Site: CyrusOne Allen

Company: CyrusOne
Metro: Dallas
State: Texas
Country: United States
Region: North America
Region: Americas
Region: World
Address:
Site Stats:
Current Under Construction Potential Expansion Total at Full Buildout
Building SqFt: 350,950 1,031,900 1,382,850
Gross SqFt: 670,000 670,000
Usable SqFt:
Office SqFt:
Power (MW): 80.00 80.00

CyrusOne is building a 66-acre data center campus in Allen Texas.

The project will have three phases. The first phase of CyrusOne's planned Allen data center would be 350,950 square feet. Two additional phases would add a 619,100 square foot and a 412,800 square-foot building.

Phase Square Feet
Phase 1 340,000
Phase 2 619,100
Phase 3 412,800
**Total ** 1,371,900

The 2-story data center building campus would include almost 500 parking spaces.

Map and Nearby Locations:

2300 Chelsea Blvd, Allen, TX 75013

SITES within 15 miles of CyrusOne Allen

Show SqM



Distance Site name SqFt MW
12.09 miles 850 E. Collins Blvd: DRT 6.90
12.10 miles DataBank North Dallas DFW2 42,000 10.00
12.19 miles 1232 Alma Road: DRT 60,687 6.75
12.19 miles Digital Dallas Campus in Richardson - Digital Realty 579,859 72.00
12.19 miles Equinix Dallas DA10 13,000 6.00
12.21 miles 1210 Integrity Drive: DRT 60.00
12.22 miles Sungard Dallas (DAL-1001) 75,000
12.26 miles 907 Security Row: DRT 70,000 8.40
12.28 miles Rackspace Richardson DFW3 56,179 6.98
12.78 miles 900 N Dorothy - Digital Realty 56,000
The data center is sandwiched between Tierpoint and Cisco Systems data centers
From Left to Right: Laramie Dorris, VP Design & Construction, Kellie Teal-Guess, CPO (Chief People Officer), Gary Caplinger, Allen Mayor Pro Tem Baine Brooks, Allen City Council Member John Hatem, ...

The data center is sandwiched between Tierpoint and Cisco Systems data centers
Location of New CONE Data Center in Allen

The data center is sandwiched between Tierpoint and Cisco Systems data centers

From Left to Right: Laramie Dorris, VP Design & Construction, Kellie Teal-Guess, CPO (Chief People Officer), Gary Caplinger, Allen Mayor Pro Tem Baine Brooks, Allen City Council Member John Hatem, ...
Allen data center ground breaking in October 2017

From Left to Right: Laramie Dorris, VP Design & Construction, Kellie Teal-Guess, CPO (Chief People Officer), Gary Caplinger, Allen Mayor Pro Tem Baine Brooks, Allen City Council Member John Hatem, EVP, Operations, Design & Construction, Allen Mayor Stephen Terrell, Robert Jackson, General Counsel, Peter Vargas, City Manager Dan Bowman, Executive Director/CEO, AEDC Danny Cowser, Director, Construction & Design

Exterior of the Massive facility
New Colocation Room ready for a deployment (Nov 2018)
Source: CyrusOne

January 2019

Allen data sheet