Crusoe: Tordal

Site was first built in 2026 and has expansions through 2027
Ownership: Crusoe does not own the building.
This site is leased from Polar DC in the Polar DC: DRA1 building
░░░░ Request Dataset MW
Total Power

Crusoe has finalized a lease agreement for a data center in Norway to house Crusoe Cloud, its GPU cloud services. This facility is anticipated to be operational later 2025 and has the potential to expand up to 52 megawatts (MW).

Map and Nearby Locations

Varpet Industrial Area
Crusoe Sites
Nearby Facilities

Crusoe: Tordal Power Growth Over Time

+0% since 2022
Operational
Construction
Planned
Prospective
In Doubt
Withdrawn
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Crusoe: Tordal

Distance Site About
0.04 miles Polar DC: DRA1
European data center firm Polar DC's DRA1 facility is located on a 60,600 sqm plot in southeast Norway.

Crusoe: Tordal Data Center Photos See all

Crusoe’s DFM system converts natural gas into electricity that powers wellsite digital operations
Source: Source: Crusoe Energy Systems

Operating Company

Operated by:

Crusoe is a privately held AI infrastructure developer and GPU cloud provider that builds AI data center campuses and offers GPU cloud services in the United States. The company began as Crusoe Energy Systems, a flare mitigation provider that powered onsite computing from stranded natural gas, with bitcoin mining as an early use case.

Crusoe is developing an AI campus at the Lancium Clean Campus in Abilene, Texas, planned for 1.2 GW, and in May 2025 it secured $11.6 billion in debt and equity to expand the site from two to eight buildings.

For this project, it is reported that Crusoe’s direct customer is Oracle and that OpenAI is Oracle’s customer; the Abilene campus is tied to OpenAI’s Stargate program;

OpenAI later announced an additional 4.5 GW Stargate partnership with Oracle that references the Abilene Stargate I site. Crusoe also expanded in-house manufacturing capability through the acquisition of Easter-Owens Electric in 2022.

Crusoe History:

  • In July 2025 announced a 1.8 GW AI data center campus with Tallgrass near Cheyenne, Wyoming.
  • In May, 2025, secured $11.6 billion in debt and equity to expand the Abilene, Texas campus to eight buildings, with Crusoe noting Oracle as the direct customer and OpenAI as Oracle’s customer for the site.
  • In March 2025 began construction on the second phase of the Abilene, Texas campus to bring total planned capacity to 1.2 GW.
  • In April 2022 raised Series C financing that included plans to launch the CrusoeCloud platform for high performance computing.
  • In June 2022 acquired Easter-Owens Electric to vertically integrate modular data center manufacturing.
  • Founded in 2018 as Crusoe Energy Systems to mitigate gas flaring by powering onsite computing, including bitcoin mining.
24
Facilities
7
Markets

News See all

Read Crusoe Tied to Proposed Data Center Development in Virginia's Franklin County
A proposed data center project could be coming to Franklin County, Virginia. Local media report that county officials have been in discussions with Crusoe over the potential "Project Flash" develop...

Crusoe Tied to Proposed Data Center Development in Virginia's Franklin County

July 16, 2026 Crusoe

A proposed data center project could be coming to Franklin County, Virginia. Local media report that county officials have been in discussions with Crusoe over the potential "Project Flash" development since November. Few details have been disclosed, but the project is reportedly being considered...

Read more
Read Crusoe Temporarily Stops 1.8GW Data Center Build in Wyoming
Crusoe has paused development of Project Jade, a planned 1.8GW data center campus in Cheyenne, Wyoming that was announced last year and designed to potentially scale up to 10GW. The project was bei...

Crusoe Temporarily Stops 1.8GW Data Center Build in Wyoming

June 10, 2026 Crusoe

Crusoe has paused development of Project Jade, a planned 1.8GW data center campus in Cheyenne, Wyoming that was announced last year and designed to potentially scale up to 10GW. The project was being developed in partnership with Blackstone-backed energy company Tallgrass. Crusoe said it has...

Read more
Read Crusoe Plans Modular Data Center Deployment at Energy Vault’s Snyder, Texas Technology Center
Crusoe Plans Modular Data Center Deployment at Energy Vault’s Snyder, Texas Technology Center

Crusoe Plans Modular Data Center Deployment at Energy Vault’s Snyder, Texas Technology Center

February 12, 2026 Crusoe

US energy storage firm Energy Vault has partnered with AI infrastructure provider Crusoe to deploy modular data centers at Energy Vault’s technology center in Snyder, Texas.“Crusoe is executing against a clear market imperative: customers need scalable compute delivered quickly and reliably,”...

Read more
Read Crusoe to Deploy in Starcloud Satellite Data Center
Crusoe to Deploy in Starcloud Satellite Data Center

Crusoe to Deploy in Starcloud Satellite Data Center

October 22, 2025 Crusoe

Neocloud Crusoe is going to space and has revealed plans to deploy on a Starcloud satellite scheduled to launch in late 2026, and offer limited GPU capacity from space by early 2027. This comes ahead of the expected launch of the Starcloud-1 satellite this November. About the size of a small...

Read more
Read Crusoe's Abilene Data Center Campus id Officially Live
Crusoe's Abilene Data Center Campus id Officially Live

Crusoe's Abilene Data Center Campus id Officially Live

September 30, 2025 Crusoe

Stargate's flagship data center campus in Abilene, Texas, is now live. The first two buildings on the planned 1.2GW site are now operational and being used by Oracle Cloud Infrastructure (OCI) for OpenAI. The two buildings span 980,000 square feet and support 200MW+ of IT.“One of the defining...

Read more
Read More News

Podcasts See all

See More Podcasts

Documents See all

Ready to Level up Your
Data Center Strategy?