Headwaters: Catlett, VA

Latest Podcast Catlett Rd
Withdrawn
Project cancelled before construction
Operated by:

Headwaters: Catlett, VA

Year Built: 2025
Lot Size: 68 acres

The Headwaters Site Development was a proposed $400 million data center project planned for a 67-acre site in the Catlett Station area of Fauquier County, Virginia. The developer, Headwaters Site Development LLC, intended to rezone the land for a massive hyperscale facility. However, the proposal faced intense, organized opposition from local residents concerned about the facility's impact on noise, water resources, power demands, and environmental conservation. Due to this significant community resistance, the developer voluntarily withdrew the application in July 2024, effectively halting the project before it could proceed to a Planning Commission hearing.

Map and Nearby Locations

Catlett Rd
Headwaters Site Development Sites
Nearby Facilities

Headwaters: Catlett, VA Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Headwaters: Catlett, VA

Distance Site About
5.41 miles Data Center Edge District
The House family has submitted an application to modify their property's designation in the county's Comprehensive Plan from agricultural estate to the proposed Data Center Edge District (DCED).
6.34 miles OVH: Vint Hill Bldg 1
This facility, situated on the grounds of a former Army base in Vint Hill, became OVHcloud's first U.S. data center and officially began operations in 2017.
6.38 miles Vint Hill Corners
The Vint Hill Corners data center campus proposal, submitted by a company called Vint Hill Corners LLC, which owns about 80 acres on Brookside Parkway, seeks to develop two one-story data centers on about 50 acres of property at 4295 Aiken Drive in Vint Hill.
6.39 miles OVH: Vint Hill Bldg 2
OVHcloud currently plans an expansion of its existing data center, which currently calls the Vint Hill Business Park home.
6.69 miles CyrusOne: Vint Hill
CyrusOne LLC, a data center developer and operator, submitted its first site plan to the county in March for an 870,000-square-foot data center campus.
7.05 miles Stack: Bristow 1 (NVA02K)
Bristow 1 (NVA02K) is the first of two three-story data centers STACK Infrastructure proposed on a 58-acre site in Bristow, Virginia. Prince William County supervisors rejected the project in September 2025.
7.28 miles Stack: Bristow 2 (NVA02L)
Prince William County supervisors have voted to reject STACK Infrastructure’s proposal for the Bristow Campus, a large-scale data center project.
7.32 miles Point AlphaInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
7.32 miles Stack: NVA02J
NVA02J is a 201,000 sq ft data center building under construction on STACK Infrastructure's NVA02 campus at 10155 Linton Hall Road in Prince William County, Virginia.
7.38 miles Stack: NVA02I
NVA02I is a 256,280 sq ft data center building under construction on STACK Infrastructure's NVA02 campus at 10161 Linton Hall Road in Prince William County, Virginia.
7.38 miles Ridge BetaInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
7.47 miles Metro RidgeInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
7.47 miles Stack: NVA02H
NVA02H is a 256,212 sq ft, two-story data center building under construction on STACK Infrastructure's NVA02 campus at 10167 Linton Hall Road in Prince William County, Virginia.
7.64 miles Stack: NVA02F
NVA02F is a data center building under construction on STACK Infrastructure's NVA02 campus at 9640 Hornbaker Road in Manassas, Virginia.
7.67 miles Stack: NVA02E
NVA02E is a 259,200 sq ft data center building on STACK Infrastructure's NVA02 campus at 9570 Hornbaker Road in Manassas, Virginia.
7.71 miles CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
7.78 miles MetroInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
7.78 miles Stack: NVA02A
NVA02A is a 226,862 sq ft data center building on STACK Infrastructure's NVA02 campus at 9750 Hornbaker Road in Manassas, Virginia.
7.81 miles Center BetaInterested in this information?Contact us
7.82 miles JK Land: Hunter Trust
JK Land Holdings has submitted a site plan for a property within the Data Center Overlay, allowing for buildings up to 75 feet in height.
7.84 miles Stack: NVA02B
NVA02B is a 224,652 sq ft data center building on STACK Infrastructure's NVA02 campus at 9740 Hornbaker Road in Manassas, Virginia.
7.84 miles EastInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
7.85 miles Stack: NVA02D
NVA02D is a 281,000 sq ft data center building on STACK Infrastructure's NVA02 campus at 9590 Hornbaker Road in Manassas, Virginia.
7.88 miles Stack: NVA02G
NVA02G is a 185,803 sq ft data center building under construction on STACK Infrastructure's NVA02 campus at 9530 Hornbaker Road in Manassas, Virginia.
7.89 miles Stack: NVA02C
NVA02C, or Building C, is a 14,387 sq ft building on STACK Infrastructure's NVA02 campus at 9730 Hornbaker Road in Manassas, Virginia.
7.94 miles ThreeInterested in this information?Contact us
8.00 miles CenterInterested in this information?Contact us
8.05 miles CloudHQ MCC3
CloudHQ MCC3 is a part of The MCC data center campus.
8.07 miles VAZATA Northern Virginia (NoVa One)
8.07 miles CloudHQ Manassas Hornbaker
Built in 2010, The site was previously known as COPT-6. There is a 100,000 SF raised floor data area, divisible in bays of 6,250 SF
8.07 miles Evoswitch USA WDC 1
8.07 miles North PlazaInterested in this information?Contact us
8.10 miles GlobalInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
8.14 miles Maple Tree Farm
A 145-acre property known as Maple Tree Farm, located just east of Warrenton, is being marketed as a potential data center location.
8.15 miles 8217 Linton Hall (VA4) Digital Realty
8.16 miles CloudHQ: MCC1
CloudHQ's Manassas Corporate Center (MCC) is a 100-acre, 2,232,875 SF (207,441 SM) data center campus.
8.21 miles Yondr: Bristow Bldg2
Yondr Group's Bristow Data Center Campus is located at 12981 Rollins Ford Road, Bristow, VA.
8.23 miles CloudHQ: MDC3
CloudHQ is constructing a three-building data center campus in the heart of the Manassas data center market, just south of the intersection of Routes 28 and 234.
8.25 miles CloudHQ: MCC6Z
MCC6Z will be a part of CloudHQ's MCC Campus in Manassas. MCC6 site consists of two data center buildings, MCC6A and MCC6Z.
8.25 miles CloudHQ: MDC2
CloudHQ is constructing a three-building data center campus in the heart of the Manassas data center market, just south of the intersection of Routes 28 and 234.
8.26 miles CloudHQ: MCC7
MCC7 will be part of CloudHQ's MCC Campus in Manassas. The facility is slated to begin construction in mid-2025 with an expected ready-for-service delivery in Q3 2026.
8.28 miles CloudHQ: MDC1
CloudHQ is constructing a three-building data center campus in the heart of the Manassas data center market, just south of the intersection of Routes 28 and 234.
8.31 miles CloudHQ: MCC6A
MCC6A is part of CloudHQ's MCC Campus in Manassas. This data center became operational in 2022.
8.37 miles CloudHQ: MCC4
CloudHQ has announced plans for MCC4, a new facility to be located at 10849 Airman Avenue in the Northern Virginia market. The data center will span 225,585 sqft of space.
8.38 miles CloudHQ MCC2
MCC2 is part of CloudHQ's series of data centers in Manassas, Northern Virginia. The facility, with 250,144 sq ft of gross space, came online in 2019.
8.38 miles Yondr: Bristow Bldg1
Yondr Group's Bristow Data Center Campus is located at 12981 Rollins Ford Rd, Bristow. The two-building campus is set to deliver critical cloud capacity in one of the world’s largest data center markets.
8.47 miles Campus ThreeInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
8.53 miles Digital Realty: IAD51
8.54 miles Digital Realty: IAD50
8.55 miles PointInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
8.55 miles Central StationInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
8.56 miles Station BetaInterested in this information?Contact us
8.57 miles West ValleyInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
8.59 miles CloudHQ: MCC5
MCC5 will be part of CloudHQ's MCC Campus in Manassas. The project has received site plan approval and is ready for immediate development in 2024. The data center will span 369,600 sq ft of space.
8.60 miles CloudInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
8.60 miles PlazaInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
8.61 miles StationInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
8.62 miles Valley TwoInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
8.64 miles JK Land: Comcast Center
The property, which spans 17 acres, features an existing 108,000-square-foot building that previously served as both office space and a data center.
8.70 miles Edge CampusInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
8.78 miles Yondr: Manassas
Yondr and Cerberus have acquired land in Manassas for a new hyperscale data center campus targeted for service in 2029.
8.83 miles ThreeInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
8.84 miles Digital Realty: IAD53
A company known as Digital Second Manassas LLC developed a 185,000 sq ft data center at 9905 Godwin Drive in Manassas. Digital Second Manassas is a listed subsidiary of Digital Realty.
8.87 miles QTS: Manassas 1 DC4
8.91 miles Iron Mountain: VA-6
VA-6 is one of nine planned data centers situated on a 142-acre, highly secure campus that provides 2,100,000 sq. ft. of highly efficient, green colocation space. VA-6 offers 230,000 gross sq. ft. of space.
8.92 miles QTS Manassas 1 DC6
This facility is part of QTS Manassas 1 Campus in Virginia.
8.96 miles QTS Manassas 1 DC5
This facility is part of QTS Data Center Campus in Manassas.
8.98 miles TwoInterested in this information?Contact us
8.98 miles East StationInterested in this information?Contact us
9.01 miles Iron Mountain: VA-8
Iron Mountain Data Center seeks to expand its Manassas campus with a new two-story building totaling 165,428 square feet (15,369 square meters).
9.03 miles QTS: Manassas 1 DC1
QTS is building a 100+ acre campus in Manassas, Virginia. QTS bought the property, at 10680 University Blvd. adjacent to its existing data center, for $5 million in 2018.
9.03 miles ProInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.05 miles QTS: Manassas 1 DC2
This facility is part of QTS Data Center Campus in Manassas.
9.06 miles Center GammaInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.10 miles Opus Interactive Manassas
9.14 miles Stack: NVA05A
STACK Infrastructure's NVA05A data center offers 36MW of flexible capacity within its 262,000 sq. ft. building in Northern Virginia.
9.14 miles QTS: Manassas 1 DC3
This facility is part of QTS Data Center Campus in Manassas.
9.17 miles Iron Mountain: VA-5
Iron Mountain continues to grow it's Virginia campus at 11560 Hayden Rd, Manassas. VA5 is the fifth building on the Virginia campus over 165,000 sqft of space. The facility will house 40 MW of critical load on completion.
9.17 miles Global PointInterested in this information?Contact us
9.18 miles HubInterested in this information?Contact us
9.19 miles Iron Mountain: VA-3
Iron Mountain continues to grow it's Virginia campus. VA3 is the third and largest building on the Virginia campus over 165,000 sqft and includes two 48 MW data center halls at 30,000 SF each.
9.22 miles Iron Mountain: VA-4
Iron Mountain continues to grow it's Virginia campus at 11560 Hayden Rd, Manassas. VA4 is the fourth building on the Virginia campus over 165,000 sqft of space. The facility will house 32 MW of critical load on completion.
9.24 miles Ridge AlphaInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.25 miles Iron Mountain VA-2
9.26 miles BlackChamber: Gainesville, VA
The Merrifield Garden Center in Gainesville, VA (Prince William County), has been sold for $160M to data center developer BlackChamber Group.
9.27 miles Edge ValleyInterested in this information?Contact us
9.28 miles Iron Mountain VA-1
Announced in March 2016, Iron Mountain’s Manassas data center in Prince William County will include four buildings totaling 915,000 square feet and 60 MW of power. The campus is 83 acres. VA-1, the first building on the campus, is a 165,000Sqft facility with 12.4 MW of power.
9.29 miles Prime HubInterested in this information?Contact us
9.30 miles HubInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.34 miles Iron Mountain: VA-7
The Iron Mountain VA-7 data center is a $100 million project housed in a single building (also known as Iron Mountain DC2) on a 24-acre plot.
9.35 miles Black Chamber: Nokesville
Data center developer Black Chamber Partners is looking to acquire the 7-acre Manassas Church of the Brethren property at 10047 Nokesville Road to expand its footprint in Northern Virginia’s digital infrastructure hub.
9.36 miles HubInterested in this information?Contact us
9.39 miles Stack: NVA05B
STACK Infrastructure is constructing a new data center facility at9001 Freedom Center Blvd, Building B in Manassas, with a substantial footprint of 340000 square feet.
9.39 miles PlazaInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.42 miles Gardner Property Project
A developer files plans for an 82-acre data center campus on the site of the Hillwood Camping Park in Gainesville.
9.47 miles Stack: NVA05C
STACK Infrastructure announced plans to construct a new facility on Wellington Road in Manassas. The purpose-built facility will have a total footprint of 176,276 SF upon completion.
9.48 miles PlusInterested in this information?Contact us
9.48 miles Stack: NVA05D
The purpose-built facility will have a total footprint of 364,998 SF upon completion and is expected to significantly enhance the company's data center capacity in the area.
9.49 miles Hub AlphaInterested in this information?Contact us
9.50 miles Central HubInterested in this information?Contact us
9.50 miles Valley ThreeInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.50 miles PlazaInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.51 miles ThreeInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.51 miles Hub BetaInterested in this information?Contact us
9.52 miles CloudInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.54 miles Hub AlphaInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.54 miles TPC: Manassas, VA
9.55 miles Station OneInterested in this information?Contact us
9.56 miles Ridge TwoInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.57 miles Valley GammaInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.57 miles Point MaxInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.58 miles Core ValleyInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.61 miles Central PlazaInterested in this information?Contact us
9.64 miles NTT: VA10
NTT is building four (4) two-story data centers and associated infrastructure on around 104 acres. The site is named "Grove at Gainesville" or "NTT VA10" in some of the planning documents.
9.68 miles NTT: VA11
VA10 DC2 will be the second building of NTT's Gainesville Data Center Campus. The campus is named "Grove at Gainesville" or "NTT VA10" in some of the planning documents.
9.68 miles North CampusInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.70 miles Tower AlphaInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.71 miles NTT: VA12
VA12 will be the third building of NTT's Gainesville Data Center Campus. The site is named "Grove at Gainesville" or "NTT VA10" in some of the planning documents.
9.72 miles ProInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.78 miles NTT: VA13
VA13 will be the fourth building of NTT's Gainesville Data Center Campus. The campus is named "Grove at Gainesville" or "NTT VA10" in some of the planning documents.
9.79 miles Global ParkInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.88 miles John Marshall Commons Tech Park
CTP-II LLC plans to rezone 22.72 acres at the intersection of Catharpin Road and John Marshall Highway from business and light industrial to office mid-rise to construct the data center.
9.90 miles Prime PlazaInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.92 miles CorScale: Gainesville 3
The data center building 3 will be a part of CorScale's Gainesville Crossing campus located at 13760 University Blvd, Gainesville.
9.94 miles CorScale: Gainesville 2
In Q1 2024, US data center firm CorScale has started work on the second facility at its Gainesville campus in Virginia's Prince William County.
9.98 miles Iron Mountain: Manassas Point
Iron Mountain plans to build two data center buildings and a new electricity substation on a 40-acre data center-zoned property in Manassas, VA.
9.98 miles Campus UltraInterested in this information?Contact us
10.03 miles PlusInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
10.03 miles Campus MaxInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
10.05 miles CentralInterested in this information?Contact us
10.09 miles CorScale: Gainesville 4
The data center building 4 will be a part of CorScale's Gainesville Crossing campus located at 13760 University Blvd, Gainesville. The two-story data center will offer 200,000 sq ft of data hall space.
10.11 miles Station GammaInterested in this information?Contact us
10.12 miles Corscale: Gainesville 1
The first building of this multi-phase development was originally scheduled to open in 2023 but came online in 2025. It is a two-story building with eight (8) data halls and office space totaling approximately 483,000 square feet.
10.18 miles CorScale: Gainesville 5
The data center building 4 will be a part of CorScale's Gainesville Crossing campus located at 13760 University Blvd, Gainesville. The two-story data center will offer 200,000 sq ft of data hall space.
10.21 miles Ridge ThreeInterested in this information?Contact us
10.22 miles Valley BetaInterested in this information?Contact us
10.32 miles Hub BetaInterested in this information?Contact us
10.37 miles Edge CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
10.42 miles Hub TwoInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
10.44 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
10.48 miles GlobalInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
10.56 miles MaxInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
10.65 miles Point AlphaInterested in this information?Contact us
10.67 miles AlphaInterested in this information?Contact us
10.72 miles Global TowerInterested in this information?Contact us
10.78 miles Center GammaInterested in this information?Contact us
10.84 miles West ParkInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
10.92 miles Center ThreeInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
11.07 miles Aligned: Manassas, VA
In 2022, Aligned acquired this plot in Manassas, Virginia.
11.62 miles SAMX data center campus
SAMX Data LLC submitted an application in October 2023 to rezone approximately 55.26 acres of property at 11825 Remington Road.
11.64 miles Quantico Ridge Data Center
The Quantico Ridge data center project was effectively rejected and halted when the developer abruptly withdrew its rezoning application in May 2026.
11.80 miles Equinix Manassas DC14
Equinix DC14 is a two-story colocation data center at 7400 Infantry Ridge Road in Manassas, Virginia, built in 2004 and acquired from Verizon, where it was IAD4, in 2017.
11.85 miles Verizon: 7777 Infantry Ridge
Former AOL data center
11.87 miles PointOne: Remington Expansion
11.91 miles PointOne: Remington 1
First building of PointOne's Remington Technology Park on Lucky Hill Road in Remington, Virginia, one of five planned buildings on the 234-acre campus.
11.98 miles Gigaland: Remington, VA
Gigaland has scrapped its initial plans for an 800MW data center campus in Fauquier County, Virginia, after facing local opposition. However, the company now plans to propose a smaller project for the site.
11.99 miles EdgeInterested in this information?Contact us
11.99 miles Compass: Prince William Digital Gateway Campus
A judicial ruling voided the massive Digital Gateway data center project, but the developers and county are appealing the decision, leaving the 1.7-gigawatt plan in doubt.
11.99 miles Convergent Technology Park
Convergent VA has submitted revised conceptual plans for the Convergent Technology Park in Remington, Fauquier County, Virginia.
13.35 miles QTS: Prince William Digital Gateway Campus
A judicial ruling voided the massive Digital Gateway data center project, but the developers and county are appealing the decision, leaving the 1.7-gigawatt plan in doubt.
15.56 miles Dulles South Innovation Center
The application for the Dulles South Innovation Center data center project in Prince William County, Virginia, has been withdrawn following overwhelming opposition and a unanimous rejection by county supervisors.
17.26 miles Parkstone Tech Park
18.91 miles XX Tech Park
The proposed XX Tech Park rezoning could include over 4.6 million square feet of data centers in an area characterized by working farmland, less than a mile from the new State Park at Culpeper Battlefields.
18.94 miles ValleyInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
18.97 miles Prime StationInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
19.09 miles Campus TwoInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
19.10 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
19.11 miles Central HubInterested in this information?Contact us
19.11 miles Plaza GammaInterested in this information?Contact us
19.13 miles Penzance: Chantilly Premier
Real estate firm Penzance has commenced construction on a new, three-story data center in Chantilly, Virginia.
19.16 miles CoreInterested in this information?Contact us
19.18 miles Tower GammaInterested in this information?Contact us
19.21 miles Station MaxInterested in this information?Contact us
19.21 miles Station OneInterested in this information?Contact us
19.23 miles Lafayette Center Drive Campus - Digital Realty
In 2010, DRT acquired this site from 365 Main. The transaction included 4 other data centers and was for a total of $725 Million.
19.36 miles Station OneInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
19.37 miles CampusInterested in this information?Contact us
19.39 miles Plaza OneInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
19.40 miles SouthInterested in this information?Contact us
19.46 miles Station GammaInterested in this information?Contact us
19.52 miles TwoInterested in this information?Contact us
19.62 miles Station ProInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
19.62 miles CloudInterested in this information?Contact us
19.69 miles North ParkInterested in this information?Contact us
19.71 miles StationInterested in this information?Contact us
19.74 miles Starwood: Stonecroft Blvd, Chantilly
Starwood Capital Group secured approval from the Fairfax County Board of Supervisors to purchase 41.7 acres of county-owned land at 3721 Stonecroft Boulevard in Chantilly, Virginia, for $166.8 million ($4M/acre).
19.78 miles PlazaInterested in this information?Contact us
19.81 miles CampusInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
19.95 miles Global ValleyInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
20.00 miles HubInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us

Headwaters: Catlett, VA Data Center Photos See all

Conceptual plan for Headwaters Site Development's project in Virginia
Source: Fauquier Times
Map of data centers immediately surrounding the Equinix campus and Beaumeade Circle.
Ashburn Data Center Cluster Map
Source: Baxtel

Map of data centers immediately surrounding the Equinix campus and Beaumeade Circle.

Operating Company

Operated by:

Headwaters serves as the site development affiliate of Stream Data Centers, focusing on building a strategic land bank specifically for the data center industry.

The company employs a team of hyperscale experts dedicated to providing sophisticated analysis and methodical processes for site selection and preparation. Headwaters' core mission is to uncover and secure low-risk land sites that are optimal for data center development.

By leveraging Stream Data Centers’ extensive industry experience and resources—developed over decades of executing complex projects—Headwaters delivers shovel-ready sites that meet the exacting standards of today's technology companies. This relationship ensures that prepared land is ready for efficient, low-risk deployment.

0
Facilities
0
Markets

News See all

Read Amazon Settles With Two Former AWS Managers Over Data Center Kickbacks
Amazon has settled its civil claims against two former AWS real estate managers it accused of taking kickbacks on Northern Virginia data center deals. The company told a federal court on October 20...

Amazon Settles With Two Former AWS Managers Over Data Center Kickbacks

October 27, 2026 Amazon AWS

Amazon has settled its civil claims against two former AWS real estate managers it accused of taking kickbacks on Northern Virginia data center deals. The company told a federal court on October 20 that it had reached the agreement with Carl Nelson and Casey Kirschner, less than two weeks before...

Read more
Read Virginia Senator Perry Proposes Three-Year Statewide Data Center Moratorium
State Sen. Russet Perry on Tuesday released draft legislation that would halt approvals for new data centers across Virginia for three years, escalating the political fight over the industry's grow...

Virginia Senator Perry Proposes Three-Year Statewide Data Center Moratorium

October 15, 2026 Virginia

State Sen. Russet Perry on Tuesday released draft legislation that would halt approvals for new data centers across Virginia for three years, escalating the political fight over the industry's growth in the world's largest data center market. Senate Bill 843 would take effect July 1, 2027 and...

Read more
Read 2026 Is the Year Texas Passes Virginia in Data Center Capacity
[Texas](https://baxtel.com/data-center/texas) now has more data center capacity operating and under construction than [Virginia](https://baxtel.com/data-center/virginia). Baxtel tracks 28.3 GW buil...

2026 Is the Year Texas Passes Virginia in Data Center Capacity

October 13, 2026 Texas

Texas now has more data center capacity operating and under construction than Virginia. Baxtel tracks 28.3 GW built or building in Texas, against 17.8 GW in Virginia. On capacity already online, Virginia still leads, 12.3 GW to 11.1 GW. If projects scheduled for this year deliver on time, Texas...

Read more
Read Synergy Group names Northern Virginia, Beijing, and Dublin as top 3 hyperscale locations
Synergy Group names Northern Virginia, Beijing, and Dublin as top 3 hyperscale locations

Synergy Group names Northern Virginia, Beijing, and Dublin as top 3 hyperscale locations

August 23, 2024 Northern Virginia

A report from Synergy Research Group found that just twenty state or metro markets account for 62 percent of the world’s current hyperscale data center capacity. Northern Virginia tops this list while the Greater Beijing Area takes the second place, with both making up 22 percent of global...

Read more
Read Data center design standards approved by Leesburg Town Council in Loudoun
Data center design standards approved by Leesburg Town Council in Loudoun

Data center design standards approved by Leesburg Town Council in Loudoun

August 16, 2023 Northern Virginia

Leesburg's Loudoun County Council unanimously approved data center design criteria. Unlike Ashburn, Virginia's Leesburg has no data centers; however, this may change. Three rezoning petitions may allow data center development in town. One is in the Oaklawn neighborhood, one close to the former...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts

Ready to Level up Your
Data Center Strategy?