Plans Filed for Two-Building Data Center Campus in Northeast Pennsylvania
April 15, 2026
Pennsylvania
Allegheny DC Property Co. plans to develop a data center complex on the 47-acre site of the former Cheswick Generating Station in Springdale, Pennsylvania.
The proposed development includes a 565,000 sq ft (52,490 sqm) data center and a 200,000 sq ft (18,580 sqm) building for cooling and facility management. The redevelopment is overseen by Charah Environmental Redevelopment Group, which acquired the site in 2022 after the 565MW coal power plant was retired. Demolition and cleanup have been ongoing since March 2025, with the site expected to be fully ready for redevelopment later this year.
If the project receives approval, construction at the site is expected to start in 2027, and the facility is expected to come online in 2028.
The project faces local opposition. The Springdale planning commission delayed a decision on recommending the project to the city council, citing the need for further studies and resident comments. A public meeting saw several residents speak out against the proposals, and a Change.org petition opposing the plan has secured more than 300 signatures.
| Distance | Site | About |
|---|---|---|
| 4.62 miles | MSA: Rockpointe |
MSA’s original facility is Tier III.
|
| 4.87 miles | Consolidated Rockpointe |
|
| 7.72 miles | TECfusions: New Kensington, PA |
In January 2024, TECfusions acquired this 1,350-acre site located 30 miles to the northeast of Pittsburgh.
|
| 11.62 miles | Lumen: Pittsburgh 2 | |
| 11.67 miles | H5 Pittsburgh | |
| 11.87 miles | Consolidated Evergreen |
|
| 11.88 miles | MSA: Evergreen Hights |
The facility is designed from the ground up to exceed Tier III uptime standards.
|
| 12.27 miles | Lumen Pittsburgh 1 | |
| 12.70 miles | Cogent: 650 Smithfield | |
| 12.74 miles | Verizon: 3 Allegheny Ctr |
Former XO Communications site
|
| 12.79 miles | DataBank Pittsburgh PIT1 |
|
| 12.80 miles | Expedient Pittsburgh (North Side) |
The site is known as Nova Place or "North Side". It was formerly known as Allegheny Center Mall (ACM)
|
| 13.00 miles | DQE Communications Pittsburgh | |
| 13.86 miles | American Tower: Pittsburgh | |
| 14.47 miles | EdgeConneX Pittsburgh |
|
| 14.67 miles | QTS: Salem Township, Pennsylvania |
QTS is proposing a 1,700+ acre technology campus in Salem Township, Pennsylvania, designed to meet growing demand for data center and AI infrastructure.
|
| 14.85 miles | SunCap: McKees Rocks, PA |
SunCap Industries, an affiliate of SunCap Property Group, is proposing a data center on the 72-acre RockPoint Industrial site in Stowe Township, PA.
|
| 15.27 miles | Expedient Pittsburgh (Green Tree) | |
| 16.88 miles | Ark: Pittsburgh Northpointe |
In October 2016, Involta announced plans for the expansion into Western Pennsylvania with UPMC, a leading integrated healthcare provider and insurer, as anchor-tenant. UPMC selected Involta to build, own and operate the multi-tenant facility in the Northpointe Business Park.
|
| 17.05 miles | Chirisa: Pittsburgh, PA |
Chirisa Technology Parks (CTP) has acquired a vacant data center property in Pittsburgh, Pennsylvania, for $5.5 million, signaling the company's continued expansion in the data center market.
|
| 19.70 miles | Crypto Mining Data Center Request Dataset |
Ardent Data Centers, a Northern Data Group company, has finalized the acquisition of a new data center site in Pittsburgh, Pennsylvania. The 41,000 sq ft (3,900 sqm) expanded the site to 20MW.
|
April 15, 2026
Pennsylvania
March 12, 2026
Pennsylvania
March 04, 2026
Pennsylvania
January 27, 2026
Pennsylvania
October 28, 2025
Pennsylvania
Mar 12, 2026
Eric Bell
World
Feb 05, 2026
Eric Bell
World
Jan 15, 2026
Eric Bell
Applied Digital
Jan 05, 2026
Eric Bell
Dallas
Sep 04, 2025
Eric Bell
Texas