[Galaxy Digital](https://baxtel.com/data-centers/galaxy-digital) has filed to build a 349,594-square-foot data center building at its Helios campus near Afton, Texas. The registration with the Texa...

Galaxy Digital Files To Build 349,594 Sq Ft Helios 5 Data Center In Texas

Abdul-Rahman Oladimeji

Abdul-Rahman Oladimeji

November 27, 2026

Galaxy Digital has filed to build a 349,594-square-foot data center building at its Helios campus near Afton, Texas. The registration with the Texas Department of Licensing and Regulation lists the building as Helios 5 and puts its estimated construction cost at $1.3 billion, Data Center Dynamics reported. Galaxy Digital develops, owns, and operates the Helios campus. CoreWeave leases the claycorp.comFeatured: Wide editorial photograph showing active mission-critical data center construction and structural work at the Galaxy Digital Helios campus.campus's data halls and runs its own AI and high-performance computing capacity inside them under 15-year agreements.

Helios 5 is planned at 1003 FM 193 in Afton, in Dickens County about 60 miles from Lubbock. The one-story building is registered for construction from November 2026 to June 2028. Galaxy Helios II LLC is the owner of record, and Stantec Architecture is the design firm. The registration was filed on November 23, according to Texas Data Center Watch, an independent tracker of Texas records. A Galaxy spokesperson told KTSM that the state filings are routine steps for development in Texas: "These are routine regulatory steps required for commercial development in Texas," the spokesperson said.

CoreWeave has committed to the campus's capacity. Across Phases I through III, the company has leased 526MW of critical IT load, the full 800MW of gross power currently approved and contracted at Helios. Phase I delivered 133MW of critical IT load in July 2026, and greenfield work on 260MW of Phase II capacity is underway. Galaxy says the campus holds 1.63GW of approved power capacity across more than 2,200 acres, with potential to scale to as much as 3.6GW.

"Completing Phase I on budget and on schedule affirms Galaxy's position as an operator capable of executing hyperscale AI data center development," said Mike Novogratz, founder and CEO of Galaxy, in the company's July update.


Galaxy bought Helios from Argo Blockchain in December 2022 for about $65 million, after Argo opened the site as a bitcoin mine in 2022. CoreWeave signed its first 15-year lease at the campus in March 2025. Galaxy has said the leases are expected to generate more than $1 billion in average annual revenue.
Baxtel counts [38 data centers in the Lubbock market](https://baxtel.com/regions/lubbock), run by 20 providers. Galaxy Digital's [Helios HEL01](https://baxtel.com/data-center/galaxy-helios-hel01) is the market's largest at 133MW.

Phase II data hall deliveries are expected to begin in the first half of 2027, and the Helios 5 building is registered for completion in June 2028.