FR Investment Poland, part of the Futureal Group, proposed a data center on a 1.9-hectare plot on Orla Street in Kajetany, in the gmina of Nadarzyn. The plan drew strong local opposition because the plot sits about 50 metres from homes. The gmina issued an environmental decision in July 2025, and residents appealed. In September 2026 the gmina council began a new local plan to rezone the plot for housing, at the request of the plot's new owner.

Site History

  • September 2026: The council began rezoning the plot for multi-family housing.
  • August 2025: An appeal against the environmental decision went to the appeals board.
  • July 2025: Nadarzyn issued the environmental decision.

Map and Nearby Locations

Orla
Futureal Investment Partners Sites
Nearby Facilities

Sites within 15 miles of FR Investment: Kajetany

Distance Site
2.43 miles Orange: Warsaw
2.54 miles Emitel: Raszyn
3.57 miles CampusInterested in this information?Contact us
3.70 miles Global PointInterested in this information?Contact us
3.72 miles Real Estate Data CenterInterested in this information?Contact us
3.77 miles CentralInterested in this information?Contact us
4.26 miles Real Estate Data CenterInterested in this information?Contact us
4.64 miles Real Estate Data CenterInterested in this information?Contact us
5.65 miles Greenfields RE: Bobrowiec
6.80 miles Hillwood: Reguły 4
6.92 miles Hillwood: Reguły 3
6.95 miles Hillwood: Reguły 2
6.98 miles Hillwood: Reguły 1
8.03 miles T-Mobile: Piaseczno
8.64 miles Atman: WAW-3 Bldg1
8.74 miles Atman: WAW-3 Bldg2
8.75 miles Polkomtel: MSC Baletowa
8.83 miles Atman: WAW-3 Bldg3
8.83 miles Equinix WA3
8.92 miles Sien Real: Piaseczno Józefosław
8.93 miles OVH Warsaw WAW1
8.98 miles EdgeConnex: Warsaw 2
9.04 miles Comarch: Warsaw
9.04 miles NASK: KCPD Księżowola
9.07 miles EdgeConnex: Warsaw 3
9.09 miles Real Estate Data CenterInterested in this information?Contact us
9.09 miles Greykite: Warsaw
9.10 miles EdgeConneX: Warsaw 4
9.11 miles Equinix: WA4x
9.16 miles Bison Investments: HiPark Piaseczno
9.21 miles Netia: MIND Jawczyce
9.22 miles Data4: Warsaw 1 DC3
9.23 miles Data4: Warsaw 1 DC1
9.24 miles Data4: Warsaw 1 DC4
9.25 miles Data4: Warsaw 1 DC2
9.28 miles Equinix Warsaw WA2
9.43 miles HPC Data CenterInterested in this information?Contact us
9.43 miles Switch Datacenters: Warsaw 1
9.61 miles Netia: BRAIN Grodzisk Mazowiecki
9.63 miles Netia Warszawa WARSC006
9.95 miles Hyperscale Data CenterInterested in this information?Contact us
10.52 miles Atman: Warsaw-2
10.52 miles Aruba Poland PL1
10.85 miles NASK: KCPD Kręczki-Kaputy
10.92 miles Orange: Warsaw Natolin
12.72 miles EdgeConnex Warsaw
12.90 miles Equinix Warsaw WA1
12.92 miles LIM Warsaw
13.01 miles Emitel: Błonie
13.06 miles T-Mobile: P24 Warsaw
13.08 miles Netia WARSC001
15.37 miles Carrier-Neutral Data CenterInterested in this information?Contact us
15.40 miles Vantage: WAW12
15.41 miles Vantage: WAW11
15.62 miles NASK: KCPD Leszno
15.63 miles Hector: DC Gwiaździsta
15.84 miles NASK: DC 11.11
16.56 miles Atman: Warsaw-1
17.55 miles Play: Warsaw Annopol
18.42 miles T-Mobile: Warsaw Szlachecka
18.66 miles University of Warsaw: ICM Technology Centre
19.97 miles Private Equity Data CenterInterested in this information?Contact us

Operating Company

Operated by:

FR Investment Poland Sp. z o.o. is part of Futureal Group, a property developer and investor active in Hungary and Poland. The company proposed a data center on Orla Street in Kajetany, southwest of Warsaw.

0
Facilities
0
Markets

News See all

Read Korbank's Data Center Development in Warsaw Delayed Due To Specification Change
Baxtel

Korbank's Data Center Development in Warsaw Delayed Due To Specification Change

March 18, 2022 Warsaw

Polish telecommunications company, Korbank has revealed that it won’t be completing the construction of its Wroclaw data center till later. The data center was scheduled to be completed this month, but the date has been shifted to June of this year. The delay is happening because Korbank wants to...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Quotes
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.