Cheswick Generating Station

Ownership: Allegheny DC Property Co. owns the building.
Lot Size: 47 acres

Allegheny DC Property Co. plans to develop a data center complex on the 47-acre site of the former Cheswick Generating Station in Springdale, Pennsylvania.

The proposed development includes a 565,000 sq ft (52,490 sqm) data center and a 200,000 sq ft (18,580 sqm) building for cooling and facility management. The redevelopment is overseen by Charah Environmental Redevelopment Group, which acquired the site in 2022 after the 565MW coal power plant was retired. Demolition and cleanup have been ongoing since March 2025, with the site expected to be fully ready for redevelopment later this year.

If the project receives approval, construction at the site is expected to start in 2027, and the facility is expected to come online in 2028.

The project faces local opposition. The Springdale planning commission delayed a decision on recommending the project to the city council, citing the need for further studies and resident comments. A public meeting saw several residents speak out against the proposals, and a Change.org petition opposing the plan has secured more than 300 signatures.

Map and Nearby Locations

151 Porter St
Allegheny DC Property Co. Sites
Nearby Facilities

Sites within 15 miles of Cheswick Generating Station

Distance Site About
4.62 miles MSA: Rockpointe
MSA’s original facility is Tier III.
4.87 miles Consolidated Rockpointe
7.72 miles TECfusions: New Kensington, PA
In January 2024, TECfusions acquired this 1,350-acre site located 30 miles to the northeast of Pittsburgh.
11.62 miles Lumen: Pittsburgh 2
11.67 miles H5 Pittsburgh
11.87 miles Consolidated Evergreen
11.88 miles MSA: Evergreen Hights
The facility is designed from the ground up to exceed Tier III uptime standards.
12.27 miles Lumen Pittsburgh 1
12.70 miles Cogent: 650 Smithfield
12.74 miles Verizon: 3 Allegheny Ctr
Former XO Communications site
12.79 miles DataBank Pittsburgh PIT1
12.80 miles Expedient Pittsburgh (North Side)
The site is known as Nova Place or "North Side". It was formerly known as Allegheny Center Mall (ACM)
13.00 miles DQE Communications Pittsburgh
13.86 miles American Tower: Pittsburgh
14.47 miles EdgeConneX Pittsburgh
14.85 miles SunCap: McKees Rocks, PA
SunCap Industries, an affiliate of SunCap Property Group, is proposing a data center on the 72-acre RockPoint Industrial site in Stowe Township, PA.
15.27 miles Expedient Pittsburgh (Green Tree)
16.88 miles Ark: Pittsburgh Northpointe
In October 2016, Involta announced plans for the expansion into Western Pennsylvania with UPMC, a leading integrated healthcare provider and insurer, as anchor-tenant. UPMC selected Involta to build, own and operate the multi-tenant facility in the Northpointe Business Park.
17.05 miles Chirisa: Pittsburgh, PA
Chirisa Technology Parks (CTP) has acquired a vacant data center property in Pittsburgh, Pennsylvania, for $5.5 million, signaling the company's continued expansion in the data center market.
19.70 miles Ardent (Northern Data): Pittsburgh, Pennsylvania
Ardent Data Centers, a Northern Data Group company, has finalized the acquisition of a new data center site in Pittsburgh, Pennsylvania. The 41,000 sq ft (3,900 sqm) expanded the site to 20MW.

Cheswick Generating Station Data Center Photos See all

Operating Company

1
Facilities
1
Markets

News See all

Read Ransom Township Could Host 930-Acre Data Centre Campus
Developer Mudiita Infra is planning a 930-acre data centre development in Ransom Township, Pennsylvania. Its affiliate, Mudiita Land Venture, acquired 530 acres south of Ransom Road and west of Sou...

Ransom Township Could Host 930-Acre Data Centre Campus

July 25, 2026 Pennsylvania

Developer Mudiita Infra is planning a 930-acre data centre development in Ransom Township, Pennsylvania. Its affiliate, Mudiita Land Venture, acquired 530 acres south of Ransom Road and west of South Keyser Avenue from KF Real Estate for $2.4 million, according to a deed filed with Lackawanna...

Read more
Read $1.7bn Lebanon County Data Center Plan Withdrawn by Developer
$1.7bn Lebanon County Data Center Plan Withdrawn by Developer

$1.7bn Lebanon County Data Center Plan Withdrawn by Developer

May 15, 2026 Pennsylvania

A proposal for a $1.7 billion data center campus in Lebanon County, Pennsylvania, has been withdrawn by developer Inch & Company. The project included plans for five data centers spanning roughly 640,000 square feet on a 100-acre site near Mt. Pleasant Road, including the rezoning of 58 acres...

Read more
Read Plans Emerge for $1.7bn Data Center in Lebanon County
Plans Emerge for $1.7bn Data Center in Lebanon County

Plans Emerge for $1.7bn Data Center in Lebanon County

April 20, 2026 Pennsylvania

A $1.7 billion data center project could be developed in South Annville Township in southeastern Lebanon County, Pennsylvania. During a public presentation to Lebanon County Commissioners on Wednesday, property developer Inch & Company said it is considering plans to build five data centers...

Read more
Read Plans Filed for Two-Building Data Center Campus in Northeast Pennsylvania
Plans Filed for Two-Building Data Center Campus in Northeast Pennsylvania

Plans Filed for Two-Building Data Center Campus in Northeast Pennsylvania

April 15, 2026 Pennsylvania

Another data center development is being proposed in Pennsylvania. As reported by the Times-Tribune and WVIA, Popca LLC has filed plans to develop a two-building campus in Newton Township.Popca’s application was first filed in January but was denied in February, according to local reports, as...

Read more
Read Data Center Proposed for Stroudsburg, Pennsylvania
Data Center Proposed for Stroudsburg, Pennsylvania

Data Center Proposed for Stroudsburg, Pennsylvania

March 12, 2026 Pennsylvania

A data center project has been proposed for Stroudsburg, Pennsylvania. The proposed “Smithfield Gateway” development was discussed by the Smithfield Township Planning Commission in mid-February and would be located south of Music Center Drive and north of Smithfield Lane. Plans include two data...

Read more
Read More News

Podcasts See all

See More Podcasts

Documents See all

Ready to Level up Your
Data Center Strategy?