Read Galaxy Digital Files To Build 349,594 Sq Ft Helios 5 Data Center In Texas
[Galaxy Digital](https://baxtel.com/data-centers/galaxy-digital) has filed to build a 349,594-square-foot data center building at its Helios campus near Afton, Texas. The registration with the Texa...

Galaxy Digital Files To Build 349,594 Sq Ft Helios 5 Data Center In Texas

November 27, 2026 CoreWeave

Galaxy Digital has filed to build a 349,594-square-foot data center building at its Helios campus near Afton, Texas. The registration with the Texas Department of Licensing and Regulation lists the building as Helios 5 and puts its estimated construction cost at $1.3 billion, Data Center Dynamics...

Read more
Read Rolling Meadows Approves Digital Realty's 156MW Data Center Campus
Rolling Meadows backed a tax incentive on Nov. 24 for Digital Realty's 156MW data center, over objections from residents who packed the council chambers. Councilors voted 4-2 to support a Cook Coun...

Rolling Meadows Approves Digital Realty's 156MW Data Center Campus

November 25, 2026 Digital Realty Trust

Rolling Meadows backed a tax incentive on Nov. 24 for Digital Realty's 156MW data center, over objections from residents who packed the council chambers. Councilors voted 4-2 to support a Cook County Class 6b tax break for the project at 3800 Golf Road, CBS Chicago reported. The council also...

Read more
Read Cogent Sells Three Data Centers to I Squared's Saragon for $35M
[Cogent Communications](https://baxtel.com/data-centers/cogent-communications) agreed to sell three data centers to [Saragon](https://baxtel.com/data-centers/saragon) Infrastructure for $35 million...

Cogent Sells Three Data Centers to I Squared's Saragon for $35M

November 22, 2026 Cogent Communications

Cogent Communications agreed to sell three data centers to Saragon Infrastructure for $35 million in cash, Cogent's announcement said. Saragon is a portfolio company of I Squared Capital, and the facilities are in Omaha, Nebraska; Tacoma, Washington; and Cheyenne, Wyoming. Cogent expects the...

Read more
Read CyrusOne and KEP Top Out 48MW OSK1 Data Center in Japan
CyrusOne and Kansai Electric Power Company have [topped out OSK1](https://www.facebook.com/CyrusOne/posts/cyrusone-keps-first-data-center-in-japan-designed-to-deliver-48-mw-of-it-capacit/1631891085...

CyrusOne and KEP Top Out 48MW OSK1 Data Center in Japan

November 20, 2026 CyrusOne

CyrusOne and Kansai Electric Power Company have topped out OSK1, the first data center under their Japanese joint venture, at a planned 48MW of IT capacity. CyrusOne and KEP marked the structural completion this week with a traditional Jōtōshiki ceremony. CyrusOne KEP, the 50:50 joint venture the...

Read more
Read AMD Named Tenant for 5C's 160MW Project Phoenix Data Center
AMD is the intended end user of a proposed data center in Mount Carmel Township, [Pennsylvania](https://baxtel.com/regions/pennsylvania), under an executed lease agreement. The conditional use appl...

AMD Named Tenant for 5C's 160MW Project Phoenix Data Center

November 20, 2026 AMD

AMD is the intended end user of a proposed data center in Mount Carmel Township, Pennsylvania, under an executed lease agreement. The conditional use application on file with the township lists AMD as the tenant of the first building, The News-Item reported. The project, called Project Phoenix,...

Read more
Read TensorWave Signs Six-Year Deal To Supply OpenAI 457MW of AMD Capacity
TensorWave has signed a six-year agreement to supply OpenAI with 457MW of dedicated AI capacity across multiple [United States](https://baxtel.com/regions/united-states) data center sites, [the com...

TensorWave Signs Six-Year Deal To Supply OpenAI 457MW of AMD Capacity

November 17, 2026 OpenAI

TensorWave has signed a six-year agreement to supply OpenAI with 457MW of dedicated AI capacity across multiple United States data center sites, the company said. TensorWave deploys and operates the infrastructure, and OpenAI takes the full deployment as a single tenant under the contract. The...

Read more
Read Core Scientific to Exit Bitcoin Mining as Colocation Billing Reaches 485MW
Core Scientific plans to end Bitcoin mining by the end of 2026 and operate only as a high-density colocation provider in 2027. The Nasdaq-listed operator said in its [third-quarter 2026 results](ht...

Core Scientific to Exit Bitcoin Mining as Colocation Billing Reaches 485MW

November 16, 2026 Core Scientific

Core Scientific plans to end Bitcoin mining by the end of 2026 and operate only as a high-density colocation provider in 2027. The Nasdaq-listed operator said in its third-quarter 2026 results that it billed 485MW of colocation capacity at September 30, up from 395MW at the end of June....

Read more
Read Core Scientific Files $1.3B Plan for 285MW Hunt County Data Center
Core Scientific has registered a $1.3 billion plan to build a data center building at its [285MW Hunt County campus](https://baxtel.com/data-center/core-scientific-hunt-county-tx) outside Dallas. T...

Core Scientific Files $1.3B Plan for 285MW Hunt County Data Center

November 16, 2026 Core Scientific

Core Scientific has registered a $1.3 billion plan to build a data center building at its 285MW Hunt County campus outside Dallas. The filing with the Texas Department of Licensing and Regulation covers a 341,326 sq ft core-and-shell building at 4852 County Road 3507 in Quinlan, about 53 miles...

Read more
Read CoreWeave Tops 1.7GW Active Power As Backlog Reaches $132.5B
[CoreWeave](https://baxtel.com/data-centers/coreweave) added more than 200 MW of active power in the third quarter, lifting its live footprint past 1.7 GW. The neocloud [reported third-quarter resu...

CoreWeave Tops 1.7GW Active Power As Backlog Reaches $132.5B

November 12, 2026 CoreWeave

CoreWeave added more than 200 MW of active power in the third quarter, lifting its live footprint past 1.7 GW. The neocloud reported third-quarter results on Nov. 10 with revenue of $3.66 billion for the quarter ended Sept. 30, up 168 percent from a year earlier. The company said the gain doubled...

Read more
Read Georgia Residents File RICO Suit Against OpenAI Over 3.2GW Project Camellia
Three residents of Effingham County, [Georgia](https://baxtel.com/regions/georgia), sued [OpenAI](https://baxtel.com/data-centers/openai) and county officials on Nov. 6 over a 3.2-gigawatt data cen...

Georgia Residents File RICO Suit Against OpenAI Over 3.2GW Project Camellia

November 12, 2026 OpenAI

Three residents of Effingham County, Georgia, sued OpenAI and county officials on Nov. 6 over a 3.2-gigawatt data center project. The 44-page complaint, filed in Effingham County State Court, seeks compensatory and punitive damages and three times actual damages from the defendants named in its...

Read more
Read Riot Leases 910MW Corsicana Campus To Anthropic In $28B Deal
[Riot Platforms](https://baxtel.com/data-centers/riot-platforms) has signed a 15-year lease for its entire Corsicana data center campus in [Texas](https://baxtel.com/regions/texas), a contract valu...

Riot Leases 910MW Corsicana Campus To Anthropic In $28B Deal

November 10, 2026 Riot Platforms

Riot Platforms has signed a 15-year lease for its entire Corsicana data center campus in Texas, a contract valued at about $28 billion. The lease covers 910MW of critical IT capacity, and Bitcoin Magazine reports that Riot's 10-Q filing names the tenant as Anthropic PBC. Riot disclosed the...

Read more
Read Goodman and Digital Realty Launch A$715M Bid for 9.9% NEXTDC Stake
[Goodman Group](https://baxtel.com/data-centers/goodman-group) and [Digital Realty](https://baxtel.com/data-centers/digital-realty-trust) moved to buy up to 9.9% of Australian operator [NEXTDC](htt...

Goodman and Digital Realty Launch A$715M Bid for 9.9% NEXTDC Stake

November 05, 2026 Digital Realty Trust

Goodman Group and Digital Realty moved to buy up to 9.9% of Australian operator NEXTDC at a 45.5% premium to the previous close. The buyers offered A$9.50 a share through an aftermarket bookbuild, a purchase Reuters valued at about A$715 million (US$501 million) after reviewing the term sheet....

Read more
Read Google Backstops TeraWulf Debt for $19B Anthropic Campus in Kentucky
TeraWulf has secured Google as a credit backstop for the debt financing behind its Justified Data Campus in Hawesville, Kentucky ([TeraWulf press release](https://investors.terawulf.com/news-events...

Google Backstops TeraWulf Debt for $19B Anthropic Campus in Kentucky

November 05, 2026 Anthropic

TeraWulf has secured Google as a credit backstop for the debt financing behind its Justified Data Campus in Hawesville, Kentucky (TeraWulf press release). The campus carries a 20-year lease with Anthropic worth about $19 billion (Reuters). Baxtel reported in July that the company was seeking...

Read more
Read AMD Reports Record $13.4B Quarter as Data Center Revenue Climbs 97%
AMD reported record quarterly revenue of $13.4 billion, as data center sales nearly doubled from a year earlier. Revenue from the data center segment reached $8.5 billion, up 97%, and AMD guided to...

AMD Reports Record $13.4B Quarter as Data Center Revenue Climbs 97%

November 04, 2026 AMD

AMD reported record quarterly revenue of $13.4 billion, as data center sales nearly doubled from a year earlier. Revenue from the data center segment reached $8.5 billion, up 97%, and AMD guided to about $17 billion for the fourth quarter. The chip designer released the figures on November 3 in...

Read more
Read OpenAI Rebrands Data Centers as Compute Campuses After Midterm Rebuke
[OpenAI](https://baxtel.com/data-centers/openai) is now calling its data centers compute campuses, a change that arrived with a policy package published two days after the midterms. The company rel...

OpenAI Rebrands Data Centers as Compute Campuses After Midterm Rebuke

November 04, 2026 OpenAI

OpenAI is now calling its data centers compute campuses, a change that arrived with a policy package published two days after the midterms. The company released a National Community Compact and a Compute Campus Policy Blueprint on Nov. 5. The compact covers future campuses that OpenAI owns and...

Read more
Read Sabey Data Centers Pilots HVO Diesel Replacement at Austin Data Center
[Sabey Data Centers](https://baxtel.com/data-centers/sabey-data-centers) has started a pilot using hydrotreated vegetable oil (HVO) as a diesel replacement in backup generators at its Austin campus...

Sabey Data Centers Pilots HVO Diesel Replacement at Austin Data Center

October 30, 2026 Sabey Data Centers

Sabey Data Centers has started a pilot using hydrotreated vegetable oil (HVO) as a diesel replacement in backup generators at its Austin campus. The company is testing the renewable fuel as the primary fuel source for those generators, according to Sabey's announcement. Sabey says the pilot...

Read more
Read Anthropic Files For IPO, Disclosing $417B In Compute Commitments
Anthropic filed a registration statement for a Nasdaq initial public offering that discloses about $417 billion in future payments to compute providers. The [Form S-1](https://www.sec.gov/Archives/...

Anthropic Files For IPO, Disclosing $417B In Compute Commitments

October 27, 2026 Anthropic

Anthropic filed a registration statement for a Nasdaq initial public offering that discloses about $417 billion in future payments to compute providers. The Form S-1, filed with the U.S. Securities and Exchange Commission on Oct. 26, covers data centers, the computing equipment inside them and...

Read more
Read Verizon Signs $2B-Plus Dark Fiber Deal With AWS
[Verizon](https://baxtel.com/data-centers/verizon-enterprise) will supply dark fiber to Amazon Web Services ([AWS](https://baxtel.com/data-centers/amazon-aws)) under an agreement worth more than $2...

Verizon Signs $2B-Plus Dark Fiber Deal With AWS

October 27, 2026 Verizon Enterprise

Verizon will supply dark fiber to Amazon Web Services (AWS) under an agreement worth more than $2 billion, the carrier said on Oct. 26. Verizon disclosed the deal in its third-quarter results. The carrier provides the high-capacity fiber links, and AWS is the customer that uses that connectivity...

Read more
Read CoreWeave Brings 22.5MW Online at atNorth's Copenhagen Data Center
CoreWeave has brought most of its planned 22.5MW of IT capacity online at [atNorth](https://baxtel.com/data-centers/atnorth)'s [DEN01](https://baxtel.com/data-center/atnorth-den01) data center in t...

CoreWeave Brings 22.5MW Online at atNorth's Copenhagen Data Center

October 27, 2026 CoreWeave

CoreWeave has brought most of its planned 22.5MW of IT capacity online at atNorth's DEN01 data center in the Copenhagen metro, its first deployment in Denmark. The company announced the activation from London on October 27. atNorth owns and operates DEN01, a colocation site in Ballerup,...

Read more
Read Clayco and Kiewit Top Out First Building at Project Jupiter in New Mexico
Clayco and Kiewit New Mexico Co. topped out the 855,000-square-foot first building at Project Jupiter, a data center campus in Doña Ana County, [New Mexico](https://baxtel.com/regions/new-mexico). ...

Clayco and Kiewit Top Out First Building at Project Jupiter in New Mexico

October 27, 2026 OpenAI

Clayco and Kiewit New Mexico Co. topped out the 855,000-square-foot first building at Project Jupiter, a data center campus in Doña Ana County, New Mexico. The contractors placed the final structural beam atop the building, completing its primary structural framework, Clayco announced on October...

Read more