Core Scientific plans to end Bitcoin mining by the end of 2026 and operate only as a high-density colocation provider in 2027. The Nasdaq-listed operator said in its third-quarter 2026 results that it billed 485MW of colocation capacit
Featured: Exterior power and cooling infrastructure supporting Core Scientific's high-density computing campus.y at September 30, up from 395MW at the end of June. Colocation produced $215.4 million of quarterly revenue, about 92.5 percent of the total.
Core Scientific owns and operates the buildings and leases capacity to compute customers. CoreWeave has 590MW contracted across five Core Scientific campuses, with full delivery expected in early 2027. AMD holds 530MW under an agreement that combines direct AMD leases with leases to an AMD-backed neocloud operator. Billing for 485MW represented more than $700 million in average annualized colocation revenue, CryptoPotato reported.
Third-quarter revenue reached $232.9 million, up from $81.1 million a year earlier. Bitcoin mining revenue fell to $17.4 million from $66.2 million, split between $12.3 million of self-mining and $5.2 million of hosting for third parties. Adjusted EBITDA rose to $133.6 million from $41.1 million in the second quarter. Net income of $1.18 billion included a $1.034 billion non-cash gain from the revaluation of warrants and contingent value rights, and capital expenditure reached $985.1 million. Core Scientific sold 3,374 Bitcoin for $286.8 million in the first nine months of 2026 and held 32 Bitcoin, worth $2.7 million, at September 30.
The AMD capacity spans Pecos and Hunt County in Texas, Dalton in Georgia, Muskogee in Oklahoma, and Auburn in Alabama. Initial deliveries are scheduled for the first half of 2027, and the program is due for completion by the end of 2028. In August, Core Scientific closed its roughly $444 million acquisition of Polaris DS, adding about 40 acres and 440MW of grid-connected power beside its Muskogee campus. The company plans to expand that campus to 1.5GW of gross power.
"We expect to complete our exit from bitcoin mining by year-end," said Adam Sullivan, Chief Executive Officer at Core Scientific, on the November 5 earnings call, as Data Center Dynamics reported. Chief Financial Officer Jim Nygaard said the company had nearly 50 percent fewer miners online at the end of September than at the end of 2025. Sullivan said in the results release that Core Scientific is "nearing full delivery under our first colocation agreement while construction under our second is underway across five campuses."
Baxtel tracks 14 Core Scientific data center sites in the United States, nine of them operational.