Overview
Louisville is the largest metro in Kentucky and holds most of the state's retail colocation. The market covers Jefferson County, its Kentucky suburbs and nearby Indiana counties across the Ohio River. For two decades, carriers and colocation providers served local enterprises. Since 2024, hyperscale developers have arrived, led by Meta in Jeffersonville and PowerHouse Data Centers on Camp Ground Road.
History
Louisville's data center market grew around its carrier buildings. By 2004 the Heyburn Building, a 17-story tower on West Broadway completed in 1928, marketed fiber from several carriers and in-building colocation. Peak 10 entered the market in November 2004 by buying local provider Xodiax. It leased space next door in 2005, opened a third data hall in 2011 and bought an existing data center east of the city in 2017. Peak 10 combined with ViaWest in August 2017, and the company became Flexential in January 2018. In February 2025 Aphorio Carter bought two enterprise data centers in Louisville and Simpsonville.
The Market Today
Flexential runs two Louisville data centers, and Lumen runs three network sites. The Heyburn Building houses Cogent's Louisville data center. It also hosts an access point for MidWest-IX, an Indianapolis-based internet exchange.
Meta announced an $800 million campus at the River Ridge Commerce Center in Jeffersonville, Indiana, in January 2024. It said it expected operations in 2026. PowerHouse Data Centers and Poe Companies announced a hyperscale campus on Camp Ground Road, west of Shively, in January 2025. A revised plan of about 1.6 million square feet won approval in March 2026. Louisville Gas and Electric (LG&E) has started building a substation for it.
Other proposals have stalled. Western Hospitality Partners dropped Project Lincoln in Oldham County in July 2025, two days after the county passed a 150-day moratorium. Meade County rejected a rezoning for a data center near Brandenburg in October 2025.
Advantages
-
Tax exemption. Kentucky's sales and use tax exemption on data center equipment applied only in Louisville Metro when it passed in 2024. Projects in Jefferson County qualify with at least $450 million of investment.
-
Low-cost power. Kentucky's industrial power price ran about 18% below the US average through September 2026.
-
Two states. Sites on both sides of the Ohio River let developers compare Kentucky and Indiana incentives. Indiana gave Meta a 35-year data center sales tax exemption.
-
New generation. In October 2025 the Kentucky Public Service Commission (PSC) approved two new gas units for LG&E and Kentucky Utilities (KU). One is Mill Creek 6 in Jefferson County. The utilities tied the need to data center demand.
Challenges
-
City pause. In August 2026 the Louisville Metro Council passed a 180-day moratorium on data center rezonings, conditional use permits and development plans. It also covers the reuse of existing buildings.
-
Unsettled rules. The draft rules cap new data centers at 500,000 square feet and limit them to industrial zoning. A Council committee has held them since September 2026.
-
Local opposition. Opposition helped stop proposals in Oldham and Meade counties in 2025. In July 2026 Charlestown, Indiana, approved a QLevr data center by a 4-3 vote.
-
Large-load terms. LG&E's Extremely High Load Factor (EHLF) rate requires 15-year contracts and collateral from new loads of 50 MVA or more. Mill Creek 6 is not due until 2031.
Trends
-
Hyperscale arrives. Meta and PowerHouse plan hyperscale campuses in a market built on retail colocation.
-
Warehouses become data centers. In August 2026 Dermody Properties filed plans to convert a new warehouse on Kramers Lane into a data center. The city's pause now covers such conversions.
Power and Policy
LG&E serves Louisville and Jefferson County, and KU serves parts of the surrounding counties, including Simpsonville in Shelby County. Both are PPL subsidiaries that sit outside a regional transmission organization. The PSC approves their rates, large-load contracts and new plants. It approved Mill Creek 6 in October 2025, with monitoring conditions, and the EHLF rate in February 2026.