DataBank: IAD5

Latest Podcast 14601 Germanna Hwy
Under Construction
New facility under construction
Operated by:

DataBank: IAD5

Year Planned: 2027
Utility Provider: Dominion Energy
Lot Size: 85 acres

Sites on this Campus:

DataBank has acquired 85 acres of land in Culpeper, Virginia, for a new data center campus. The new Culpeper Campus will host two two-story data centers.The site will also include a 300MW on-site substation from Dominion Energy.

IAD5 will be the first data center constructed on DataBank’s new Culpeper campus in the Northern Virginia market.; it will offer 229,932 sq ft of data center space.

Map and Nearby Locations

14601 Germanna Hwy
DataBank Sites
Nearby Facilities

DataBank: IAD5 Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of DataBank: IAD5

Distance Site About
0.19 miles DataBank: IAD6
IAD6 will be the first data center constructed on DataBank’s new Culpeper campus in the Northern Virginia market.; it will offer 383,220 raised square feet of space.
0.38 miles Equinix Culpeper CU1
Equinix CU1 is a colocation data center in Building A at 18155 Technology Drive, Culpeper, Virginia. Terremark opened it in 2008 as the first building of the NAP of the Capital Region.
0.41 miles Equinix Culpeper CU2
Equinix CU2 is a colocation data center in Building B at 18155 Technology Drive, Culpeper, Virginia. Terremark opened it in 2010 as the second building of the NAP of the Capital Region.
0.42 miles STACK: Rabbit Run Technology Park
Rabbit Run Technology Park is a proposed two-building data center campus in Culpeper County, Virginia, developed by STACK Infrastructure within the county's 950-acre Culpeper Tech Zone corridor.
0.43 miles Equinix Culpeper CU3
Equinix CU3 is a colocation data center in Building C at 18155 Technology Drive, Culpeper, Virginia. Terremark opened it in 2010 as the third building of the NAP of the Capital Region.
0.49 miles Equinix Culpeper CU4
Equinix CU4 is a colocation data center in Building D at 18155 Technology Drive, Culpeper, Virginia. Verizon opened the fourth building of the campus before Equinix bought it in 2017; Equinix expanded it in 2018.
0.56 miles Swift: Culpeper, VA
Swift operates a 90,000-square-foot facility on a 30-acre campus in Culpeper, Virginia.
0.82 miles CloudHQ: CLP 3
0.86 miles Peterson: Culpeper Bldg 7
0.87 miles CloudHQ: CLP 2
0.95 miles Peterson: Culpeper Bldg 6
0.96 miles CloudHQ: CLP1
Proposed campus in CulpeperIn early 2022, CloudHQ acquired a 40-hectare plot in Culpepper, Virginia.
0.98 miles Peterson: Culpeper Bldg 4
1.03 miles Peterson: Culpeper Bldg 3
1.04 miles Peterson: Culpeper Bldg 5
1.10 miles Peterson: Culpeper Bldg 2
1.14 miles Peterson: Culpeper Bldg 8
1.16 miles Peterson: Culpeper Bldg 1
Peterson Companies has obtained approval for its 150-acre data center campus. The campus is located on land along Route 799 (McDevitt Drive) and Route 699 (East Chandler Street) in Culpeper and will span 2,049,058 SF.
1.26 miles STACK: Copper Ridge Expansion
1.40 miles Red Ace Bldg B
The Culpeper County Board of Supervisors in Virginia has approved the rezoning of the Red Ace Data Center campus, also known as the Keyser Road Data Center.
1.47 miles STACK: Culpeper
1.48 miles Red Ace Bldg C
The Culpeper County Board of Supervisors in Virginia has approved the rezoning of the Red Ace Data Center campus, also known as the Keyser Road Data Center.
1.49 miles Red Ace Bldg A
The Culpeper County Board of Supervisors in Virginia has approved the rezoning of the Red Ace Data Center campus, also known as the Keyser Road Data Center.
1.52 miles EdgeCore: Culpeper
Data center firm EdgeCore is expanding in Virginia again with plans for a new campus in Culpeper County.
1.57 miles Red Ace Bldg D
The Culpeper County Board of Supervisors in Virginia has approved the rezoning of the Red Ace Data Center campus, also known as the Keyser Road Data Center.
1.57 miles STACK: CUL01
The proposed Copper Ridge site is immediately adjacent to Peterson Companies’ proposed 2.1 million sq ft data center campus.
4.76 miles XX Tech Park
The proposed XX Tech Park rezoning could include over 4.6 million square feet of data centers in an area characterized by working farmland, less than a mile from the new State Park at Culpeper Battlefields.
5.35 miles Core TowerInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
5.44 miles Hub PrimeInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
11.70 miles Convergent Technology Park
Convergent VA has submitted revised conceptual plans for the Convergent Technology Park in Remington, Fauquier County, Virginia.
11.99 miles PointOne: Remington 1
First building of PointOne's Remington Technology Park on Lucky Hill Road in Remington, Virginia, one of five planned buildings on the 234-acre campus.
11.99 miles PointOne: Remington Expansion
12.03 miles Gigaland: Remington, VA
Gigaland has scrapped its initial plans for an 800MW data center campus in Fauquier County, Virginia, after facing local opposition. However, the company now plans to propose a smaller project for the site.
12.15 miles SAMX data center campus
SAMX Data LLC submitted an application in October 2023 to rezone approximately 55.26 acres of property at 11825 Remington Road.
15.59 miles Ridge PlusInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
15.71 miles Hub UltraInterested in this information?Contact us
20.00 miles Maple Tree Farm
A 145-acre property known as Maple Tree Farm, located just east of Warrenton, is being marketed as a potential data center location.

DataBank: IAD5 Data Center Photos See all

DataBank Culpeper data center campus sitemap
Source: DataBank
DataBank Culpeper Campus Revised Sitemap
Source: DataBank
Map of data centers immediately surrounding the Equinix campus and Beaumeade Circle.
Ashburn Data Center Cluster Map
Source: Baxtel

Map of data centers immediately surrounding the Equinix campus and Beaumeade Circle.

Operating Company

Operated by:

DataBank is a data center developer and operator that provides colocation, interconnection, cloud and managed services. Founded in 2005 and headquartered in Dallas, the company expanded its footprint through acquisitions and new builds.

Following the December 2020 close of its purchase of zColo assets from Zayo, DataBank reported operating 60 data centers across 28 markets in the U.S. and the U.K. In October 2024, DataBank announced an approximately $2.0 billion equity raise led by AustralianSuper to support new campuses in Dallas, Culpeper and Atlanta.

DataBank History:

  • In October 2024, announced an approximately $2.0 billion equity raise led by AustralianSuper to fund development of new campuses in Dallas, Culpeper, and Atlanta.
  • In December 2020, Databank closed the acquisition of zColo data center assets in the U.S. and U.K. from Zayo.
  • In January 2017, Boca Raton-based Digital Bridge Holdings acquired DataBank. DataBank will continue to operate independently
  • Also in January 2017 DataBank separately acquired C7 Data Centers and C7's four Utah data centers.
  • In January 2017, acquired facilities in Cleveland and Pittsburgh from 365 Data Centers.
  • In July 2016, acquired by Digital Bridge Holdings from Avista Capital Partners.
  • Founded in 2005 in Dallas, Texas.
0
Facilities
0
Markets
0MW
Megawatts

News See all

Read Amazon Settles With Two Former AWS Managers Over Data Center Kickbacks
Amazon has settled its civil claims against two former AWS real estate managers it accused of taking kickbacks on Northern Virginia data center deals. The company told a federal court on October 20...

Amazon Settles With Two Former AWS Managers Over Data Center Kickbacks

October 27, 2026 Amazon AWS

Amazon has settled its civil claims against two former AWS real estate managers it accused of taking kickbacks on Northern Virginia data center deals. The company told a federal court on October 20 that it had reached the agreement with Carl Nelson and Casey Kirschner, less than two weeks before...

Read more
Read Virginia Senator Perry Proposes Three-Year Statewide Data Center Moratorium
State Sen. Russet Perry on Tuesday released draft legislation that would halt approvals for new data centers across Virginia for three years, escalating the political fight over the industry's grow...

Virginia Senator Perry Proposes Three-Year Statewide Data Center Moratorium

October 15, 2026 Virginia

State Sen. Russet Perry on Tuesday released draft legislation that would halt approvals for new data centers across Virginia for three years, escalating the political fight over the industry's growth in the world's largest data center market. Senate Bill 843 would take effect July 1, 2027 and...

Read more
Read 2026 Is the Year Texas Passes Virginia in Data Center Capacity
[Texas](https://baxtel.com/data-center/texas) now has more data center capacity operating and under construction than [Virginia](https://baxtel.com/data-center/virginia). Baxtel tracks 28.3 GW buil...

2026 Is the Year Texas Passes Virginia in Data Center Capacity

October 13, 2026 Texas

Texas now has more data center capacity operating and under construction than Virginia. Baxtel tracks 28.3 GW built or building in Texas, against 17.8 GW in Virginia. On capacity already online, Virginia still leads, 12.3 GW to 11.1 GW. If projects scheduled for this year deliver on time, Texas...

Read more
Read Synergy Group names Northern Virginia, Beijing, and Dublin as top 3 hyperscale locations
Synergy Group names Northern Virginia, Beijing, and Dublin as top 3 hyperscale locations

Synergy Group names Northern Virginia, Beijing, and Dublin as top 3 hyperscale locations

August 23, 2024 Northern Virginia

A report from Synergy Research Group found that just twenty state or metro markets account for 62 percent of the world’s current hyperscale data center capacity. Northern Virginia tops this list while the Greater Beijing Area takes the second place, with both making up 22 percent of global...

Read more
Read DataBank raises capital for new data centers
DataBank raises capital for new data centers

DataBank raises capital for new data centers

November 29, 2023 DataBank

DataBank has raised $533 million of capital to build new data centers through debt and equity. This brings the total funds raised by the company this year to $1.6 billion, with $715 million of secured notes issued in February and a $350 million credit facility announced later in March. DataBank...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts

Documents See all

Ready to Level up Your
Data Center Strategy?