SpaceX has reportedly installed more than $250 million of Tesla Megapack battery storage at its planned Starbase, Texas, data center, according to [Data Center Dynamics](https://www.datacenterdynam...

SpaceX Reportedly Installs $250M of Tesla Megapacks at Starbase Data Center

Dragan Spasic

Dragan Spasic

November 27, 2026

SpaceX has reportedly installed more than $250 million of Tesla Megapack battery storage at its planned Starbase, Texas, data center, according to Data Center Dynamics. The figure is an estimate from aerial imagery, not a disclosure by SpaceX or Tesla.
basenor.comFeatured: Overview of the rapid Tesla Megapack battery deployment supporting the planned data center at SpaceX's Starbase campus.
The estimate comes from Tesla investor Sawyer Merritt, who posted images of the site on X.

"Wild. This site was literally just dirt less than 90 days ago. SpaceX is constructing this new data center at Starbase at breakneck speeds. Looks like over $250m of Tesla Megapacks have also been installed," Merritt wrote.

Data Center Dynamics said it has asked SpaceX to confirm the report. Neither company has published a statement on the installation, and the available sources give no unit count or storage capacity.

The batteries support a larger plan. SpaceX proposes to build, own and operate a data center and a co-located natural gas-fired power plant on a 444-acre tract east of Brownsville, between Boca Chica Boulevard and the Port of Brownsville, in Cameron County. The Texas Tribune reported the initial investment at about $24 billion. The campus is designed to run behind the meter, generating its own electricity instead of drawing from the ERCOT grid.

Texas regulators approved a behind-the-meter power installation of 35 natural gas turbines with up to 750 MW of combined capacity, according to Supercomputing Online. The Megapacks buffer that on-site generation. Each Tesla Megapack is a containerized lithium-ion unit that stores more than 3.9 MWh, Data Center Dynamics reported.

SpaceX has used the same approach before. Its AI division, then known as xAI, installed 168 Megapack units at its Colossus supercomputer in Memphis, Tennessee. SpaceX told investors it purchased $295 million of Megapacks in the second quarter of 2026, Merritt wrote, citing a 10-Q filing.

Baxtel tracks 75 data centers across South Texas, operated by 31 providers, and records two 500 MW buildings under construction at SpaceX's Starbase site.

Cameron County commissioners rejected a tax break request for the project, Data Center Dynamics reported. The City of Starbase is scheduled to consider a property tax abatement at its Dec. 9 meeting.