Equinix Culpeper CU2

Latest Podcast 18155 Technology Drive
Operational
Fully operational facility
Operated by:

Equinix Culpeper CU2

Short Code: CU2
Year Built: 2010
Ownership: Equinix owns the building.
░░░░ Request Dataset MW
Operational Power
░░░░░░ Interested in this information? Contact us SqFt
Gross Colocation Size

Equinix CU2 (Building B) is the second data center building on the Equinix Culpeper campus. Terremark began construction in January 2009 and opened it in early 2010 as Pod 2 of the NAP of the Capital Region; Equinix bought the campus from Verizon in May 2017.

The two-story precast concrete building offers about 62,000 sq ft of colocation space, served by six 2,250 kW and two 1,500 kW diesel generators.

Map and Nearby Locations

18155 Technology Drive ( Building B )
Equinix Sites
Nearby Facilities

Equinix Culpeper CU2 Power Growth Over Time

+0% since 2022
Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Equinix Culpeper CU2

Distance Site About
0.07 miles Equinix Culpeper CU1
Equinix CU1 is a colocation data center in Building A at 18155 Technology Drive, Culpeper, Virginia. Terremark opened it in 2008 as the first building of the NAP of the Capital Region.
0.07 miles Equinix Culpeper CU3
Equinix CU3 is a colocation data center in Building C at 18155 Technology Drive, Culpeper, Virginia. Terremark opened it in 2010 as the third building of the NAP of the Capital Region.
0.09 miles Equinix Culpeper CU4
Equinix CU4 is a colocation data center in Building D at 18155 Technology Drive, Culpeper, Virginia. Verizon opened the fourth building of the campus before Equinix bought it in 2017; Equinix expanded it in 2018.
0.22 miles DataBank: IAD6
IAD6 will be the first data center constructed on DataBank’s new Culpeper campus in the Northern Virginia market.; it will offer 383,220 raised square feet of space.
0.30 miles Swift: Culpeper, VA
Swift operates a 90,000-square-foot facility on a 30-acre campus in Culpeper, Virginia.
0.38 miles STACK: Rabbit Run Technology Park
Rabbit Run Technology Park is a proposed two-building data center campus in Culpeper County, Virginia, developed by STACK Infrastructure within the county's 950-acre Culpeper Tech Zone corridor.
0.41 miles DataBank: IAD5
DataBank has acquired 85 acres of land in Culpeper, Virginia, for a new data center campus. The new Culpeper Campus will host two two-story data centers.
0.41 miles CloudHQ: CLP 3
0.46 miles CloudHQ: CLP 2
0.53 miles Peterson: Culpeper Bldg 7
0.55 miles CloudHQ: CLP1
Proposed campus in CulpeperIn early 2022, CloudHQ acquired a 40-hectare plot in Culpepper, Virginia.
0.61 miles Peterson: Culpeper Bldg 4
0.63 miles Peterson: Culpeper Bldg 6
0.67 miles Peterson: Culpeper Bldg 3
0.73 miles Peterson: Culpeper Bldg 8
0.74 miles Peterson: Culpeper Bldg 5
0.75 miles Peterson: Culpeper Bldg 2
0.82 miles Peterson: Culpeper Bldg 1
Peterson Companies has obtained approval for its 150-acre data center campus. The campus is located on land along Route 799 (McDevitt Drive) and Route 699 (East Chandler Street) in Culpeper and will span 2,049,058 SF.
0.86 miles STACK: Copper Ridge Expansion
1.01 miles Red Ace Bldg B
The Culpeper County Board of Supervisors in Virginia has approved the rezoning of the Red Ace Data Center campus, also known as the Keyser Road Data Center.
1.07 miles STACK: Culpeper
1.10 miles Red Ace Bldg A
The Culpeper County Board of Supervisors in Virginia has approved the rezoning of the Red Ace Data Center campus, also known as the Keyser Road Data Center.
1.10 miles Red Ace Bldg C
The Culpeper County Board of Supervisors in Virginia has approved the rezoning of the Red Ace Data Center campus, also known as the Keyser Road Data Center.
1.18 miles Red Ace Bldg D
The Culpeper County Board of Supervisors in Virginia has approved the rezoning of the Red Ace Data Center campus, also known as the Keyser Road Data Center.
1.20 miles STACK: CUL01
The proposed Copper Ridge site is immediately adjacent to Peterson Companies’ proposed 2.1 million sq ft data center campus.
1.22 miles EdgeCore: Culpeper
Data center firm EdgeCore is expanding in Virginia again with plans for a new campus in Culpeper County.
4.56 miles XX Tech Park
The proposed XX Tech Park rezoning could include over 4.6 million square feet of data centers in an area characterized by working farmland, less than a mile from the new State Park at Culpeper Battlefields.
5.46 miles ProInterested in this information?Contact us
Amazon is building a two-building data center campus along Route 3 in Stevensburg, a town in Culpeper County, Northern Virginia.
5.55 miles Plaza ThreeInterested in this information?Contact us
Amazon is building a two-building data center campus along Route 3 in Stevensburg, a town in Culpeper County, Northern Virginia.
11.50 miles Convergent Technology Park
Convergent VA has submitted revised conceptual plans for the Convergent Technology Park in Remington, Fauquier County, Virginia.
11.82 miles PointOne: Remington Expansion
11.83 miles PointOne: Remington 1
First building of PointOne's Remington Technology Park on Lucky Hill Road in Remington, Virginia, one of five planned buildings on the 234-acre campus.
11.88 miles Gigaland: Remington, VA
Gigaland has scrapped its initial plans for an 800MW data center campus in Fauquier County, Virginia, after facing local opposition. However, the company now plans to propose a smaller project for the site.
11.97 miles SAMX data center campus
SAMX Data LLC submitted an application in October 2023 to rezone approximately 55.26 acres of property at 11825 Remington Road.
15.84 miles EastInterested in this information?Contact us
Amazon is planning to build data centers near the Wilderness Battlefield in Orange County, Virginia, as part of a larger 2,600-acre development project.
15.96 miles North PointInterested in this information?Contact us
19.68 miles Maple Tree Farm
A 145-acre property known as Maple Tree Farm, located just east of Warrenton, is being marketed as a potential data center location.

Equinix Culpeper CU2 Data Center Photos See all

Map of data centers immediately surrounding the Equinix campus and Beaumeade Circle.
Ashburn Data Center Cluster Map
Source: Baxtel

Map of data centers immediately surrounding the Equinix campus and Beaumeade Circle.

Equinix cage door
Source: Baxtel

Operating Company

Operated by:

Equinix connects the world’s leading businesses to their customers, employees and partners inside the most interconnected data centers.

0
Facilities
0
Markets
0MW
Megawatts

News See all

Read Schneider Electric and Equinix Trial Software-Defined Switchgear for Data Centers
Equinix and Schneider Electric have partnered to pilot software-defined medium-voltage switchgear at an undisclosed Equinix data center. The technology, developed by Schneider Electric, is designed...

Schneider Electric and Equinix Trial Software-Defined Switchgear for Data Centers

September 30, 2026 Equinix

Equinix and Schneider Electric have partnered to pilot software-defined medium-voltage switchgear at an undisclosed Equinix data center. The technology, developed by Schneider Electric, is designed to reduce the need for specialized cabling and hardware in data centers. Schneider said the...

Read more
Read Diraq And Equinix To Deploy Australia’s First Commercial Quantum Computer
Australian quantum startup Diraq has partnered with Equinix to deploy a quantum computer at an Equinix data center in Sydney. The eight-qubit system will use a silicon chip with self-contained cryo...

Diraq And Equinix To Deploy Australia’s First Commercial Quantum Computer

September 03, 2026 Equinix

Australian quantum startup Diraq has partnered with Equinix to deploy a quantum computer at an Equinix data center in Sydney. The eight-qubit system will use a silicon chip with self-contained cryogenic cooling and control electronics. The chip can be replaced to increase the qubit count without...

Read more
Read Equinix to Reuse Data Center Heat to Warm Homes in Milan
Equinix has partnered with Italian energy company A2A to recover waste heat from its data center campus in Settimo Milanese and feed it into Milan’s district heating network. Under the agreement, E...

Equinix to Reuse Data Center Heat to Warm Homes in Milan

July 10, 2026 Equinix

Equinix has partnered with Italian energy company A2A to recover waste heat from its data center campus in Settimo Milanese and feed it into Milan’s district heating network. Under the agreement, Equinix will design and operate the heat recovery system, while A2A will use four large-scale heat...

Read more
Read Equinix Trials Hydrogen Fuel Cell Technology at Data Center in Ireland
Equinix has launched its first trial of hydrogen fuel cell technology as a replacement for diesel backup generation at a data center in Ireland. Working with ESB and GeoPura, the company has deploy...

Equinix Trials Hydrogen Fuel Cell Technology at Data Center in Ireland

June 19, 2026 Equinix

Equinix has launched its first trial of hydrogen fuel cell technology as a replacement for diesel backup generation at a data center in Ireland. Working with ESB and GeoPura, the company has deployed two hydrogen-powered generators at its DB3 Data Center facility. The 12-week trial will support...

Read more
Read Equinix is Building its Fourth Data Center in Malaysia
Equinix is Building its Fourth Data Center in Malaysia

Equinix is Building its Fourth Data Center in Malaysia

May 12, 2026 Equinix

Equinix will build its fourth data center in Malaysia, KL2, in Kuala Lumpur. The US$190 million facility will house over 2,200 cabinets at full build-out, though its size and IT capacity were not disclosed. Equinix said the new data center will be located less than 1 km from its KL1 facility in...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts

Ready to Level up Your
Data Center Strategy?