Year Planned: 2027
Lot Size: 340 acres

Sites on this Campus:

Crusoe is developing a 340-acre data center campus in Warrenton, Missouri, consisting of two 805,000-square-foot buildings and a 40,000-square-foot administrative facility. Following the early 2026 approval of its site plan and conditional use permits, the company secured a 75% personal property tax abatement from the city in April 2026.

With an estimated $8.36 billion being spent on high-performance computing equipment, construction is scheduled to support an initial operational date in late 2027, with the full campus build-out expected by 2029.

Map and Nearby Locations

22151 NW Service Rd
Crusoe Sites
Nearby Facilities

Crusoe: Warrenton Bldg1 Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Crusoe: Warrenton Bldg1

Distance Site About
0.16 miles Crusoe: Warrenton Bldg2
This facility is part of Crusoe's Warrenton Campus in Missouri.
13.89 miles CampusInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
13.91 miles Campus TwoInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
13.91 miles Valley ThreeInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
13.99 miles Core RidgeInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
14.04 miles Ridge OneInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
14.07 miles PointInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
14.10 miles North RidgeInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
14.11 miles Core CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
14.13 miles CoreInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
14.17 miles South CampusInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
14.20 miles West StationInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
14.28 miles Center TwoInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
14.28 miles TowerInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
14.31 miles Global StationInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
14.39 miles Station PlusInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
14.40 miles North ValleyInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
14.48 miles Global ValleyInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
14.55 miles Hub GammaInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us

Crusoe: Warrenton Bldg1 Data Center Photos See all

Crusoe’s DFM system converts natural gas into electricity that powers wellsite digital operations
Source: Source: Crusoe Energy Systems

Operating Company

Operated by:

Crusoe is a privately held AI infrastructure developer and GPU cloud provider that builds AI data center campuses and offers GPU cloud services in the United States. The company began as Crusoe Energy Systems, a flare mitigation provider that powered onsite computing from stranded natural gas, with bitcoin mining as an early use case.

Crusoe is developing an AI campus at the Lancium Clean Campus in Abilene, Texas, planned for 1.2 GW, and in May 2025 it secured $11.6 billion in debt and equity to expand the site from two to eight buildings.

For this project, it is reported that Crusoe’s direct customer is Oracle and that OpenAI is Oracle’s customer; the Abilene campus is tied to OpenAI’s Stargate program;

OpenAI later announced an additional 4.5 GW Stargate partnership with Oracle that references the Abilene Stargate I site. Crusoe also expanded in-house manufacturing capability through the acquisition of Easter-Owens Electric in 2022.

Crusoe History:

  • In July 2025 announced a 1.8 GW AI data center campus with Tallgrass near Cheyenne, Wyoming.
  • In May, 2025, secured $11.6 billion in debt and equity to expand the Abilene, Texas campus to eight buildings, with Crusoe noting Oracle as the direct customer and OpenAI as Oracle’s customer for the site.
  • In March 2025 began construction on the second phase of the Abilene, Texas campus to bring total planned capacity to 1.2 GW.
  • In April 2022 raised Series C financing that included plans to launch the CrusoeCloud platform for high performance computing.
  • In June 2022 acquired Easter-Owens Electric to vertically integrate modular data center manufacturing.
  • Founded in 2018 as Crusoe Energy Systems to mitigate gas flaring by powering onsite computing, including bitcoin mining.
0
Facilities
0
Markets

News See all

Read Crusoe Signs 106MW Paraguay AI Cloud Partnership With Araico
[Crusoe](https://baxtel.com/data-centers/crusoe) signed a [strategic partnership](https://markets.businessinsider.com/news/stocks/crusoe-partners-with-araico-to-deploy-ai-cloud-infrastructure-in-pa...

Crusoe Signs 106MW Paraguay AI Cloud Partnership With Araico

October 23, 2026 Crusoe

Crusoe signed a strategic partnership with Araico, a Paraguayan energy and infrastructure developer, to build AI compute infrastructure powered by the Itaipú Hydroelectric Dam. The first deployment is planned for mid-2027, with a path to 106 MW of IT capacity. Under the partnership, Araico leads...

Read more
Read Crusoe Takes 40MW Second Phase At Polar's Hydro-Powered Norway Campus
[Crusoe](https://baxtel.com/data-centers/crusoe) will take a second, larger building at [Polar Data Centers](https://baxtel.com/data-centers/polar-dc)' Tørdal campus in Norway. Polar announced the ...

Crusoe Takes 40MW Second Phase At Polar's Hydro-Powered Norway Campus

October 22, 2026 Crusoe

Crusoe will take a second, larger building at Polar Data Centers' Tørdal campus in Norway. Polar announced the expansion on Oct. 21 (announcement). The new building, DRA02, will add 40MW of liquid-cooled critical IT capacity on hydroelectric power and is due online in late 2027. Crusoe plans...

Read more
Read Crusoe Files For $4.8B Data Center Campus In Jayton, Texas
Crusoe has filed plans with the [Texas Department of Licensing and Regulation](https://www.tdlr.texas.gov/tabs/search) for a two-building data center campus in Jayton, in rural Kent County, Texas, ...

Crusoe Files For $4.8B Data Center Campus In Jayton, Texas

October 02, 2026 Crusoe

Crusoe has filed plans with the Texas Department of Licensing and Regulation for a two-building data center campus in Jayton, in rural Kent County, Texas, carrying an estimated investment of $4.8 billion. The filings, first reported by Data Center Dynamics, place the site along County Road 233...

Read more
Read Crusoe Plans $4.8bn Data Center Campus in Jayton, Texas
Crusoe has filed plans for two data center buildings in Jayton, Texas.
According to filings with the Texas Department of Licensing and Regulation, both facilities will be located along Country Roa...

Crusoe Plans $4.8bn Data Center Campus in Jayton, Texas

October 02, 2026 Crusoe

Crusoe has filed plans for two data center buildings in Jayton, Texas. According to filings with the Texas Department of Licensing and Regulation, both facilities will be located along Country Road 233 and P2390 at an unspecified address in Jayton, Kent County. Each data center will span 759,260...

Read more
Read Crusoe Confirms Google AI Campus In Texas With 531MW Wind Link
Crusoe is the developer behind Google's data center campus under construction in Armstrong County, Texas, the company [said on Sept. 28](https://www.crusoe.ai/resources/newsroom/crusoe-developing-d...

Crusoe Confirms Google AI Campus In Texas With 531MW Wind Link

October 01, 2026 Crusoe

Crusoe is the developer behind Google's data center campus under construction in Armstrong County, Texas, the company said on Sept. 28. The site sits outside Amarillo, and it pairs with 531 megawatts of adjacent West Texas wind, a design that puts generation rather than land at the center of...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.