CyrusOne: Castroville SAT14A

Latest Podcast 3397 US Highway 90 W
Under Construction
New facility under construction
Operated by:

CyrusOne: Castroville SAT14A

Short Code: SAT14A
Year Planned: 2027
Utility Provider: Medina Electric Cooperative
Floors: 1
Lot Size: 244 acres

SAT14A is a one-story insulated precast data center building of about 460,000 sq ft on CyrusOne's Castroville SAT14 campus in Medina County, Texas. The building is at 3397 US Highway 90 W, with an estimated cost of $500 million. It is CyrusOne's sixth facility in the San Antonio area.

The building's backup plant has 84 critical 2.25 MW diesel generators and three house generators. Mass grading began in spring 2026, and the structure was rising by September 2026.

Map and Nearby Locations

3397 US Highway 90 W
CyrusOne Sites
Nearby Facilities

CyrusOne: Castroville SAT14A Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of CyrusOne: Castroville SAT14A

Distance Site About
0.30 miles Carrier-Neutral Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
0.60 miles Tract: Medina Expansion
Later phases of Tract's Medina Technology Park in Medina County, Texas.
0.67 miles ValleyInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
0.69 miles Tract: Medina 1
Medina 1 is the first planned building at Tract's Medina Technology Park in Medina County, Texas.
0.70 miles PrimeInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
4.92 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
6.61 miles East RidgeInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
6.67 miles Point PlusInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
6.73 miles Central TowerInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.50 miles HubInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.53 miles Hub PrimeInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.60 miles CoreInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.67 miles Valley ThreeInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.68 miles ProInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.74 miles MaxInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.75 miles Station AlphaInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.86 miles Hub ProInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.93 miles Cloud PointInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.98 miles CloudHQ: SAT1
SAT1 is the first of five data centers CloudHQ plans on about 120 acres at Texas Research Park in west San Antonio.
9.98 miles QTS San Antonio III
QTS San Antonio III is a site on Omicron Drive at Texas Research Park in west San Antonio, platted into three lots for future QTS data centers.
10.00 miles CloudHQ: SAT2
SAT2 is one of five data centers CloudHQ plans on its Texas Research Park campus in west San Antonio.
10.12 miles CloudHQ: SAT3
SAT3 is one of five data centers CloudHQ plans on its Texas Research Park campus in west San Antonio.
10.15 miles CloudHQ: SAT4
SAT4 is one of five data centers CloudHQ plans on its Texas Research Park campus in west San Antonio.
10.27 miles CloudHQ: SAT5
SAT5 is one of five data centers CloudHQ plans on its Texas Research Park campus in west San Antonio.
10.50 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
10.50 miles Vantage: San Antonio TX11
TX11 is the first data center on Vantage Data Centers' TX1 campus at 14720 Omicron Drive in San Antonio, Texas. The two-story building spans 242,667 sq ft (22,545 sqm).
10.51 miles Vantage: TX12
Vantage Data Centers is developing the TX12 facility, a two-story, 432,800 sq ft (40,208 sqm) data center in San Antonio, Texas. The $276.8 million project is scheduled for completion in August 2027.
10.51 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
10.62 miles CyrusOne: SAT6
SAT6 is the second of two CyrusOne data centers on its Omicron Drive campus at Texas Research Park in west San Antonio; its first data halls opened in January 2025.
10.66 miles CyrusOne: SAT7
SAT7 was the third building in CyrusOne's original plan for its Omicron Drive campus in west San Antonio; its lot now holds the campus substation.
10.67 miles CyrusOne: SAT10
SAT10 is one of two data centers CyrusOne plans on a 25-acre tract on Lambda Drive at Texas Research Park in west San Antonio.
10.68 miles CyrusOne: SAT8
SAT8 is the north half of CyrusOne's two-story SAT8 and SAT9 data center on Omicron Drive at Texas Research Park in west San Antonio.
10.68 miles CyrusOne: SAT9
SAT9 is the south half of CyrusOne's two-story SAT8 and SAT9 data center on Omicron Drive at Texas Research Park in west San Antonio.
10.70 miles Carrier-Neutral Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
10.70 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
10.70 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
10.70 miles CyrusOne: SAT5
SAT5 is the first of two CyrusOne data centers on its Omicron Drive campus at Texas Research Park in west San Antonio, opened in 2020.
11.00 miles TwoInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
11.05 miles Cloud PlazaInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
11.54 miles Rowan: Cinco, TX
U.S. data center company Rowan Digital Infrastructure has started construction on its Cinco data center campus, a hyperscale project located near San Antonio, Texas.
11.54 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
11.80 miles Rowan: Pirate
Project Pirate is Rowan Digital Infrastructure's planned second data center campus near Lytle in Medina County, across the road from its Cinco campus.
15.58 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
15.61 miles Stream: SATB1
SATB1 is the first of five buildings on Stream Data Centers' third San Antonio campus, on West Military Drive near Loop 1604.
15.61 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
15.64 miles Stream: SATB2
This data center is a part of Stream's 135-acre hyperscale campus in San Antonio, Texas.
15.70 miles Stream: SATB3
This data center is a part of Stream's 135-acre hyperscale campus in San Antonio, Texas.
15.70 miles Stream: SATB5
This data center is a part of Stream's 135-acre hyperscale campus in San Antonio, Texas.
15.71 miles Stream: SATB4
This data center is a part of Stream's 135-acre hyperscale campus in San Antonio, Texas.
16.27 miles Texas Energy Group: El Camino
Project El Camino is a planned AI data center campus with its own natural-gas power plant south of Devine in Medina County, southwest of San Antonio.
16.89 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
17.07 miles Tower PlusInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
17.07 miles Center OneInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
17.33 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
17.33 miles Vantage: TX22
Data center operator Vantage is developing a two-story, 214,525 square-foot (19,930 sqm) facility known as TX22.
17.41 miles Vantage: San Antonio TX21
TX21 is the first data center on Vantage Data Centers' TX2 campus at 5207 Rogers Road in San Antonio, Texas.
17.41 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
17.51 miles CyrusOne: San Antonio SAT1
SAT1 is CyrusOne's first San Antonio data center, a converted warehouse in the Westover Hills business park that opened in October 2012.
17.51 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
17.54 miles Global RidgeInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
17.63 miles Lowe's: San Antonio Data Center
Lowe's corporate data center in Westover Hills on San Antonio's west side, opened in 2007 alongside the company's North Carolina data center.
17.65 miles Frost Bank: Technology Center
Frost Bank's in-house data center at its Frost Technology Center in Westover Hills on San Antonio's west side, in service since 2009.
17.68 miles PrimeInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
17.73 miles CHRISTUS Health: Information Technology Center
CHRISTUS Health's information technology center in Westover Hills on San Antonio's west side, a data center the health system opened in 2008.
17.74 miles ThreeInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
18.12 miles MaxInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
18.19 miles Valero: San Antonio Data Center
Valero's corporate data center on Wiseman Boulevard in Westover Hills on San Antonio's west side, built for the company's own use in 2008.
18.24 miles AlphaInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
18.47 miles CyrusOne: SAT2
SAT2 is the first of three CyrusOne data centers on its Westover Hills campus in San Antonio, opened in 2015.
18.47 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
18.48 miles CyrusOne: SAT3
SAT3 is the second of three CyrusOne data centers on its Westover Hills campus in San Antonio, built in about seven months and fully leased before it opened in 2017.
18.48 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
18.57 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
18.57 miles Stream: San Antonio SATA1
SATA1, marketed as San Antonio II, is Stream Data Centers' colocation building in the Westover Hills business park in west San Antonio, opened in 2014.
18.62 miles Hyperscale Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
18.62 miles CyrusOne: SAT4
SAT4 is the third of three CyrusOne data centers on its Westover Hills campus in San Antonio, opened in late 2017.
18.98 miles QTS: SAT2-DC1
SAT2-DC1 is the first data center on QTS's San Antonio 2 Campus at Potranco and Ingram roads in west San Antonio, a three-story building opened in 2022.
19.06 miles QTS: SAT2-DC2
SAT2-DC2 is the second data center QTS plans on its San Antonio campus at Potranco and Ingram roads in west San Antonio.
19.85 miles Global PlazaInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
19.85 miles RidgeInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us

Operating Company

Operated by:

CyrusOne is a data center owner, operator, and developer that manages more than 50 facilities, with its footprint concentrated in the U.S. and Europe. The company is based in Dallas and was taken private in March 2022 by funds managed by KKR and Global Infrastructure Partners in a transaction valued at approximately 15 billion dollars including debt.

Its portfolio centers on hyperscale and enterprise colocation across multi-building campuses. CyrusOne has also pursued international growth initiatives alongside its core North American and European markets.

CyrusOne History:

  • March 2022: Taken private by funds managed by KKR and Global Infrastructure Partners in an approximately 15 billion dollar all-cash transaction including debt.
  • July 2015: Acquired Cervalis, adding four data centers and two disaster recovery sites in the New York metro.
  • July 2014: Acquired Cervalis
  • January 2013: Completed initial public offering on NASDAQ as a carve-out of Cincinnati Bell’s data center business.
  • June 2010: Cincinnati Bell acquired CyrusOne for approximately 525 million dollars.
  • 2000: Founded by David Ferdman.
0
Facilities
0
Markets

News See all

Read CyrusOne Files Plans for Three-Building, $1.5bn Data Center Campus in Fairfield, Texas
CyrusOne has filed plans for three buildings at a new data center campus in Fairfield, Texas, located adjacent to Calpine’s Freestone natural gas power plant. The project, on FM 488 in Freestone Co...

CyrusOne Files Plans for Three-Building, $1.5bn Data Center Campus in Fairfield, Texas

August 01, 2026 CyrusOne

CyrusOne has filed plans for three buildings at a new data center campus in Fairfield, Texas, located adjacent to Calpine’s Freestone natural gas power plant. The project, on FM 488 in Freestone County, about 90 miles (144.8km) south of Dallas, is part of a 760MW data center development being...

Read more
Read CyrusOne Begins Construction on 380MW Data Center in Texas
CyrusOne has begun construction on a new data center campus in Texas, breaking ground last week in Freestone County, about 90 miles (144 km) south of Dallas. Full details of the planned development...

CyrusOne Begins Construction on 380MW Data Center in Texas

June 08, 2026 CyrusOne

CyrusOne has begun construction on a new data center campus in Texas, breaking ground last week in Freestone County, about 90 miles (144 km) south of Dallas. Full details of the planned development have not yet been disclosed. CyrusOne has partnered with Constellation on a 380MW agreement to...

Read more
Read CyrusOne to Internalize US Data Center Operations
CyrusOne to Internalize US Data Center Operations

CyrusOne to Internalize US Data Center Operations

May 07, 2026 CyrusOne

US data center operator CyrusOne is bringing a significant portion of its on-site operations in-house, ending large sections of its existing outsourcing partnership with JLL. The KKR-owned company confirmed to DCD this week that it is restructuring its US operating model by internalizing on-site...

Read more
Read CyrusOne Wins Approval for Sangamon, Illinois Data Center
CyrusOne Wins Approval for Sangamon, Illinois Data Center

CyrusOne Wins Approval for Sangamon, Illinois Data Center

April 09, 2026 CyrusOne

CyrusOne has received approval to build a data center in Sangamon, Illinois. Members of the Sangamon County Board voted on Tuesday to allow construction of the $500 million project, which will span 280 acres and include four buildings at the 13000 block of Thayer Road in Waverly.CyrusOne has said...

Read more
Read CyrusOne Starts Construction on First Italy Data CenterI Outside Milan
CyrusOne Starts Construction on First Italy Data CenterI Outside Milan

CyrusOne Starts Construction on First Italy Data CenterI Outside Milan

March 28, 2026 CyrusOne

CyrusOne has broken ground on its first data center in Italy. The company this week announced it has officially broken ground on MIL1 in Milan. The three-story facility will deliver 27MW of IT capacity across 7,000 sqm (75,345 sq ft) of technical space, with the first phase expected to go live by...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Quotes
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.