Prime: AUS01-01

Latest Podcast 1395 Bobwhite Rd
Under Construction
New facility under construction
Operated by:

Prime: AUS01-01

Short Code: AUS01-01
Year Planned: 2027
Lot Size: 206 acres

Prime Data Centers is developing a new data center campus in Caldwell County, located outside of Austin, Texas. Tied to a 206-acre site previously known as "Project Snow," the full campus master plan is designed to deliver massive capacity across eight buildings totaling 2 million square feet.

The initial phase of the development represents a $400 million investment and features two buildings, designated as AUS01 and AUS02. Each of these first two facilities will span 380,000 square feet (35,303 square meters), bringing the initial physical footprint to 760,000 square feet. Construction on these structures is scheduled to begin in June 2026, with an estimated completion date in September 2027.

After first surfacing in early 2024, Prime Data Centers LLC secured county financial incentives in March 2024. While initial agreements provisionally pegged Phase 1 at $1.3 billion and 144 MW across three buildings, recent state filings have finalized the immediate scope to a $400 million, two-building configuration.

Map and Nearby Locations

1395 Bobwhite Rd
Prime Data Centers Sites
Nearby Facilities

Prime: AUS01-01 Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Prime: AUS01-01

Distance Site About
0.12 miles Prime: AUS01-03
The facility is a part of Prime's Austin Data Center Campus in Texas.
0.18 miles Prime: AUS01-02
The facility is a part of Prime's Austin Data Center Campus in Texas.
0.26 miles Prime: AUS01-05
The facility is a part of Prime's Austin Data Center Campus in Texas.
0.28 miles Prime: AUS01-04
The facility is a part of Prime's Austin Data Center Campus in Texas.
0.35 miles Prime: AUS01-06
The facility is a part of Prime's Austin Data Center Campus in Texas.
0.38 miles Prime: AUS01-07
The facility is a part of Prime's Austin Data Center Campus in Texas.
0.46 miles Prime: AUS01-08
The facility is a part of Prime's Austin Data Center Campus in Texas.
1.43 miles PowerHouse: Austin
PowerHouse Data Centers is planning a large-scale data center campus within the Caldwell Valley Technology Park near Uhland, Texas, expanding its presence in one of the fastest-growing digital infrastructure corridors between Austin and San Antonio.
1.43 miles Tract: Caldwell Valley
Tract plans to develop a data center park in Uhland, Texas, a city spanning Caldwell and Hays counties approximately 30 miles south of Austin.
5.57 miles Edged Energy: Martindale 2
This facility is part of Edged Energy's data center campus in Maxwell, within Caldwell County outside Austin, Texas.
6.58 miles Edged Energy: Martindale 1
Edged Energy is developing a massive, state-of-the-art data center campus outside Austin, Texas, designed to handle the intense power and infrastructure demands of modern artificial intelligence.
15.71 miles Park BetaInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
15.86 miles Sabey: San Macros, TX
Sabey, a US data center firm, plans to develop a new campus on 786 acres in San Marcos, Texas.
16.55 miles CloudBurst: San Marcos 12
This facility is part of CloudBurst's San Marcos Campus in Texas.
16.60 miles CloudBurst: San Marcos 11
This facility is part of CloudBurst's San Marcos Campus in Texas.
16.66 miles CloudBurst: San Marcos 10
This facility is part of CloudBurst's San Marcos Campus in Texas.
16.72 miles CloudBurst: San Marcos 9
This facility is part of CloudBurst's San Marcos Campus in Texas.
16.78 miles CloudBurst: San Marcos 8
This facility is part of CloudBurst's San Marcos Campus in Texas.
16.84 miles CloudBurst: San Marcos 7
This facility is part of CloudBurst's San Marcos Campus in Texas.
17.36 miles Highlander SM One: San Marcos, TX
A proposed $1.5 billion, 199-acre data center campus in San Marcos, Texas, was formally rejected by the City Council following strong local opposition centered on water usage and energy demand.
17.43 miles CloudBurst: San Marcos 6
This facility is part of CloudBurst's San Marcos Campus in Texas.
17.50 miles CloudBurst: San Marcos 5
This facility is part of CloudBurst's San Marcos Campus in Texas.
17.59 miles CloudBurst: San Marcos 4
This facility is part of CloudBurst's San Marcos Campus in Texas.
17.66 miles CloudBurst: San Marcos 3
This facility is part of CloudBurst's San Marcos Campus in Texas.
17.72 miles CloudBurst: San Marcos 2
This facility is part of CloudBurst's San Marcos Campus in Texas.
17.80 miles CloudBurst: San Marcos 1
CloudBurst, a new US data center developer focused on artificial intelligence (AI), is building a natural gas-powered facility in Texas.
18.77 miles EdgeConneX: AUS01
Located in the tech-forward Cedar Creek area of Bastrop County, EdgeConneX AUS01 is the high-performance anchor of a massive new data center campus.
18.82 miles EdgeConneX: AUS02
The upcoming AUS02 facility is designed as a massive two-story structure, set to encompass 578,000 square feet (approximately 54,000 square meters) of high-density data center space.
18.97 miles Lumen Austin 1 (4207 Smith School)
19.04 miles EdgeConneX: AUS11
EdgeConneX is developing two new 730,000 sq ft data centers, EDCAUS11 and EDCAUS12, in Bastrop County, Texas.
19.08 miles EdgeConneX: AUS03
This facility is part of the EdgeConneX data center campus in Bastrop, Texas.
19.10 miles EdgeConneX: AUS12
EdgeConneX is developing two new 730,000 sq ft data centers, EDCAUS11 and EDCAUS12, in Bastrop County, Texas.
19.14 miles Switch: Texas 1
Texas 1 is the first building on Switch's Data Ranch campus in southeast Austin. Data Foundry built the single-story, 130,000 sq ft data center in 2010-2011 with three data halls, and Switch bought it in 2021.
19.15 miles EdgeConneX: AUS04
This facility is part of the EdgeConneX data center campus in Bastrop, Texas.
19.19 miles Switch: Texas 2
Texas 2 is the second building on Switch's Data Ranch campus in southeast Austin. Data Foundry opened its first phase in 2018, and Switch bought it in 2021.
19.31 miles Switch: Texas 3
Texas 3 (AUS03) is Switch's planned third data center on the Data Ranch campus in southeast Austin, a building of about 300,000 sq ft on the campus's vacant eastern lots next to a planned Austin Energy substation.
19.34 miles LightEdge Austin2 Burleson
The site was formerly operated by OnRamp before being acquired in July 2018.
19.73 miles DataCanopy: Austin, TX
Data Canopy's Austin, TX facility delivers exceptional connectivity and 100% power uptime within a state-of-the-art environment secured by industry-leading features.
19.75 miles CyrusOne Austin II
Supports 250 wpsf with the ability to support over 1,000 wpsf Raised Floor: 48"
19.78 miles CyrusOne: Austin III
CyrusOne's AUS3 data center is projected to be the company's largest facility in Austin, spanning 172,000 total square feet, which includes 120,000 square feet of colocation space (CSF) and over 25,000 square feet of Class A office space.

Prime: AUS01-01 Data Center Photos See all

Rendering of Prime's LAX-01 facility
Source: Prime DC

Operating Company

Operated by:

Prime Data Centers develops, acquires, and operates data centers for large enterprises and hyper-scalers. Through our own properties, customer assets (sale-leaseback), or greenfield developments, Prime delivers build-to-suit, powered-shell and turn-key solutions.

0
Facilities
0
Markets

News See all

Read Big Watt, PowerHouse Win Taylor Approval for 1GW Texas Data Center Campus
Taylor City Council voted 5-0 on Oct. 8 to approve a development agreement with Big Watt Digital and PowerHouse Data Centers for the Taylor Technology Campus, a 664-acre hyperscale project immediat...

Big Watt, PowerHouse Win Taylor Approval for 1GW Texas Data Center Campus

October 15, 2026 PowerHouse Data Centers

Taylor City Council voted 5-0 on Oct. 8 to approve a development agreement with Big Watt Digital and PowerHouse Data Centers for the Taylor Technology Campus, a 664-acre hyperscale project immediately east of the city that could reach one gigawatt of capacity. The joint venture announced the...

Read more
Read Big Watt, PowerHouse Win Approval for 1GW Behind-the-Meter Texas Campus
Taylor City Council voted 5-0 on Oct. 8 to approve a development agreement with Big Watt Digital and PowerHouse Data Centers for Taylor Technology Campus, a 664-acre data center and power project e...

Big Watt, PowerHouse Win Approval for 1GW Behind-the-Meter Texas Campus

October 15, 2026 PowerHouse Data Centers

Taylor City Council voted 5-0 on Oct. 8 to approve a development agreement with Big Watt Digital and PowerHouse Data Centers for Taylor Technology Campus, a 664-acre data center and power project east of the city that could reach one gigawatt of capacity. In a joint press release, the partners...

Read more
Read Taylor Approves 1GW Gas-Fired Data Center Campus for Big Watt, PowerHouse
Taylor City Council voted 5-0 on Oct. 8 to annex and approve a development agreement for Taylor Technology Campus, a 664-acre hyperscale project east of Taylor that Big Watt Digital and PowerHouse ...

Taylor Approves 1GW Gas-Fired Data Center Campus for Big Watt, PowerHouse

October 15, 2026 PowerHouse Data Centers

Taylor City Council voted 5-0 on Oct. 8 to annex and approve a development agreement for Taylor Technology Campus, a 664-acre hyperscale project east of Taylor that Big Watt Digital and PowerHouse Data Centers say could support up to one gigawatt. The partners announced the approval in a Business...

Read more
Read Project Longhorn Files $366M First Building at Anthropic-Linked Texas Campus
The first data center building at the 2,842-acre Cedar Creek campus being developed by [Pacifico Energy](https://baxtel.com/data-centers/pacifico-energy) and [BlackChamber Group](https://baxtel.com...

Project Longhorn Files $366M First Building at Anthropic-Linked Texas Campus

October 11, 2026 Pacifico Energy

The first data center building at the 2,842-acre Cedar Creek campus being developed by Pacifico Energy and BlackChamber Group is on file with the Texas Department of Licensing and Regulation. The October 7 filing, reported by Community Impact, outlines a $366 million building at the Bastrop...

Read more
Read PDC Breaks Ground on Three Buildings at Phoenix Campus
PDC Breaks Ground on Three Buildings at Phoenix Campus

PDC Breaks Ground on Three Buildings at Phoenix Campus

May 22, 2026 Prime Data Centers

Prime Data Centers has broken ground on three of five buildings at its 240MW PHX01 campus in Phoenix. Each 267,000 sq ft facility will deliver 48MW of IT capacity, while the campus’ new 250MW substation is expected to provide 144MW of IT load in Phase I.The campus is being developed on a...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts

Ready to Level up Your
Data Center Strategy?