Rowan Digital Infrastructure

Rowan Digital Infrastructure is a US data center developer that designs and delivers hyperscale campuses for large cloud and AI customers. The company is part of Quinbrook Infrastructure Partners and began in 2020 as a joint venture with Birch Infrastructure, and has been referred to as Rowan Green Data.

Its current US pipeline includes three campuses at the Quantum Frederick park in Maryland, the Cinco campus near San Antonio, Texas, a site in Temple, Texas, and the Percheron campus in Oregon. Verified capacity figures include a 300 MW Percheron plan in Morrow County, Oregon, and a 300 MW Cinco campus in Medina County, Texas.

Rowan Digital Infrastructure History:

  • In August 2025, broke ground on the 300 MW Cinco hyperscale campus outside San Antonio, Texas.
  • In February 2025, closed approximately $1.24 billion in construction financing for the second phase of its Maryland campus at TPG’s Quantum Frederick site.
  • Founded as Rowan Green Data in 2020 via a joint venture between Quinbrook Infrastructure Partners and Birch Infrastructure.

Rowan Digital Infrastructure Data Center Map

Rowan Digital Infrastructure Power Growth Over Time

+500% since 2022
Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Rowan Digital Infrastructure Locations

Rowan: AUS03

Austin

Rowan: AUS03 is the third building planned on Rowan Digital Infrastructure's Project Temple campus in east Temple, Texas, on the site the City of Temple calls the Lasso Building.

View Data Center

Rowan: Moriah DC

Austin

Former bitcoin mining data center in Temple's Synergy Park, Texas, that Rowan built for Rhodium. Rhodium left in late 2024, and Rowan began converting the building into a warehouse in January 2026.

View Data Center

Rowan: AUS04

Austin

Rowan: AUS04 is Rowan Digital Infrastructure's Project Stampede, a two-building data center campus under construction in Temple's Synergy Park, Texas.

View Data Center

Rowan Digital Infrastructure Data Center Photos See all

Rendering of Rowan's Temple facility scheduled to open in 2022
Source: Baxtel
Rendering of Rowan Digital's Project Temple in Texas
Source: Rowan Digital Infrastructure

Related News See all

Read Proper Voltage Launches 333kW Sodium-Ion UPS Cabinet With UNIGRID
Proper Voltage launched the Salt Vault battery cabinet on Nov. 19, with sodium-ion cells from UNIGRID for ![datocms-assets.com](/rails/active_storage/representations/proxy/eyJfcmFpbHMiOnsibWVzc2FnZ...

Proper Voltage Launches 333kW Sodium-Ion UPS Cabinet With UNIGRID

November 24, 2026 California

Proper Voltage launched the Salt Vault battery cabinet on Nov. 19, with sodium-ion cells from UNIGRID for data center uninterruptible power supply systems (GlobeNewswire). Proper Voltage, based in Carlsbad, California, designs and integrates the cabinet and supplies its battery operating system,...

Read more
Read Google Signs 50MW Superhot Geothermal PPA With Quaise in Oregon
Google will buy 50MW of superhot geothermal power from Quaise Energy's Project Obsidian in Central Oregon under a [power purchase agreement](https://www.quaise.com/news/quaise-energy-signs-50-mw-ge...

Google Signs 50MW Superhot Geothermal PPA With Quaise in Oregon

November 17, 2026 Oregon

Google will buy 50MW of superhot geothermal power from Quaise Energy's Project Obsidian in Central Oregon under a power purchase agreement announced Nov. 17. Quaise develops and operates Project Obsidian and will generate the electricity and sell it to Google under the agreement. The power is...

Read more
Read Dexter Introduces H.R. 11002 To Ban Data Centers On Federal Lands
[Oregon](https://baxtel.com/regions/oregon) Representative Maxine Dexter introduced a bill to ban new data centers on federal lands managed by the U.S. Forest Service and the Interior Department. T...

Dexter Introduces H.R. 11002 To Ban Data Centers On Federal Lands

November 16, 2026 Oregon

Oregon Representative Maxine Dexter introduced a bill to ban new data centers on federal lands managed by the U.S. Forest Service and the Interior Department. The Nov. 11 measure, H.R. 11002, is the Protecting Our Public Lands from Data Centers Act. It would block the development, sale, or...

Read more
Read California Resources and Bloom Energy Sign MOU For 1GW of California Fuel Cells
California Resources and Bloom Energy signed a [memorandum of understanding](https://www.globenewswire.com/news-release/2026/11/02/3393776/0/en/california-resources-corporation-announces-strategic-...

California Resources and Bloom Energy Sign MOU For 1GW of California Fuel Cells

November 03, 2026 California

California Resources and Bloom Energy signed a memorandum of understanding to jointly evaluate 1GW or more of solid-oxide fuel cell generation in California. The non-binding agreement names data centers, utilities, community choice aggregators, municipalities, and other industrial users as...

Read more
Read Sabey Data Centers Pilots HVO Diesel Replacement at Austin Data Center
[Sabey Data Centers](https://baxtel.com/data-centers/sabey-data-centers) has started a pilot using hydrotreated vegetable oil (HVO) as a diesel replacement in backup generators at its Austin campus...

Sabey Data Centers Pilots HVO Diesel Replacement at Austin Data Center

October 30, 2026 Austin

Sabey Data Centers has started a pilot using hydrotreated vegetable oil (HVO) as a diesel replacement in backup generators at its Austin campus. The company is testing the renewable fuel as the primary fuel source for those generators, according to Sabey's announcement. Sabey says the pilot...

Read more
Read PG&E Data Center Pipeline Reaches 12.87GW, Defers Load Beyond 1.8GW
PG&E's data center pipeline reached 12,870 MW in September, up from 12,710 MW at the end of June. The utility furnished the figures with its [third-quarter 2026 earnings materials](https://investor...

PG&E Data Center Pipeline Reaches 12.87GW, Defers Load Beyond 1.8GW

October 28, 2026 California

PG&E's data center pipeline reached 12,870 MW in September, up from 12,710 MW at the end of June. The utility furnished the figures with its third-quarter 2026 earnings materials on October 22. Large load beyond an initial 1.8 GW sits on a list of work that will be delayed or deferred....

Read more
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.