Overview
Telemark, in southern Norway, grew around hydropower and heavy industry. Its data centre market centres on Grenland, the urban area around Skien and Porsgrunn, and on inland valleys with spare power. Google, GPU clouds and AI developers lead the new projects.
History
Green Mountain opened a data centre at Rjukan in 2014, in a valley of hydropower plants. Bitcoin miners followed, and Northern Data halted its Notodden mine in May 2022. Google bought about 200 hectares at Gromstul in Skien in 2019 and broke ground in 2024. Polar DC signed Crusoe for its Tørdal campus in June 2025, and its first building there went live in early 2026. Fossefall bought Norsk Data's crypto hall in Fyresdal in 2025.
The Market Today
Google's Skien campus started its first building in October 2026, and Skien has granted the frame permit for a second. Nscale and landowner Løvenskiold-Fossum plan AI data centres next to it and at Bolvik, beside Statnett's Grenland station. In Porsgrunn, Polar DC is converting the former REC Wafer building in Herøya Industrial Park for CoreWeave. BW Velora plans a campus at Frier Vest in Bamble.
Inland, Crusoe leases Polar's first Tørdal building in Drangedal, and a second is due in late 2027. EdgeConneX is building six data centre buildings at Molandsmoen in Fyresdal. Fossefall runs its crypto hall there and is building its first AI factory beside it. Green Mountain runs its Rjukan site, and Skygard and Tinfos are studying a site at Svelgfoss near Notodden.
Advantages
-
Hydropower. Telemark's valleys hold many hydropower plants, and Statnett's Rød and Grenland stations serve Grenland.
-
Industrial land. Herøya and Frier Vest offer brownfield plots with grid connections.
-
Cool climate. Free cooling covers most of the year.
Challenges
-
Grid access. Power at Herøya stays capped until more Statnett capacity arrives in late 2027. Statnett's November 2026 pause on new reservations slows other projects.
-
Generator permits. Large campuses need emission permits for their backup generators. Google's second Skien building and EdgeConneX's Fyresdal campus both wait on one.
-
Power prices. Telemark lies in NO2, where prices follow continental Europe more closely than in the north.
Trends
-
AI tenants lease whole buildings. Crusoe and CoreWeave lease Polar DC's buildings at Tørdal and Herøya.
-
Crypto halls convert. Fossefall is adding AI capacity beside the Fyresdal crypto hall it bought.
Power and Policy
Statnett runs the transmission grid. Lede distributes power in Grenland, Herøya Nett runs the grid inside Herøya Industrial Park, and Tnett serves Fyresdal. Telemark lies in the NO2 bidding zone.