Bridge DC: MY06 Expansion

Latest Podcast Sedenak Tech Park, Taman Perindustrian Kulai
Prospective Expansion
Prospective future expansion capacity
Operated by:

Bridge DC: MY06 Expansion

Utility Provider: Tenaga Nasional Berhad

Bridge Data Centres markets MY06 as a 15-building campus with a 275 kV power intake. Two clusters are built: MY06-1 to MY06-4 on Jalan Digital 7, and MY06-C2 on Persiaran Digital Perdana. Bridge has not announced a location or schedule for the remaining buildings.

Map and Nearby Locations

Sedenak Tech Park, Taman Perindustrian Kulai
Bridge Data Centres Sites
Nearby Facilities

Sites within 15 miles of Bridge DC: MY06 Expansion

Distance Site
0.08 miles Bridge DC: MY06-1
0.08 miles Bridge DC: MY06-2
0.09 miles Bridge DC: MY06-4
0.12 miles Bridge DC: MY06-3
0.18 miles Carrier-Neutral Data CenterInterested in this information?Contact us
0.26 miles K2: Kulai JHR01-03
0.28 miles K2: Kulai JHR04
0.29 miles Valley ThreeInterested in this information?Contact us
0.29 miles Keppel DC: Johor Sedenak 1
0.32 miles Vantage: JHB12
0.32 miles Vantage: JHB11
0.36 miles GDC SDN: Johor SDK2
0.37 miles K2: Kulai Expansion
0.37 miles Vantage: JHB13
0.46 miles Princeton PDG: JH1 Bldg-2
0.48 miles Carrier-Neutral Data CenterInterested in this information?Contact us
0.50 miles Princeton PDG: JH1 Bldg-1
0.56 miles BrightRay: Johor MY-01
0.57 miles BrightRay: MY-03
0.58 miles Princeton PDG: JH1 Bldg-3
0.61 miles Bridge DC: MY06-C2
0.62 miles Princeton PDG: JH1 Bldg-4
0.63 miles BrightRay: MY-02
0.77 miles GDC SDN: Johor SDK1
1.36 miles YTL: Sedenak Tech Park West
8.58 miles Carrier-Neutral Data CenterInterested in this information?Contact us
9.26 miles YTL: JDC11
9.29 miles YTL: JDC6
9.30 miles YTL: JDC5
9.33 miles YTL: JDC4
9.34 miles YTL: JDC3
9.36 miles YTL: JDC2
9.39 miles YTL: JDC1
9.53 miles YTL: Kulai Expansion
10.45 miles Princeton PDG: JH2
10.91 miles PlazaInterested in this information?Contact us
13.19 miles Global Switch: Johor
16.64 miles Fintech Data CenterInterested in this information?Contact us
16.64 miles EdgeConneX: Johor
19.29 miles ZData: Johor
19.44 miles NTT: Gelang Patah
19.91 miles Stack: JHB01A
19.96 miles Stack: JHB01B

Operating Company

Operated by:

Bain Capital merged ChinData with Bridge Data Centres in 2019; the combined company operates as ChinData within China and Bridge across the rest of Asia.

Bridge History

Bridge Data Centres Malaysia Sdn Bhd (formerly known as CSF CX Sdn Bhd) was incorporated on 27 September 2007. Bridge Data Centres Malaysia Sdn Bhd was acquired by Bridge Data Centres Malaysia Holdings Sdn Bhd in November 2017, which in turn is a wholly owned subsidiary of BDC (Malaysia) Holdco Pte. Ltd, Bridge Data Centres is founded by Michael Foust and Kris Kumar who collectively have more than 50 years experience investing in, conceptualizing, designing, building and operating high quality data centre facilities, with best-in-class operating and maintenance procedures to ensure the highest level of uptime and reliability. (Source: Bridge Data Centres About Us)

0
Facilities
0
Markets

News See all

Read Malaysia Requires Data Centers To Source 30% Renewable Energy
Malaysia's government has approved a requirement for data centers to source at least 30 percent of their power from renewable energy. Deputy Prime Minister Datuk Seri Fadillah Yusof told the Dewan ...

Malaysia Requires Data Centers To Source 30% Renewable Energy

October 29, 2026 Malaysia

Malaysia's government has approved a requirement for data centers to source at least 30 percent of their power from renewable energy. Deputy Prime Minister Datuk Seri Fadillah Yusof told the Dewan Rakyat on October 27 that the rule applies to a data center's total capacity or its energy...

Read more
Read DayOne Adds $3.67 Billion Johor Financing, Bank Platform Hits $7.3 Billion
A seven-bank consortium has added RM15 billion, about US$3.67 billion, to [DayOne](https://baxtel.com/data-centers/dayone)'s Johor data center financing, lifting the Singapore-headquartered operato...

DayOne Adds $3.67 Billion Johor Financing, Bank Platform Hits $7.3 Billion

October 14, 2026 DayOne

A seven-bank consortium has added RM15 billion, about US$3.67 billion, to DayOne's Johor data center financing, lifting the Singapore-headquartered operator's debt platform in Malaysia's southern state to RM30 billion, or roughly US$7.3 billion. The lenders set out the upsizing in a...

Read more
Read Bridge Data Centres in Discussions Over $6bn Loan
 Bridge Data Centres in Discussions Over $6bn Loan

Bridge Data Centres in Discussions Over $6bn Loan

March 23, 2026 Bridge Data Centres

Bridge Data Centres, owned by Bain Capital, is reportedly pursuing a loan of up to $6 billion. Bloomberg, citing people familiar with the matter, said the company is in discussions with lenders to finance its planned expansion in Thailand.The company’s QHI01 data center in Bangkok broke ground in...

Read more
Read Bridge Data Centres Plans $2.3B–$4B Investment in Singapore’s Digital Infrastructure
Bridge Data Centres Plans $2.3B–$4B Investment in Singapore’s Digital Infrastructure

Bridge Data Centres Plans $2.3B–$4B Investment in Singapore’s Digital Infrastructure

March 13, 2026 Bridge Data Centres

Bridge Data Centres plans to invest S$3–5 billion ($2.3–4 billion) in Singapore’s next-generation digital infrastructure.In an announcement, the company said it is “uniquely positioned to support hyperscaler customers and global technology companies seeking high-performance, sustainable and...

Read more
Read Bridge DC Secures 'Sustainable' Water Supply for Upcoming Thailand Facility
Bridge DC Secures 'Sustainable' Water Supply for Upcoming Thailand Facility

Bridge DC Secures 'Sustainable' Water Supply for Upcoming Thailand Facility

October 17, 2025 Bridge Data Centres

APAC data center developer Bridge Data Centres (BDC) has signed an industrial water purchase agreement with Thai utility Eastwater Stecon Utilities Co (EWS) for ‘sustainable’ water supply for its under-construction hyperscale data center campus in Chonburi Province, Thailand.Eric Fan, CEO, Bridge...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Quotes
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.