In Doubt
The development is facing regulatory or community opposition
Operated by: Attotek Inc

XX Tech Park

Lot Size: 426 acres

The proposed XX Tech Park rezoning could include over 4.6 million square feet of data centers in an area characterized by working farmland, less than a mile from the new State Park at Culpeper Battlefields.

  • Update: The Culpeper Planning Commission has reportedly recommended the denial of the project, but the final decision rests with the Board of Supervisors.

This proposal follows a previous attempt in 2022, when AttoTek withdrew its data center campus plans for the same location after strong community opposition over potential impacts to the area's historic and agricultural character.

Map and Nearby Locations:

Hoffman Ln
Attotek Inc Sites
Nearby Facilities

Sites within 15 miles of XX Tech Park

Distance Site About
3.38 miles EdgeCore: Culpeper
Data center firm EdgeCore is expanding in Virginia again with plans for a new campus in Culpeper County.
3.71 miles Red Ace Bldg C
The Culpeper County Board of Supervisors in Virginia has approved the rezoning of the Red Ace Data Center campus, also known as the Keyser Road Data Center.
3.77 miles Red Ace Bldg D
The Culpeper County Board of Supervisors in Virginia has approved the rezoning of the Red Ace Data Center campus, also known as the Keyser Road Data Center.
3.84 miles Red Ace Data Center campus
The Culpeper County Board of Supervisors in Virginia has approved the rezoning of the Red Ace Data Center campus, also known as the Keyser Road Data Center.
3.87 miles Red Ace Bldg B
The Culpeper County Board of Supervisors in Virginia has approved the rezoning of the Red Ace Data Center campus, also known as the Keyser Road Data Center.
3.89 miles Hyperscale Data Center Request Dataset
Amazon is building a two-building data center campus along Route 3 in Stevensburg, a town in Culpeper County, Northern Virginia.
3.99 miles Hyperscale Data Center Request Dataset
Amazon is building a two-building data center campus along Route 3 in Stevensburg, a town in Culpeper County, Northern Virginia.
4.34 miles CloudHQ: CLP 3
4.36 miles Peterson: Culpeper Bldg 8
4.40 miles CloudHQ: Culpeper
Proposed campus in CulpeperIn early 2022, CloudHQ acquired a 40-hectare plot in Culpepper, Virginia.
4.42 miles CloudHQ: CLP 2
4.51 miles Cooper Ridge Expansion
4.59 miles Equinix Culpeper Campus
4.60 miles Cooper Ridge Campus
The proposed Copper Ridge site is immediately adjacent to Peterson Companies’ proposed 2.1 million sq ft data center campus.
4.63 miles Peterson: Culpeper Bldg 4
4.69 miles Peterson: Culpeper Bldg 3
4.70 miles DataBank: IAD6
IAD6 will be the first data center constructed on DataBank’s new Culpeper campus in the Northern Virginia market.; it will offer 383,220 raised square feet of space.
4.76 miles Peterson: Culpeper Bldg 7
4.76 miles DataBank: IAD5
DataBank has acquired 85 acres of land in Culpeper, Virginia, for a new data center campus. The new Culpeper Campus will host two two-story data centers.
4.77 miles Peterson: Culpeper Bldg 2
4.79 miles Swift: Culpeper, VA
Swift operates a 90,000-square-foot facility on a 30-acre campus in Culpeper, Virginia.
4.82 miles Peterson: Culpeper Technology Campus
Peterson Companies has obtained approval for its 150-acre data center campus. The campus is located on land along Route 799 (McDevitt Drive) and Route 699 (East Chandler Street) in Culpeper and will span 2,049,058 SF.
4.85 miles Peterson: Culpeper Bldg 6
4.93 miles Peterson: Culpeper Bldg 5
6.94 miles Convergent Technology Park
Convergent VA has submitted revised conceptual plans for the Convergent Technology Park in Remington, Fauquier County, Virginia.
7.28 miles PointOne: Remington Expansion
7.29 miles PointOne: Remington Technology Park
In March 2018, Alberta-based PointOne Holdings Inc. received approval to rezone 234 acres on Lucky Hill Road, Remington, for a data center project.
7.37 miles Gigaland: Remington, VA
Gigaland has scrapped its initial plans for an 800MW data center campus in Fauquier County, Virginia, after facing local opposition. However, the company now plans to propose a smaller project for the site.
7.41 miles SAMX data center campus
SAMX Data LLC submitted an application in October 2023 to rezone approximately 55.26 acres of property at 11825 Remington Road.
14.59 miles Hyperscale Data Center Request Dataset
Amazon is planning to build data centers near the Wilderness Battlefield in Orange County, Virginia, as part of a larger 2,600-acre development project.
14.70 miles Hyperscale Data Center Request Dataset
15.58 miles Maple Tree Farm
A 145-acre property known as Maple Tree Farm, located just east of Warrenton, is being marketed as a potential data center location.
17.66 miles Hyperscale Data Center Request Dataset
Amazon Web Services' plans to build a 220,000-square-foot data center at the intersection of Blackwell Road and Lee Highway in Warrenton.
18.91 miles Headwaters: Catlett, VA
The Headwaters Site Development was a proposed $400 million data center project planned for a 67-acre site in the Catlett Station area of Fauquier County, Virginia.

XX Tech Park Data Center Photos (See all)

Map of data centers immediately surrounding the Equinix campus and Beaumeade Circle.
Ashburn Data Center Cluster Map
Source: Baxtel

Map of data centers immediately surrounding the Equinix campus and Beaumeade Circle.

Operating Company

Operated by: Attotek Inc
1
Facilities
0
Markets

News (See all)

Read More News

Podcasts (See all)

See More Podcasts

Documents (See all)

Ready to Level up Your
Data Center Strategy?