Featured
atNorth Plans €2B Salo Data Center With 75MW First Phase, 230MW Path
October 05, 2026
Posted by: Abdul-Rahman Oladimeji
atNorth
Pure Data Centres Group
Pure Data Centres Group has secured a $780 million platform growth facility that can expand to about $1.9 billion. The London-based operator announced the financing on November 4, pairing the initial $780 million with a $1.1 billion accordion that allows it to rFeatured: Exterior photograph of Pu...
Read more
Terawulf
TeraWulf has secured Google as a credit backstop for the debt financing behind its Justified Data Campus in Hawesville, Kentucky (TeraWulf press release). The campus carries a 20-year lease with Anthropic worth about $19 billion (Reuters). Baxtel reporteFeatured: Landscape photo of an operational...
Read more
Lambda
Lambda will anchor Project Red Clay, a 1GW data center campus in Lowndes County, Alabama. The AI cloud provider said on November 4 that it will serve as the end user for the site, which Cloverleaf Infrastructure readied for development, and estimates the project represents a $33.1 billion investm...
Read more
NEXTDC
Goodman Group and Digital Realty moved to buy up to 9.9% of Australian operator NEXTDC at a 45.5% premium to the previous close. The buyers offered A$9.50 a share through an aftermarket bookbuild, a purchase Reuters valued at about A$715 million (US$501 million) after reviewing the term sheet. NE...
Read more
OpenAI
OpenAI is now calling its data centers compute campuses, a change that arrived with a policy package published two days after the midterms. The company released a National Community Compact and a Compute Campus Policy Blueprint on Nov. 5. The compact covers future campuses that OpenAI owns and op...
Read more
TerraVolt Holdings
TerraVolt Holdings has secured options to buy about 1,077 acres in Cassia County, Idaho, for a 240 MW gas-powered data center campus. The developer announced the agreements in a press release on Oct. 30 and set out the terms in a Form 8-K filed the same day. Wickel Land Company LLP granted the op...
Read more
United States
Voters in 10 states approved nearly every local data center restriction on the Nov. 3 ballot. Ballotpedia counted 41 measures across those states, and voters backed limits or rejected pro-development proposals in 40 of them, according to the tracker's analysis and results compiled by CNBC. Th...
Read more
atNorth
atNorth has signed a project development agreement with the Swedish energy infrastructure company Calentix covering the SWE04 data center in Långsele, Sweden. Under the agreement, Calentix will develop and finance a system that recovers surplus heat from SWE04 and supplies it to the nearby Långse...
Read more
AMD
AMD reported record quarterly revenue of $13.4 billion, as data center sales nearly doubled from a year earlier. Revenue from the data center segment reached $8.5 billion, up 97%, and AMD guided to about $17 billion for the fourth quarter. The chip designer released the figures on November 3 in i...
Read more
Google will invest $15 billion in Malaysia to build new data center campuses, the company said in its Nov. 4 announcement. The two-year program runs through 2027 and 2028 and expands on the $2 billion the company committed in 2024. It follows Baxtel's Nov. 2 report on Google's $160 millio...
Read more
Virginia
Dominion Energy reports 54.9 gigawatts of data center capacity in various stages of contracting across Virginia, a 13 percent increase from December 2025. The Richmond-based utility disclosedFeatured: Broad landscape view of a utility transmission line right-of-way powering data center corridors ...
Read more
Samsung SDS
Samsung SDS has begun construction on the Gumi AI Data Center in Gongdan-dong, Gumi, in South Korea's North Gyeongsang Province. The company held a groundbreaking ceremony on Nov. 2 at the former Samsung Electronics Gumi Plant 1 site, Samsung SDS said. The facility starts with 60MW of power c...
Read more
Russia / Россия
President Vladimir Putin has allowed Russian companies to run workloads in data centers outside Russia, subject to approval by the FSB. The decree, signed on Nov. 2, also requires non-state Russian data center operators to reserIn-article: Exterior view of the industrial and data center facility ...
Read more
California
California Resources and Bloom Energy signed a memorandum of understanding to jointly evaluate 1GW or more of solid-oxide fuel cell generation in California. The non-binding agreement names data centers, utilities, community choice aggregators, municipalities, and other industrial users as potent...
Read more
Drax Group
Drax Group will develop up to 1GW of data center capacity at its North Yorkshire power station with Brookfield and Radiant. The deal was announced on Nov. 3. Brookfield estimates investment in the site could exceed £20 billion ($26.8 billion), including £2.5 billion foFeatured: Wide landscape edi...
Read more
NTT
NTT DATA opened its new Jakarta data center on Nov. 3, adding 12MW of IT capacity at its existing campus in South Jakarta. The facility, the Jakarta 2 Annex Data Center, is known as JKFeatured: Wide editorial photograph accompanying coverage of NTT DATA's data center campus expansion in Jakar...
Read more
xAI
SpaceXAI is adding two data center campuses in Southaven, Mississippi, to its Colossus 2 complex, facilities chief executive Elon Musk said will host about 420,000 Nvidia GB300 GPUs and be operating by the end of the year. Musk announced the sites, named Gun Range and Spam after their former occu...
Read more
Inner Mongolia
Envision says it is running the world's first 800VDC power system in a large-scale AI data center at its Galaxy campus in Ulanqab, Inner Mongolia. Envision announced the deployment in a Nov. 2 pFeatured: Wide editorial photograph showcasing the Ulanqab AI data center campus following the soli...
Read more
Aligned
Aligned Data Centers launched Delta Cube 3.0 on October 28, a new generation of its patented air-cooling unit developed with Munters. The Aligned press release states the system delivers a 10 percent increase in cooling capacity and a 10 percent gain inFeatured: High-resolution editorial photo of...
Read more
Prometheus Hyperscale
Prometheus Hyperscale will not build its planned 1,250 MW data center campus near Casper, Wyoming, the developer said on October 28. Company president Trevor Neilson told WyoFile that Prometheus is withdrawing from the project in Natrona and Converse counties. Prometheus was the developer of the ...
Read moreTell us what you're looking for. We respond within one business day.