Crusoe: Abilene 2
This facility is part of Crusoe Energy's Lancium Clean Compute Campus in West Texas.
Crusoe is a privately held AI infrastructure developer and GPU cloud provider that builds AI data center campuses and offers GPU cloud services in the United States. The company began as Crusoe Energy Systems, a flare mitigation provider that powered onsite computing from stranded natural gas, with bitcoin mining as an early use case.
Crusoe is developing an AI campus at the Lancium Clean Campus in Abilene, Texas, planned for 1.2 GW, and in May 2025 it secured $11.6 billion in debt and equity to expand the site from two to eight buildings.
For this project, it is reported that Crusoe’s direct customer is Oracle and that OpenAI is Oracle’s customer; the Abilene campus is tied to OpenAI’s Stargate program;
OpenAI later announced an additional 4.5 GW Stargate partnership with Oracle that references the Abilene Stargate I site. Crusoe also expanded in-house manufacturing capability through the acquisition of Easter-Owens Electric in 2022.
Crusoe History:
This facility is part of Crusoe Energy's Lancium Clean Compute Campus in West Texas.
Crusoe is developing a 340-acre data center campus in Warrenton, Missouri, consisting of two 805,000-square-foot buildings and a 40,000-square-foot administrative facility.
This facility is part of Crusoe's Warrenton Campus in Missouri.
Crusoe is considering a hyperscale AI data center campus on rural land northwest of Kingdom City in Callaway County. The project remains in preliminary development, with land acquisition, utility agreements and county tax incentives still unresolved.
Crusoe plans an AI data center campus of about 1,600 acres in Calhoun County, Texas, near the Port of Victoria, powered by Blue Energy's planned gas and nuclear plant.
Crusoe has finalized a lease agreement for a data center in Norway to house Crusoe Cloud, its GPU cloud services.
Crusoe Energy is linked to a potential data center development known as "Project Flash" in Franklin County, Virginia.
Monolith Inc. is partnering with AI infrastructure provider Crusoe to develop a modular data center on a 10-acre section of its Olive Creek campus in Hallam, Nebraska.
This building will be part of the second phase of Crusoe's data center complex currently under construction at the Lancium Clean Campus in Abilene, Texas.
This building will be part of the second phase of Crusoe's data center complex currently under construction at the Lancium Clean Campus in Abilene, Texas.
Planned single-story AI data center at Crusoe's Project Hyper development near Jayton, Texas, scheduled for completion in 2029.
Second planned AI data center at Crusoe's Project Hyper development near Jayton, Texas, targeting completion in May 2029.
Construction is underway for the second phase of Crusoe's data center complex at the Lancium Clean Campus in Abilene, Texas.
This building will be part of the second phase of Crusoe's data center complex currently under construction at the Lancium Clean Campus in Abilene, Texas.
Crusoe plans a large data center campus on about 2,042 acres near Weinert in northern Haskell County, Texas, beside the Willow Springs wind farm.
Crusoe Cloud runs Crusoe Spark modular data centers at Energy Vault's SnyderAI campus in Scurry County, Texas.
Crusoe plans a data center campus with its own natural-gas power plant on about 2,216 acres along State Highway 70, south of Sweetwater in Nolan County, Texas.
Crusoe has proposed a data center on ranch land southeast of Aspermont in Stonewall County, Texas. Its tax abatement is still under negotiation.
Building 2 of Crusoe's Project Hyper is a single-story AI data center under construction on Lancium's Clean Campus in Childress County, Texas.
Building 3 of Crusoe's Project Hyper is a single-story AI data center under construction on Lancium's Clean Campus in Childress County, Texas.
Building 1 of Crusoe's Project Hyper is a single-story AI data center under construction on Lancium's Clean Campus in Childress County, Texas.
Crusoe is building a six-building AI data center campus on Lima Road near Claude in Armstrong County, Texas. Construction began in June 2025.
This building will be part of the second phase of Crusoe's data center complex currently under construction at the Lancium Clean Campus in Abilene, Texas.
Crusoe is building two data center buildings, numbered 9 and 10, on the Lancium campus in Abilene for Microsoft. Each building is about 738,000 square feet.
The first phase will see a 998,000 square foot facility designed to handle huge AI workloads, supporting up to 100,000 GPUs per building.
Crusoe is building two data center buildings, numbered 9 and 10, on the Lancium campus in Abilene for Microsoft. Each building is about 738,000 square feet.
This building will be part of the second phase of Crusoe's data center complex currently under construction at the Lancium Clean Campus in Abilene, Texas.
October 26, 2026 Missouri
Amazon Web Services plans up to 15 more data center buildings on as much as 890 acres in Missouri's Montgomery County, a second campus that would sit closer to Danville, several miles from the Project Green build already under construction near New Florence. Amazon representative Brian Bolton...
Read more
October 23, 2026 Crusoe
Crusoe signed a strategic partnership with Araico, a Paraguayan energy and infrastructure developer, to build AI compute infrastructure powered by the Itaipú Hydroelectric Dam. The first deployment is planned for mid-2027, with a path to 106 MW of IT capacity. Under the partnership, Araico leads...
Read more
October 22, 2026 Crusoe
Crusoe will take a second, larger building at Polar Data Centers' Tørdal campus in Norway. Polar announced the expansion on Oct. 21 (announcement). The new building, DRA02, will add 40MW of liquid-cooled critical IT capacity on hydroelectric power and is due online in late 2027. Crusoe plans...
Read more
October 02, 2026 Crusoe
Crusoe has filed plans with the Texas Department of Licensing and Regulation for a two-building data center campus in Jayton, in rural Kent County, Texas, carrying an estimated investment of $4.8 billion. The filings, first reported by Data Center Dynamics, place the site along County Road 233...
Read more
October 02, 2026 Crusoe
Crusoe has filed plans for two data center buildings in Jayton, Texas. According to filings with the Texas Department of Licensing and Regulation, both facilities will be located along Country Road 233 and P2390 at an unspecified address in Jayton, Kent County. Each data center will span 759,260...
Read more
October 01, 2026 Crusoe
Crusoe is the developer behind Google's data center campus under construction in Armstrong County, Texas, the company said on Sept. 28. The site sits outside Amarillo, and it pairs with 531 megawatts of adjacent West Texas wind, a design that puts generation rather than land at the center of...
Read moreTell us what you're looking for. We respond within one business day.