Skybox is developing PowerCampus Texas in the Wichita Falls Business Park, with Blue Owl as its partner. The master plan calls for up to 2 million sq ft of data center space on private on-site substations. The first building is due in late 2028, with more buildings following through 2031.
The campus's grid timing now turns on ERCOT's Batch Zero review. Texas set up that process in 2026 to sort the large loads already waiting in the interconnection queue.
Site History
- In October 2026, Skybox filed a complaint at the Public Utility Commission of Texas over ERCOT's classification of the campus load.
- In September 2026, ERCOT provisionally moved the campus out of the base-load group in its Batch Zero review.
- In May 2026, the Wichita Falls Economic Development Corporation approved the sale of about 171 more acres for Phase II.
- In February 2026, city leaders named Skybox as the buyer of the business park land.
- In October 2025, the Wichita Falls City Council approved the sale of the Phase I land.