's Gainesville Data Center Campus. The site is named "Grove at Gainesville" or "NTT VA10" in some of the planning documents.
|
|
11.66 miles
|
NTT: VA11
|
VA10 DC2 will be the second building of NTT's Gainesville Data Center Campus. The campus is named "Grove at Gainesville" or "NTT VA10" in some of the planning documents.
|
|
11.68 miles
|
NTT Gainesville VA Campus
|
NTT is building four (4) two-story data centers and associated infrastructure on around 104 acres. The site is named "Grove at Gainesville" or "NTT VA10" in some of the planning documents.
|
|
11.80 miles
|
Yondr: Bristow Bldg 2
|
Yondr Group's Bristow Data Center Campus is located at 12981 Rollins Ford Road, Bristow, VA.
|
|
11.93 miles
|
Global TowerInterested in this information?Contact us
|
Amazon Data Services acquired the 269-acre site of the planned Devlin Technology Park in Prince William County, Bristow, in late 2025.
|
|
12.00 miles
|
Yondr Bristow Campus
|
Yondr Group's Bristow Data Center Campus is located at 12981 Rollins Ford Rd, Bristow. The two-building campus is set to deliver critical cloud capacity in one of the world’s largest data center markets.
|
|
12.02 miles
|
Ridge BetaInterested in this information?Contact us
|
|
|
12.44 miles
|
Point OneInterested in this information?Contact us
|
Microsoft Corp. recently acquired 124 acres across two parcels at 13490 University Blvd. and 5941 Wellington Road. University Boulevard site is seeking an allowance for up to nearly 4 million square feet of data centers and a new electric substation.
|
|
12.50 miles
|
Prime ParkInterested in this information?Contact us
|
AWS has proposed the site for a 2.2 million sqft data center campus on approximately 117 acres.
|
|
12.54 miles
|
Metro CampusInterested in this information?Contact us
|
|
|
12.58 miles
|
TowerInterested in this information?Contact us
|
|
|
12.58 miles
|
North ParkInterested in this information?Contact us
|
This planned facility is part of Google's Bristow Campus in Prince William County, Virginia.
|
|
12.61 miles
|
Metro TowerInterested in this information?Contact us
|
|
|
12.63 miles
|
South TowerInterested in this information?Contact us
|
|
|
12.66 miles
|
Plaza OneInterested in this information?Contact us
|
Microsoft Corp. recently acquired 124 acres across two parcels at 13490 University Blvd. and 5941 Wellington Road. University Boulevard site is seeking an allowance for up to nearly 4 million square feet of data centers and a new electric substation.
|
|
12.71 miles
|
Center AlphaInterested in this information?Contact us
|
|
|
12.73 miles
|
Central ParkInterested in this information?Contact us
|
Microsoft Corporation owns 83 acres of land located at 8008 Devlin Road in Bristow, Prince William County, Virginia, on which it is developing a multi-phase data center campus.
|
|
12.80 miles
|
MaxInterested in this information?Contact us
|
This planned facility is part of Google's Bristow Campus in Prince William County, Virginia.
|
|
12.84 miles
|
CorScale: Gainesville 2
|
In Q1 2024, US data center firm CorScale has started work on the second facility at its Gainesville campus in Virginia's Prince William County.
|
|
12.86 miles
|
Plaza UltraInterested in this information?Contact us
|
The campus will include four data center buildings, an electric substation, auxiliary equipment structures, and a small administrative building.
|
|
12.92 miles
|
CorScale: Gainesville 3
|
The data center building 3 will be a part of CorScale's Gainesville Crossing campus located at 13760 University Blvd, Gainesville.
|
|
12.96 miles
|
Stack: Bristow Campus (NVA02K)
|
Stack Infrastructure planned to build a large-scale data center campus on a 58-acre site in Bristow, but Prince William County supervisors voted to reject STACK Infrastructure’s proposed Bristow Campus.
|
|
12.97 miles
|
Metro TowerInterested in this information?Contact us
|
This planned facility is part of Google's Bristow Campus in Prince William County, Virginia.
|
|
12.98 miles
|
Corscale: Gainesville Crossing
|
The first building of this multi-phase development was originally scheduled to open in 2023 but came online in 2025. It is a two-story building with eight (8) data halls and office space totaling approximately 483,000 square feet.
|
|
13.01 miles
|
Stack: NVA02H
|
This facility is part of Stack's NVA02 Campus in Northern Virginia.
|
|
13.10 miles
|
Stack: NVA02J
|
This facility is part of Stack's NVA02 Campus in Northern Virginia.
|
|
13.13 miles
|
Station UltraInterested in this information?Contact us
|
Amazon Data Services has expanded its footprint in Northern Virginia’s hyper-competitive data center corridor with a $120 million acquisition of 44 contiguous acres in Manassas, Prince William County.
|
|
13.13 miles
|
Stack: NVA02I
|
This facility is part of Stack's NVA02 Campus in Northern Virginia.
|
|
13.16 miles
|
CorScale: Gainesville 4
|
The data center building 4 will be a part of CorScale's Gainesville Crossing campus located at 13760 University Blvd, Gainesville. The two-story data center will offer 200,000 sq ft of data hall space.
|
|
13.17 miles
|
Stack: Bristow 2 (NVA02L)
|
Prince William County supervisors have voted to reject STACK Infrastructure’s proposal for the Bristow Campus, a large-scale data center project.
|
|
13.19 miles
|
Hub GammaInterested in this information?Contact us
|
|
|
13.23 miles
|
Plaza ProInterested in this information?Contact us
|
|
|
13.23 miles
|
CorScale: Gainesville 5
|
The data center building 4 will be a part of CorScale's Gainesville Crossing campus located at 13760 University Blvd, Gainesville. The two-story data center will offer 200,000 sq ft of data hall space.
|
|
13.30 miles
|
BlackChamber: Gainesville, VA
|
The Merrifield Garden Center in Gainesville, VA (Prince William County), has been sold for $160M to data center developer BlackChamber Group.
|
|
13.43 miles
|
Stack: NVA02E
|
STACK Infrastructure's NVA02E, Building E of NVA02 Campus, is located at Hornbaker Road in Manassas. The data center spans a substantial footprint of 280,000 square feet, encompassing both critical and non-critical spaces.
|
|
13.44 miles
|
Stack: NVA02F
|
This facility is part of Stack's NVA02 Campus in Northern Virginia.
|
|
13.52 miles
|
Stack: NVA02G
|
This facility is part of Stack's NVA02 Campus in Northern Virginia.
|
|
13.55 miles
|
Central ParkInterested in this information?Contact us
|
A proposed 389,425 square-foot data center development is planned for the Brentsville Magisterial District.
|
|
13.55 miles
|
Stack: NVA02D
|
STACK Infrastructure NVA02D, Building D of NVA02 Campus, is located at Hornbaker Road in Manassas.
|
|
13.64 miles
|
Stack: Northern Virginia, NVA02
|
Data center firm Stack Infrastructure isData center firm STACK Infrastructure's NVA02 campus in Prince William County will house at least seven data centers, offering 420MW of power capacity for scalability.
|
|
13.68 miles
|
Stack: NVA02B
|
STACK Infrastructure is constructing a new data center facility at 9750 Hornbaker Road, Building B in Manassas with a substantial footprint of 227,000 square feet.
|
|
13.71 miles
|
Stack: NVA02C
|
The facility has a substantial footprint of 15,000 square feet, encompassing both critical and non-critical spaces.
|
|
13.71 miles
|
Global StationInterested in this information?Contact us
|
|
|
13.75 miles
|
Opus Interactive Manassas
|
|
|
13.76 miles
|
Iron Mountain Northern Virginia (Manassas)
|
Announced in March 2016, Iron Mountain’s Manassas data center in Prince William County will include four buildings totaling 915,000 square feet and 60 MW of power. The campus is 83 acres.
VA-1, the first building on the campus, is a 165,000Sqft facility with 12.4 MW of power.
|
|
13.78 miles
|
Iron Mountain: VA-3
|
Iron Mountain continues to grow it's Virginia campus. VA3 is the third and largest building on the Virginia campus over 165,000 sqft and includes two 48 MW data center halls at 30,000 SF each.
|
|
13.78 miles
|
Iron Mountain VA-2
|
|
|
13.81 miles
|
Evoswitch USA WDC 1
|
|
|
13.81 miles
|
CloudHQ Manassas Hornbaker
|
Built in 2010, The site was previously known as COPT-6. There is a 100,000 SF raised floor data area, divisible in bays of 6,250 SF
|
|
13.81 miles
|
VAZATA Northern Virginia (NoVa One)
|
|
|
13.81 miles
|
Park BetaInterested in this information?Contact us
|
|
|
13.82 miles
|
ThreeInterested in this information?Contact us
|
|
|
13.83 miles
|
Iron Mountain: VA-8
|
Iron Mountain Data Center seeks to expand its Manassas campus with a new two-story building totaling 165,428 square feet (15,369 square meters).
|
|
13.88 miles
|
Iron Mountain: VA-6
|
VA-6 is one of nine planned data centers situated on a 142-acre, highly secure campus that provides 2,100,000 sq. ft. of highly efficient, green colocation space. VA-6 offers 230,000 gross sq. ft. of space.
|
|
13.89 miles
|
PlazaInterested in this information?Contact us
|
|
|
13.91 miles
|
Iron Mountain: VA-4
|
Iron Mountain continues to grow it's Virginia campus at 11560 Hayden Rd, Manassas. VA4 is the fourth building on the Virginia campus over 165,000 sqft of space. The facility will house 32 MW of critical load on completion.
|
|
13.94 miles
|
Iron Mountain: VA-5
|
Iron Mountain continues to grow it's Virginia campus at 11560 Hayden Rd, Manassas. VA5 is the fifth building on the Virginia campus over 165,000 sqft of space. The facility will house 40 MW of critical load on completion.
|
|
14.02 miles
|
Global TowerInterested in this information?Contact us
|
|
|
14.06 miles
|
Iron Mountain: VA-7
|
The Iron Mountain VA-7 data center is a $100 million project housed in a single building (also known as Iron Mountain DC2) on a 24-acre plot.
|
|
14.08 miles
|
Ridge AlphaInterested in this information?Contact us
|
|
|
14.08 miles
|
Metro RidgeInterested in this information?Contact us
|
|
|
14.12 miles
|
EastInterested in this information?Contact us
|
|
|
14.13 miles
|
Hub ThreeInterested in this information?Contact us
|
|
|
14.16 miles
|
OneInterested in this information?Contact us
|
|
|
14.19 miles
|
Ridge PrimeInterested in this information?Contact us
|
|
|
14.26 miles
|
Compass: Prince William Digital Gateway Campus
|
A judicial ruling voided the massive Digital Gateway data center project, but the developers and county are appealing the decision, leaving the 1.7-gigawatt plan in doubt.
|
|
14.29 miles
|
JK Land: Comcast Center
|
The property, which spans 17 acres, features an existing 108,000-square-foot building that previously served as both office space and a data center.
|
|
14.42 miles
|
ValleyInterested in this information?Contact us
|
Amazon IAD-104 data center is located at 9680 Innovation Dr, Manassas, VA 20110, USA.
|
|
14.46 miles
|
Center GammaInterested in this information?Contact us
|
Amazon has acquired a plot of government-owned land, approximately 20 acres on Wakeman Drive, Manassas, in Virginia's Prince William County for a new data center.
|
|
14.46 miles
|
South RidgeInterested in this information?Contact us
|
|
|
14.48 miles
|
Iron Mountain: Manassas Point
|
Iron Mountain plans to build two data center buildings and a new electricity substation on a 40-acre data center-zoned property in Manassas, VA.
|
|
14.49 miles
|
PlazaInterested in this information?Contact us
|
|
|
14.52 miles
|
Valley ThreeInterested in this information?Contact us
|
Amazon IAD-105 data center is located at 9700 Innovation Dr, Manassas, VA 20110, USA.
|
|
14.53 miles
|
EdgeInterested in this information?Contact us
|
Amazon IAD-106 data center is located at 9720 Innovation Dr, Manassas, VA 20110, USA.
|
|
14.53 miles
|
Valley AlphaInterested in this information?Contact us
|
Amazon paid $152 million to acquire roughly 140 acres across four parcels in Manassas. One pair of parcels comprises around 27 acres at 7151 and 7350 Century Park Drive.
|
|
14.56 miles
|
Point BetaInterested in this information?Contact us
|
Amazon paid $152 million to acquire roughly 140 acres across four parcels in Manassas. One pair of parcels comprises around 27 acres at 7151 and 7350 Century Park Drive.
|
|
14.60 miles
|
Global RidgeInterested in this information?Contact us
|
Amazon is building another data center in it's Innovation Drive campus.
|
|
14.61 miles
|
Central HubInterested in this information?Contact us
|
|
|
14.64 miles
|
CloudHQ: MDC3
|
CloudHQ is constructing a three-building data center campus in the heart of the Manassas data center market, just south of the intersection of Routes 28 and 234.
|
|
14.70 miles
|
QTS Manassas DC5
|
This facility is part of QTS Data Center Campus in Manassas.
|
|
14.72 miles
|
StationInterested in this information?Contact us
|
|
|
14.72 miles
|
CloudHQ: MDC2
|
CloudHQ is constructing a three-building data center campus in the heart of the Manassas data center market, just south of the intersection of Routes 28 and 234.
|
|
14.73 miles
|
QTS: Manassas DC4
|
|
|
14.74 miles
|
Hub TwoInterested in this information?Contact us
|
Amazon acquired the 10 acres property in June of 2018. Development plans are unknown
|
|
14.77 miles
|
Stack: Northern Virginia NVA05
|
STACK Infrastructure's NVA05A data center offers 36MW of flexible capacity within its 262,000 sq. ft. building in Northern Virginia.
|
|
14.80 miles
|
Plaza OneInterested in this information?Contact us
|
|
|
14.81 miles
|
CloudHQ: Manassas MDC Campus
|
CloudHQ is constructing a three-building data center campus in the heart of the Manassas data center market, just south of the intersection of Routes 28 and 234.
|
|
14.85 miles
|
QTS Manassas DC6
|
This facility is part of QTS Manassas 1 Campus in Virginia.
|
|
14.87 miles
|
Digital Realty: IAD50
|
|
|
14.87 miles
|
QTS Manassas DC1
|
QTS is building a 100+ acre campus in Manassas, Virginia. QTS bought the property, at 10680 University Blvd. adjacent to its existing data center, for $5 million in 2018.
|
|
14.90 miles
|
Digital Realty: IAD51
|
|
|
14.91 miles
|
Stack: NVA05D
|
The purpose-built facility will have a total footprint of 364,998 SF upon completion and is expected to significantly enhance the company's data center capacity in the area.
|
|
14.91 miles
|
QTS: Manassas DC2
|
This facility is part of QTS Data Center Campus in Manassas.
|
|
14.93 miles
|
Cloud PointInterested in this information?Contact us
|
Amazon's Tanner Way Campus in Manassas comprises four single-story data center buildings, spanning a total of 795,191 square feet.
|
|
14.94 miles
|
Stack: NVA05B
|
STACK Infrastructure is constructing a new data center facility at9001 Freedom Center Blvd, Building B in Manassas, with a substantial footprint of 340000 square feet.
|
|
14.97 miles
|
Metro ValleyInterested in this information?Contact us
|
The IAD-101 data center building is part of Amazon's Tanner Way Campus in Manassas, VA. The one-story building consists of 22 backup diesel generators with 124 exhaust fans.
|
|
14.98 miles
|
Core HubInterested in this information?Contact us
|
Microsoft intends to construct two 3-story data center buildings, known as MNZ01 and MNZ02, which will comprise 623,360 square feet. Microsoft acquired the 46 acre plot in 2020 for $29 million.
|
|
15.01 miles
|
QTS: Manassas DC3
|
This facility is part of QTS Data Center Campus in Manassas.
|
|
15.06 miles
|
Campus MaxInterested in this information?Contact us
|
The IAD-102 data center building is part of Amazon's Tanner Way Campus in Manassas, VA. The one-story building consists of 26 backup diesel generators with 124 exhaust fans.
|
|
15.07 miles
|
CloudHQ: MCC7
|
MCC7 will be part of CloudHQ's MCC Campus in Manassas. The facility is slated to begin construction in mid-2025 with an expected ready-for-service delivery in Q3 2026.
|
|
15.08 miles
|
TPC: Manassas, VA
|
|
|
15.09 miles
|
CloudHQ MCC3
|
CloudHQ MCC3 is a part of The MCC data center campus.
|
|
15.09 miles
|
Stack: NVA05C
|
STACK Infrastructure announced plans to construct a new facility on Wellington Road in Manassas. The purpose-built facility will have a total footprint of 176,276 SF upon completion.
|
|
15.10 miles
|
Valley AlphaInterested in this information?Contact us
|
The IAD-103 data center building is part of Amazon's Tanner Way Campus in Manassas, VA. The one-story building consists of 18 backup diesel generators with 84 exhaust fans.
|
|
15.11 miles
|
Valley PrimeInterested in this information?Contact us
|
Microsoft acquired the 46 acre plot in 2020 for $29 million. The plans call for new construction of two - three-story data center buildings.
|
|
15.13 miles
|
CloudHQ Manassas MCC1
|
CloudHQ's Manassas Corporate Center (MCC) is a 100-acre, 2,232,875 SF (207,441 SM) data center campus.
|
|
15.14 miles
|
Plaza PrimeInterested in this information?Contact us
|
Amazon paid $152 million to acquire roughly 140 acres across four parcels in Manassas. One pair comprises two lots totaling 113 acres at 8401 and 8501 Vulcan Lane
|
|
15.15 miles
|
Digital Realty: 9905 Godwin
|
A company known as Digital Second Manassas LLC developed a 185,000 sq ft data center at 9905 Godwin Drive in Manassas. Digital Second Manassas is a listed subsidiary of Digital Realty.
|
|
15.19 miles
|
CloudHQ MCC2
|
MCC2 is part of CloudHQ's series of data centers in Manassas, Northern Virginia. The facility, with 250,144 sq ft of gross space, came online in 2019.
|
|
15.23 miles
|
Core PointInterested in this information?Contact us
|
Amazon paid $152 million to acquire roughly 140 acres across four parcels in Manassas. One pair comprises two lots totaling 113 acres at 8401 and 8501 Vulcan Lane.
|
|
15.27 miles
|
CloudHQ: MCC6Z
|
MCC6Z will be a part of CloudHQ's MCC Campus in Manassas. MCC6 site consists of two data center buildings, MCC6A and MCC6Z.
|
|
15.31 miles
|
CloudHQ: MCC4
|
CloudHQ has announced plans for MCC4, a new facility to be located at 10849 Airman Avenue in the Northern Virginia market. The data center will span 225,585 sqft of space.
|
|
15.34 miles
|
Hub ProInterested in this information?Contact us
|
Although the Planning Commission recommended its denial, Amazon Web Services (AWS) withdrew the proposal from the October 22 Board of County Supervisors agenda to allow for further community engagement and feedback.
|
|
15.35 miles
|
CloudHQ: MCC6A
|
MCC6A is part of CloudHQ's MCC Campus in Manassas. This data center became operational in 2022.
|
|
15.39 miles
|
Aligned: Manassas, VA
|
In 2022, Aligned acquired this plot in Manassas, Virginia.
|
|
15.49 miles
|
Black Chamber: Nokesville
|
Data center developer Black Chamber Partners is looking to acquire the 7-acre Manassas Church of the Brethren property at 10047 Nokesville Road to expand its footprint in Northern Virginia’s digital infrastructure hub.
|
|
15.54 miles
|
CloudHQ: MCC5
|
MCC5 will be part of CloudHQ's MCC Campus in Manassas. The project has received site plan approval and is ready for immediate development in 2024. The data center will span 369,600 sq ft of space.
|
|
15.58 miles
|
XX Tech Park
|
The proposed XX Tech Park rezoning could include over 4.6 million square feet of data centers in an area characterized by working farmland, less than a mile from the new State Park at Culpeper Battlefields.
|
|
15.60 miles
|
PrimeInterested in this information?Contact us
|
This facility is part of Amazon's Nokesville Road campus in Manassas, Virginia.
|
|
15.64 miles
|
QTS: Prince William Digital Gateway Campus
|
A judicial ruling voided the massive Digital Gateway data center project, but the developers and county are appealing the decision, leaving the 1.7-gigawatt plan in doubt.
|
|
15.69 miles
|
Hyperscale Data CenterInterested in this information?Contact us
|
Amazon had plans for a massive data center campus in Manassas, Virginia, but in December 2022, the company decided to pause the plans after county staff recommended the denial of the project.
|
|
15.75 miles
|
North HubInterested in this information?Contact us
|
This facility is part of Amazon's Nokesville Road campus in Manassas, Virginia.
|
|
15.86 miles
|
Ridge PrimeInterested in this information?Contact us
|
Amazon Web Services (AWS) is planning another data center campus in the Manassas area of Virginia's Prince William County. Construction has begun on the Amazon Web Services three-building, approximately 250,000-square-foot data center complex.
|
|
16.28 miles
|
Verizon: 7777 Infantry Ridge
|
Former AOL data center
|
|
16.29 miles
|
Equinix Manassas DC14
|
|
|
18.29 miles
|
Valley PrimeInterested in this information?Contact us
|
Amazon is building a two-building data center campus along Route 3 in Stevensburg, a town in Culpeper County, Northern Virginia.
|
|
18.33 miles
|
Park ThreeInterested in this information?Contact us
|
Amazon is building a two-building data center campus along Route 3 in Stevensburg, a town in Culpeper County, Northern Virginia.
|
|
18.44 miles
|
Campus OneInterested in this information?Contact us
|
Amazon Data Services acquired 91 acres in Manassas for $218m
|
|
18.48 miles
|
EdgeCore: Culpeper
|
Data center firm EdgeCore is expanding in Virginia again with plans for a new campus in Culpeper County.
|
|
18.57 miles
|
Red Ace Bldg D
|
The Culpeper County Board of Supervisors in Virginia has approved the rezoning of the Red Ace Data Center campus, also known as the Keyser Road Data Center.
|
|
18.61 miles
|
Red Ace Bldg C
|
The Culpeper County Board of Supervisors in Virginia has approved the rezoning of the Red Ace Data Center campus, also known as the Keyser Road Data Center.
|
|
18.66 miles
|
Red Ace Data Center campus
|
The Culpeper County Board of Supervisors in Virginia has approved the rezoning of the Red Ace Data Center campus, also known as the Keyser Road Data Center.
|
|
18.73 miles
|
Red Ace Bldg B
|
The Culpeper County Board of Supervisors in Virginia has approved the rezoning of the Red Ace Data Center campus, also known as the Keyser Road Data Center.
|
|
19.19 miles
|
Peterson: Culpeper Bldg 8
|
|
|
19.24 miles
|
STACK: Cooper Ridge Expansion
|
|
|
19.26 miles
|
STACK: Cooper Ridge Campus
|
The proposed Copper Ridge site is immediately adjacent to Peterson Companies’ proposed 2.1 million sq ft data center campus.
|
|
19.31 miles
|
CloudHQ: Culpeper
|
Proposed campus in CulpeperIn early 2022, CloudHQ acquired a 40-hectare plot in Culpepper, Virginia.
|
|
19.34 miles
|
CloudHQ: CLP 3
|
|
|
19.37 miles
|
CloudHQ: CLP 2
|
|
|
19.48 miles
|
Peterson: Culpeper Bldg 4
|
|
|
19.51 miles
|
Peterson: Culpeper Bldg 3
|
|
|
19.55 miles
|
Peterson: Culpeper Bldg 2
|
|
|
19.56 miles
|
Peterson: Culpeper Technology Campus
|
Peterson Companies has obtained approval for its 150-acre data center campus. The campus is located on land along Route 799 (McDevitt Drive) and Route 699 (East Chandler Street) in Culpeper and will span 2,049,058 SF.
|
|
19.66 miles
|
Peterson: Culpeper Bldg 7
|
|
|
19.70 miles
|
Equinix Culpeper Campus
|
|
|
19.70 miles
|
Peterson: Culpeper Bldg 6
|
|
|
19.74 miles
|
Peterson: Culpeper Bldg 5
|
|
|
19.76 miles
|
Quantico Ridge Data Center
|
The Quantico Ridge data center project was effectively rejected and halted when the developer abruptly withdrew its rezoning application in May 2026.
|
|
19.81 miles
|
Swift: Culpeper, VA
|
Swift operates a 90,000-square-foot facility on a 30-acre campus in Culpeper, Virginia.
|
|
19.88 miles
|
DataBank: IAD6
|
IAD6 will be the first data center constructed on DataBank’s new Culpeper campus in the Northern Virginia market.; it will offer 383,220 raised square feet of space.
|
|
20.00 miles
|
DataBank: IAD5
|
DataBank has acquired 85 acres of land in Culpeper, Virginia, for a new data center campus. The new Culpeper Campus will host two two-story data centers.
|