Aligned SLC-03

Latest Podcast 9300 S 3200 W
Operational
Fully operational facility
Operated by:

Aligned SLC-03

Short Code: SLC-03
Year Built: 2022
Utility Provider: Rocky Mountain Power
Floors: 2
░░░░░░░ Login to view SqFt
Total Building Size
░░░░ Request Dataset MW
Total Power

Aligned’s SLC-03 is the third building of Aligned's Salt Lake city campus. The data center is a two-story, 80MW build-to-suit facility at its West Jordan campus. The campus hosts three facilities, while Aligned has four data centers in the Salt Lake City metro area.

  • Aligned first announced plans for SLC-03 back in June 2022. It was previously described as a 100MW facility.
  • Blackstone loans Aligned $600 million in March 2024 to build out 80MW SLC-03 facility.,

Map and Nearby Locations

9300 S 3200 W
Aligned Sites
Nearby Facilities

Aligned SLC-03 Power Growth Over Time

+0% since 2022
Operational
Construction
Planned
Prospective
In Doubt
Withdrawn
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Aligned SLC-03

Distance Site About
0.11 miles Aligned SLC-02
Aligned's SLC-02 Data Center is located in West Jordan, Utah. This is the second building of Aligned's Salt Lake City data center campus with 48MW capacity.
0.30 miles Aligned Salt Lake City
Situated on 55 acres, including a dedicated on-site substation, the former Fairchild Semiconductor chip fabrication facility is being renovated to become a colocation data center delivering 34 MW of critical capacity.
2.80 miles Flexential Salt Lake (South View)
2.99 miles Cirrus DS View 78
Announced in July 2017, the Cirrus Data Services View 78 Campus is under construction. The first phase will support 224,000 sqft and a critical IT load of 32 MW. At full capacity, the campus will expand to 160 MW and over 1 million square feet.
3.47 miles Verizon: 8871 South Sandy
Former XO site
3.70 miles Hyperscale Data CenterInterested in this information?Contact us
Oracle's 235,000 sqft, Tier III data center is located in the Salt Lake City metropolitan area.
3.98 miles Novva: West Jordan 2
Phase Two of Novva’s West Jordan Campus project began construction in December 2023. It includes the campus’s second building, which measures 318,000 square feet (29,543 square meters).
4.07 miles Novva: West Jordan Campus
The campus plan involves constructing four buildings with a total investment of $1 billion. The first phase, launched in 2023, features a 300,000-square-foot building.
4.16 miles Novva: West Jordan 3
The third building of Novva’s West Jordan campus stands as a massive 318,000-square-foot (29,543-square-meter) facility.
4.33 miles Content Data CenterInterested in this information?Contact us
The first phase of eBay's Topaz project is a 240,000 square foot building housing three 20,000 square foot data center halls
4.34 miles Content Data CenterInterested in this information?Contact us
This facility is part of eBay's Topaz data center campus in South Jordan, Utah.
4.47 miles Content Data CenterInterested in this information?Contact us
This facility is part of eBay's Topaz data center campus in South Jordan, Utah.
4.50 miles Carrier-Neutral Data CenterInterested in this information?Contact us
Aligned Energy (SLC-5) is a 450,000 sqft of data center in West Jordan, Utah.
7.19 miles Edged Energy: Bluffdale, UT
Two buildings are planned for the site.
7.70 miles DataBank SLC6
7.70 miles DataBank SLC4
7.73 miles DataBank SLC5
7.78 miles DataBank SLC3
7.79 miles DataBank Bluffdale Granite Point Campus
DataBank’s Granite Point West Data Center is strategically located in Bluffdale, UT, minutes from downtown Salt Lake City. With a carrier-neutral design, the 95,000 sqft building has over 55,000 sqft of raised-floor space for customer equipment and offers network connectivity to multiple Tier 1 and Tier 2 providers. Diverse substations provide more than 11MW of high-density power, while redundant cooling systems maintain optimal temperatures for data center equipment.
7.79 miles DataBank SLC2
T
he facility has access to more than 8MW of high-density power, and redundant cooling systems maintain optimal temperatures for data center equipment. Situated in a highly secure technology park, the facility is protected by a full perimeter fence encompassing the building, parking areas, loading docks, and all customer entrances.
8.41 miles Flexential Salt Lake (Mill Creek)
8.99 miles Senawave
9.15 miles Flexential Salt Lake (Cottonwood)
9.65 miles Voonami Salt Lake City SLC2
9.65 miles EdgeConneX Salt Lake
Within 5 miles from downtown SLC and 3 miles from SLC International Airport
9.66 miles Flexential Salt Lake (Presidents)
10.03 miles Aligned SLC-04
Aligned's SLC-04 is located in West Valley City, Utah, which is part of the Salt Lake City metropolitan area. SLC-04 is the first facility of approximately 270MW of new data center development that Aligned has planned.
10.83 miles NSA Utah Data Center
10.91 miles West TowerInterested in this information?Contact us
12.08 miles Lumen Salt Lake 1
12.12 miles Flexential Downtown Salt Lake (Delong)
12.25 miles Lumen Salt Lake City 4
13.03 miles Flexential Salt Lake (Fair Park)
13.06 miles XMission 51 E 400 S
13.61 miles DataBank SLC1
DataBank’s Downtown Salt Lake City data center is a multi-tenant colocation facility located in the heart of the downtown business district. The site is the primary carrier-hotel for the Salt Lake City area and is highly populated with a number of prominent Tier-1 and Tier-2 network providers which enter the building through multiple diverse points. The site was formerly operated by C7 before the Databank acquisition.
13.72 miles Unisys Salt Lake City
Unisys's Salt Lake City data center supports multiple Unisys business functions for IT Managed Services
13.93 miles Lumen Salt Lake 2
19.90 miles Tract: Pole Canyon Tech Park
Tract is planning a large new data center park in Eagle Mountain, Utah. The company has completed the acquisition of more than 668 acres of land in Eagle Mountain.
19.95 miles Tract: Pole Canyon Expansion

Aligned SLC-03 Data Center Photos See all

Rendering of Aligned's SLC-03 data center
Source: Aligned

Operating Company

Operated by:

Aligned Data Centers is an infrastructure technology company that offers colocation and build-to-scale solutions to cloud, enterprise, and managed service providers.

In early 2022, Aligned Energy was rebranded to Aligned Data Centers.

45
Facilities
14
Markets

News See all

Read Aligned Data Centers Sold in $40bn Deal
Aligned Data Centers Sold in $40bn Deal

Aligned Data Centers Sold in $40bn Deal

October 11, 2025 Aligned

Aligned Data Centers is being sold to BlackRock and MGX in a deal worth $40 billion, the biggest ever acquisition in the digital infrastructure space. Macquarie Asset Management selling it to a group comprising the AI Infrastructure Partnership (AIP), MGX, and BlackRock-owned Global...

Read more
Read Aligned to Develop 200-Acre Data Center Campus
 Aligned to Develop 200-Acre Data Center Campus

Aligned to Develop 200-Acre Data Center Campus

July 25, 2025 Aligned

Aligned Data Centers this week announced plans to expand in Central Ohio with the development of a data center campus inside the Conesville Industrial Park in Coshocton. Coshocton is located approximately 63 miles (101 km) northeast of Columbus.Aligned will develop a 197-acre parcel adjacent to...

Read more
Read Aligned to proceed with stalled data center camps at Maryland
Aligned to proceed with stalled data center camps at Maryland

Aligned to proceed with stalled data center camps at Maryland

May 24, 2024 Aligned

Aligned Data Centers has revealed its plans to proceed with its previously halted data center campus in Maryland after recent regulatory changes. around backup generators, easing restrictions for data center firms. With this move, Aligned will now be moving ahead with its plans for a campus in...

Read more
Read Aligned Data Centres unveils new liquid cooling system
Aligned Data Centres unveils new liquid cooling system

Aligned Data Centres unveils new liquid cooling system

January 16, 2024 Aligned

Data center firm Aligned recently unveiled a new liquid cooling system designed to support high-density compute requirements and supercomputers and can cool densities up to 300kW per rack. This cooling system, called DataFlow is said to be a turnkey solution which supports current and future...

Read more
Read Alligned Reveals New Brownfield Land Acquisition for DC Campus in Ohio
Alligned Reveals New Brownfield Land Acquisition for DC Campus in Ohio

Alligned Reveals New Brownfield Land Acquisition for DC Campus in Ohio

September 28, 2023 Aligned

On September 25, 2023, Aligned Data Centers announced the acquisition of a new brownfield land in Perkins Township., Northeast Ohio. The firm purchased the 129-acre parcel to construct a new four-building hyperscale data center campus. Aligned said its NEO-01 data center, the first of the four...