Pending

Providence 6.6 MW Tier III Data Center

Move-In-Ready Tier III Data Center, Providence RI: 5 MW Utility Today, Ramping to ~18.5 MW (Triple-Net + Purchase Option)
Powered Shell
This listing is currently unavailable.

Property Highlights

  • 5 MW total utility available today; ~3.6 MW critical IT at the historic 1.4 PUE
  • Ramp: 8.5 MW utility within ~6 months; the ~10 MW second-feeder expansion is a ~30-month build, ~2029 delivery
  • Offered as a single transaction covering the full ~18.5 MW ramp; no partial tranche
  • 63,789 sq ft data hall inside a 209,927 sq ft single-story building on 24.95 acres
  • Move-in ready: recently vacated, racks and hot-aisle containment in place
  • Four Caterpillar standby generators totaling 4.95 MW (700, 1000, 1250, 2000 kW)
  • Triple-net lease with a lease-then-purchase option; the seller's facility-management group performs the operating scope as a pass-through
  • Seller builds the ~10 MW expansion to Tier III, N+1, air-cooled ~30 kW/rack with hot-aisle containment; 2N or liquid-to-chip upgrades at tenant cost (Sept 2026)
  • Air-cooled today, rear-door liquid possible; density 30-60 kW/rack
  • Rhode Island Energy at ~16.4 cents/kWh

Power & Utilities

Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
NN Request info on this listing MW
across NN Request info on this listing sites
Under Construction
NN Request info on this listing MW
NN Request info on this listing sites currently building
Planned / Prospective
NN Request info on this listing MW
NN Request info on this listing sites announced, but haven't started construction

Infrastructure Utilities

Electric Utility
Rhode Island Energy

Key Facts

Property Type
Powered Shell
Land Size
░░░░░░░░░░░ Request info on this listing
Available Power
9 MW
Power Cost
$0.16/kWh

Location

Power lines, substations, renewable energy, and telecommunications infrastructure near this property. Use the layers button to toggle groups on and off.

Nearby Hyperscalers

1 hyperscaler within 300 km 0 hyperscale sites within 100 km Nearest ≈ 250 km
Apple, Meta, Microsoft, Amazon AWS, Oracle, and OpenAI: no sites within 300 km

The nearest data center owned by each hyperscaler. The strip shows every site out to 300 km; the shaded band is the first 100 km. Distances are rounded to the nearest 10 km for this listing.

Property Description

A fully-built, move-in-ready Tier III enterprise data center in the Providence, Rhode Island metro. 63,789 sq ft of data hall within a 209,927 sq ft single-story building on 24.95 acres, configured 2N, fully racked with hot-aisle containment and recently vacated. Built 1979; steel construction, poured concrete slab, 100% sprinklered dry system. Zoned I1 Limited Manufacturing.

Power (revised August 2026). Rhode Island Energy guarantees 5 MW of total utility today. Three 2,500 kVA transformers (7,500 kVA) are installed, but the utility caps aggregate draw across all three at 5 MW. The building maps utility to critical IT at a 1.4 PUE, the figure it has historically run to, so that 5 MW of utility is ~3.6 MW of critical IT. Standby is four Caterpillar generators totaling 4.95 MW (700, 1,000, 1,250 and 2,000 kW).

Capacity ramps in two tranches. 8.5 MW of utility requires one added ~1,000 kVA transformer and a cutover once the existing 7,500 kVA is energized. A second feeder of ~10 MW then takes the campus to ~18.5 MW.

All MW figures on this listing are stated on a utility (total) basis, matching the intended contract basis. Apply the 1.4 PUE to convert any figure to critical IT. Utility power runs ~16.4 cents/kWh.

Available on a triple-net lease with a lease-then-purchase option. Air-cooled today with rear-door liquid possible; density 30 to 60 kW/rack. The 129,160 sq ft office portion is being mothballed and its power redirected to the data center.

Structure (September 2026). Triple-net: the seller's facility-management group performs the operating scope and passes it through. The seller offers the full ramp as a single transaction covering the whole ~18.5 MW, not a partial tranche.

Expansion build standard (September 2026). The seller builds the ~10 MW second-feeder expansion itself, to the same standard as the existing halls: Tier III concurrently maintainable, N+1, air-cooled at ~30 kW/rack with hot-aisle containment. A 2N topology or liquid-to-chip cooling is a change of spec at the tenant's cost. The seller's engineering team is writing the basis of design.

Delivery. About 3.6 MW of critical IT is available for move-in now. Rhode Island Energy clawed back unused capacity earlier and has since recommitted it. Substation equipment is already installed, so interconnection timing gates the next tranche, not construction; the seller guides that tranche to within six months. The ~10 MW expansion is a standalone plant with a ~30-month build from signing, ~2029 delivery. All figures are seller guidance, not committed utility dates.

Request info on this listing

This listing's details are confidential

Request info on this listing

Additional Details

Zoning
I1 Limited Manufacturing
Pending

Find your next site

28
Listed publicly
249
Off-market, on request

Only 10% of the sites we track are listed publicly.

249 more sites aren't listed. Share your power, location and timeline and our team will match you.
Match me to sites Notify me if it returns

Site Details

Location
░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░░ Request info on this listing
Providence
Listing Code
Providence 6.6 MW Tier III Data Center
Last Updated
Oct 28, 2026
What Baxtel does

Site selection powered by data

Site Selection

Tell us your power, location and timeline. We surface listings that fit and alert you to new ones.

Learn more

Find Colo Inventory

Colocation availability matched to your requirement.

Learn more
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.