Calatorao 1 (DC1) is the first of eight identical phase-1 buildings on QTS's Proyecto Rhodes campus in sector SUI-4, on the south-east side of the A-2 motorway at Calatorao, Zaragoza province, Aragon, Spain. Calanza Inmuebles S.L., a Blackstone-controlled company, is the promoter and landowner, and QTS will operate the campus. Each building has six data halls. The campus's own Rhodes 220/33 kV substation takes a mostly underground 220 kV connection from Red Eléctrica's Calatorao substation.
Earthworks on the DC1 and DC2 plots, the substation and the water basins began in October 2026, with Mercury Engineering as main contractor. The building projects still need their integrated environmental authorisation. QTS builds DC1 and DC2 first and adds the other buildings in sequence.
Site History
- Oct 2026: Earthworks began on the DC1 and DC2 plots.
- Sep 2026: The Gobierno de Aragón gave the general-interest plan partial definitive approval for urbanisation, the substation and external connections.
- Aug 2025: The general-interest plan received initial approval.
- Oct 2024: The Gobierno de Aragón declared Proyecto Rhodes an investment of regional interest.