Polarise, the German AI data center operator majority-owned by SWI Stoneweg Icona Group since February 2026, plans to turn the former Wertachtal shortwave transmitter building and the land around it into an AI data center. Polarise is working with WV Energie AG of Bad Vilbel, whose solar parks and batteries already stand on the land. The energy plan adds more solar, a wind farm and combined heat and power units. Polarise has agreed to buy the site from a consortium of Stadtwerke Bad Vilbel and a local citizens' foundation, and the purchase had not closed by November 2026.
The project still needs a change to the municipality's land-use plan, a project-specific development plan and contracts with the municipality. The municipality supports it, and an online petition against it has run since September 2026.
Site History
- November 2026: Amberg holds a public information event on 12 November and a residents' assembly on 19 November.
- September 2026: An online petition against the project opens.
- March 2026: Polarise announces the AI data center and targets operations in mid-2027.