Overview
Munich is the largest data centre market in Bavaria. Most of its capacity sits in a ring of suburbs, from Unterschleißheim and Garching in the north to Aschheim and Kirchheim in the east, with older carrier sites in the city. The market serves the headquarters of BMW, Allianz and Munich Re, the region's research institutes and a growing AI sector. It also reaches Erding and Dorfen to the east, Augsburg to the west and Ingolstadt to the north.
History
Munich's carrier-neutral market began around 2000, when KPNQwest converted a Deutsche Post sorting centre near the main station. IXEurope reopened it in 2006, and Equinix took it over when it bought IXEurope in 2007. EMC Home of Data opened in the Euro-Industriepark the same year. In 2017 e-shelter, owned by NTT since 2015, opened its Unterschleißheim campus, and noris network opened a campus in Aschheim. EdgeConneX bought a Vodafone facility in 2019. NorthC entered in 2021 by buying IP Exchange, and Equinix opened MU4 in Aschheim in 2022. In March 2025 Equinix said it would close MU1 and MU3 by mid-2027. That September NorthC bought Colt's former Level 3 gateway.
The Market Today
Equinix, NTT, noris, Portus and NorthC lead colocation. Equinix MU4 and noris's Munich East campus sit in Aschheim, and Portus runs two buildings in Kirchheim. NTT runs a two-building campus in Unterschleißheim, and NorthC runs two sites in the city. EdgeConneX, EMC Home of Data, nLighten, M-net and euNetworks also sell colocation.
EMC Home of Data hosts the MuCon-X meet-me platform and is one of the city's main interconnection points. DE-CIX Munich connects more than 180 networks across several of these buildings.
Deutsche Telekom's Industrial AI Cloud with NVIDIA runs in Polarise's Tucherpark data centre, a converted bank data centre that opened in February 2026. In Garching, the Leibniz Supercomputing Centre (LRZ) runs the SuperMUC supercomputers beside the Max Planck Computing and Data Facility. Airbus and Amadeus run large corporate data centres in Taufkirchen and Erding.
Advantages
-
Enterprise demand. BMW, Allianz and Munich Re have their headquarters in Munich.
-
Interconnection. DE-CIX Munich, MegaIX Munich and the MuCon-X platform give carriers and clouds several neutral places to interconnect.
-
Research funding. The Free State has pledged up to €500 million for LRZ's expansion and €500 million for the Max Planck campus in Martinsried.
-
Heat reuse. New builds feed waste heat into local networks. Yexio's Dorfen data centre will supply the town's district heating, and LRZ already reuses part of its supercomputers' heat.
Challenges
-
Grid access. Bayernwerk names greater Munich as one of the two main areas behind 6,000 MW of data-centre connection requests on its network. Bavaria ranks industry ahead of data centres for new connections.
-
Planning approvals. Each project needs a municipal development plan. Planegg rejected the Max Planck Society's first building application in 2024, and the revised plan was still in consultation in 2026.
-
Lease exits. Equinix is leaving MU1 and MU3 because its lease ends in 2028, and customers must move out by June 2027.
-
Power costs. German industrial power prices and grid fees rank among the highest in Europe.
Trends
-
AI conversions. Tucherpark went from planning to operation in about six months and was fully booked seven months later. Telekom is now adding a third floor.
-
New entrants. Penta Infra bought an existing Munich data centre in January 2026 to convert it to colocation. Nexspace plans an edge site in Erding, and HOCHTIEF is building a Yexio data centre in Dorfen.
-
Campus expansions. Equinix topped out MU4's third section in July 2026, and Portus is completing a second building in Kirchheim for 2027. M-net is building a new site in north Munich for 2028.
Power and Policy
SWM Infrastruktur, the grid company of Stadtwerke München, distributes power in Munich and, since 2020, in Aschheim, Kirchheim and Garching. Bayernwerk Netz serves most of the surrounding region, and TenneT runs the transmission grid. Bayernwerk is building a substation in Garching that will serve LRZ alone, due in 2028. The federal Energy Efficiency Act (EnEfG) requires data centres opening from July 2026 to reach a PUE of 1.2 and reuse part of their waste heat.