Starwood: Project Yellow (Granbury)

Latest Podcast 1015 Mitchell Bend Hwy
In Doubt
The development is facing regulatory or community opposition
Operated by:

Starwood: Project Yellow (Granbury)

Lot Size: 538 acres

Project Yellow is a proposed hyperscale data center development on about 538 acres in three parcels along Mitchell Bend Highway, next to the Wolf Hollow power plant south of Granbury. National CRE Holdings and Greenland Capital filed the concept plan with Hood County in February 2026, and a Starwood representative told residents that Starwood is the developer. The county did not act on the plan, a district court dismissed the developers' suit for automatic approval in July 2026, and their appeal is pending. A companion proposal, Project Red, covers the neighboring MARA mining site.

Site History

  • July 2026: A district court dismisses the developers' suit; they appeal.
  • February 2026: The concept plan is filed with Hood County.

Map and Nearby Locations

1015 Mitchell Bend Hwy
Starwood Digital Ventures Sites
Nearby Facilities

Sites within 15 miles of Starwood: Project Yellow (Granbury)

Distance Site About
1.00 miles Marathon Digital: Granbury, TX
MARA runs a bitcoin mining site beside Constellation's Wolf Hollow gas plant near Granbury, Hood County, Texas, which it bought in 2024.
3.30 miles Big Digital Energy: Hood County
Big Digital Energy and 10NetZero are converting the former Cowtown gas processing plant in Hood County, Texas, into an AI and HPC data center campus.
4.13 miles Valley OneInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
4.87 miles Pacifico Energy: Fort Spunky
Pacifico Energy proposed a data center and power campus near Fort Spunky in eastern Hood County, Texas; the county revoked its concept plan in March 2026 and Pacifico has sued.
5.50 miles Black Mountain: Glen Rose
Black Mountain Power plans a gas-fired power plant and a data center campus on about 460 acres along FM 56 north of Dinosaur Valley State Park, near Glen Rose, Texas.
7.12 miles Sailfish: Project Lion
Sailfish Investors' proposed two-building data center on 121 acres off Hill City Highway south of Tolar, Hood County, Texas, filed by affiliate Panther Generation LLC between the Comanche Circle tracts. Hood County denied its on-site permit in 2026.
7.47 miles Sailfish: Project Panther
Sailfish Investors' proposed four-building data center on 300 acres off Paluxy Highway (FM 51) south of Tolar, Hood County, Texas, filed by affiliate Panther Generation LLC between the Comanche Circle tracts. Hood County denied its on-site permit in 2026.
8.06 miles Sailfish: Comanche Circle Expansion
Later phases of Sailfish Investors' proposed Comanche Circle park: 27 planned buildings on a 969-acre central ranch tract and a 411-acre tract on Hill City Highway (FM 56), south of Tolar in Hood County.
8.13 miles Bilateral Energy: Project Patriot
Project Patriot is Bilateral Energy's proposed data center and power campus on the Knox Ranch west of Granbury, Hood County, Texas, now tied up by a residents' lawsuit.
8.86 miles Sailfish: Comanche Circle 1
First phase of Sailfish Investors' proposed Comanche Circle park: 18 planned buildings on a 721-acre ranch tract along Paluxy Highway (FM 51) south of Tolar, Hood County, beside the site NRG had proposed for an on-site gas plant.

Operating Company

Operated by:

Starwood Digital Ventures is a subsidiary of Starwood Capital Group. Starwood Capital Group is a private investment firm with a primary focus on global real estate. Founded in 1991 by Chairman and CEO Barry Sternlicht, Starwood Capital's hallmark is to invest opportunistically, moving between asset classes, geographies and positions in the capital stack as the firm perceives risk/return dynamics to be evolving. To execute this strategy, Starwood Capital has built up asset-class and geographic expertise in our target markets. In its pursuit of the most compelling opportunities globally, Starwood Capital has invested in more than 30 countries, ranging from the Americas to Europe to Asia. Starwood Capital is led by seasoned professionals who have successfully navigated all stages of the real estate investment cycle, with dedicated teams focused on acquisitions, asset management, capital markets, capital raising/investor relations and accounting.

0
Facilities
0
Markets

News See all

Read Fireworks Reserves $94.4M Nvidia B300 Capacity at Forum Edge AI Dallas Site
Fireworks has reserved three years of Nvidia B300 GPU capacity at Forum Edge AI's powered data center in Dallas. The 36-month agreement carries a combined total contract value of approximately $94....

Fireworks Reserves $94.4M Nvidia B300 Capacity at Forum Edge AI Dallas Site

October 26, 2026 Dallas

Fireworks has reserved three years of Nvidia B300 GPU capacity at Forum Edge AI's powered data center in Dallas. The 36-month agreement carries a combined total contract value of approximately $94.4 million, Forum Edge AI said on Oct. 26, reflecting GPU capacity and associated CPU management...

Read more
Read 2026 Is the Year Texas Passes Virginia in Data Center Capacity
[Texas](https://baxtel.com/data-center/texas) now has more data center capacity operating and under construction than [Virginia](https://baxtel.com/data-center/virginia). Baxtel tracks 28.3 GW buil...

2026 Is the Year Texas Passes Virginia in Data Center Capacity

October 13, 2026 Texas

Texas now has more data center capacity operating and under construction than Virginia. Baxtel tracks 28.3 GW built or building in Texas, against 17.8 GW in Virginia. On capacity already online, Virginia still leads, 12.3 GW to 11.1 GW. If projects scheduled for this year deliver on time, Texas...

Read more
Read PowerHouse Files Plans for 300MW Data Center Campus Near Dallas-Fort Worth
PowerHouse Data Centers is planning a new campus near Fort Worth, Texas. First reported by NBC, engineering firm Kimley-Horn has filed plans for a data center on about 88 acres in Westlake, north o...

PowerHouse Files Plans for 300MW Data Center Campus Near Dallas-Fort Worth

August 07, 2026 Dallas

PowerHouse Data Centers is planning a new campus near Fort Worth, Texas. First reported by NBC, engineering firm Kimley-Horn has filed plans for a data center on about 88 acres in Westlake, north of Fort Worth. The proposed site is at 13580 Denton Highway, near US Highway 377 and Westport...

Read more
Read DataBank Raises $2bn for Dallas Data Center Buildout
DataBank Raises $2bn for Dallas Data Center Buildout

DataBank Raises $2bn for Dallas Data Center Buildout

April 22, 2026 Dallas

US data center firm DataBank has secured new financing to support the build-out of three data centers in Dallas, Texas. The company this week announced it has obtained a $2 billion loan to fund construction of the first three facilities at its new Red Oak campus. DataBank said the deal represents...

Read more
Read MARA has Entered Into a Joint Venture Agreement with Starwood to Expand its US Data Center Portfolio
MARA has Entered Into a Joint Venture Agreement with Starwood to Expand its US Data Center Portfolio

MARA has Entered Into a Joint Venture Agreement with Starwood to Expand its US Data Center Portfolio

February 28, 2026 Starwood Digital Ventures

Marathon Digital Holdings (MARA) has signed a strategic agreement with Starwood Capital Group and its data center platform, Starwood Digital Ventures (SDV), to convert and expand selected sites for enterprise, hyperscale, and AI workloads. SDV will manage the design, development, tenant...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.