Mainova Ventures into Data Centers With 30MW Facility in Frankfurt
October 27, 2022
Frankfurt
German data center provider Firstcolo is constructing a new €250 million facility in Rosbach vor der Höhe, near Frankfurt. The 11,555 sqm data center will offer up to 40kW rack densities and provide waste heat for potential local district heating systems.
| Distance | Site | About |
|---|---|---|
| 7.62 miles | Iron Mountain Frankfurt FRA-2 |
The facility was previously known as "Keppel DC Frankfurt 1 (KDC FRA 1)" before being acquired by Iron Mountain in July 2021.
|
| 7.64 miles | Carrier-Neutral Data Center Request Dataset |
Vantage is building another data center campus called FRA61 in Frankfurt.
|
| 7.67 miles | Carrier-Neutral Data Center Request Dataset | |
| 7.87 miles | Citigroup Frankfurt | |
| 8.68 miles | IBM Frankfurt | |
| 10.04 miles | Hyperscale Data Center Request Dataset |
AWS is expanding its Frankfurt-area footprint with a new data center in Schöneck, Hesse.
|
| 11.05 miles | Rackspace: FRA2 |
|
| 11.10 miles | Equinix Frankfurt FR2 |
Located in Frankfurt, Germany's capital, Equinix FR2 is a financial low latency trading hub where many financial market participants deploy to get a low latency edge.
|
| 11.16 miles | Equinix Frankfurt FR9x | |
| 11.35 miles | FirstColo: Werkhaus |
FirstColo's Werkhaus facility has a capacity for more than 1,000 racks across 1,200 sqm (12,917 sq ft) of technical space.
|
| 11.40 miles | Equinix Frankfurt FR11x | |
| 11.42 miles | Equinix FR13 |
Equinix launched FR13 data center in Frankfurt, Germany. Located within Equinix’s Frankfurt North-East campus, the data center was first announced in November 2023.
|
| 11.56 miles | Mainova: Gwinnerstrasse |
Mainova's new facility offers 10,500 square meters (113,000 sq ft) of space across two buildings.
|
| 11.59 miles | Mainova: Gwinnerstrasse 2 |
Mainova's new facility offers 10,500 square meters (113,000 sq ft) of space across two buildings.
|
| 11.75 miles | Iron Mountain Frankfurt FRA-1 |
Iron Mountain developed FRA-1 thanks to a joint venture with AGC Equity Partners and in 2021 added FRA-2 through acquisition.
|
| 11.75 miles | maincubes: FRA02 |
Maincubes opened its second Frankfurt data center in 2024. The FRA02 facility offers 4,700 sqm of IT white space.
|
| 11.81 miles | Data Castle: Frankfurt 1 |
Data Castle has started construction on its first data center in the town of Schwalbach am Taunus, just outside of Frankfurt.
|
| 11.94 miles | maincubes: FRA03 |
maincubes is building its third data center in Frankfurt. The 27,000 sqm (290,600 sq ft) FRA03 will offer 7,500 sqm of white space across three floors and 6 data halls.
|
| 11.94 miles | EdgeConneX: Maintal Campus |
In Germany’s tightening data center market, EdgeConneX is making a strategic push into the Frankfurt metropolitan area with a proposed campus in Maintal.
|
| 12.36 miles | nLighten Frankfurt | |
| 12.36 miles | Colt Frankfurt City |
|
| 12.38 miles | Digital Realty: FRA18 |
FRA18 offers 8,200 square meters of colocation space specifically designed to support high-performance computing (HPC) and artificial intelligence (AI) workloads.
|
| 12.43 miles | Digital Realty: Digital Park Fechenheim |
Digital Realty is building a massive new campus in Digital Park Fechenheim, the former headquarters of the Neckermann mail-order company.
|
| 12.44 miles | Carrier-Neutral Data Center Request Dataset |
Construction of FRA27 started in 2022 and topped out in 2023. The facility features an IT area of around 4,700 square meters, alongside four white spaces for colocation.
|
| 12.46 miles | Digital Realty: FRA20 |
FRA20, a new data center, is part of the Digital Realty's Digital Park Fechenheim campus in eastern Frankfurt, Germany. This five-level facility will offer approximately 8,140 square meters of white space.
|
| 12.46 miles | Digital Realty: FRA23 | |
| 12.48 miles | Global Switch: Frankfurt North |
Global Switch's Frankfurt campus – comprising two data centers – Frankfurt North (launched in 2019) and Frankfurt South, is located close to the financial district, city center, and Frankfurt International Airport, which is just 15 minutes away by car.
|
| 12.51 miles | Global Switch: Frankfurt South |
Global Switch's Frankfurt campus – comprising two data centers – Frankfurt North (launched in 2019) and Frankfurt South, is located close to the financial district, city center, and Frankfurt International Airport, which is just 15 minutes away by car.
|
| 12.52 miles | Hyperscale Data Center Request Dataset | |
| 12.54 miles | Colt: Frankfurt 1 |
The site is in Frankfurt city center which is a prime location for data centres.
|
| 12.60 miles | NTT Frankfurt 1 Campus |
The almost 54,000 sqm campus, which is owned by e-shelter, offers space for five free-standing buildings
|
| 12.60 miles | Digital Realty: FRA5 |
|
| 12.61 miles | Digital Realty: FRA2 |
|
| 12.62 miles | Digital Realty Frankfurt Campus |
Digital Realty, formerly known as Interxion, has a significant presence in Frankfurt with a campus that has the densest concentration of networks in the city.
|
| 12.62 miles | Digital Realty: FRA6 |
In 2018, Interxion (now Digital Realty) expanded its FRA6 data center in Frankfurt, Germany, by 400 sqm at a cost of €5 million.
|
| 12.63 miles | Digital Realty: FRA16 |
|
| 12.65 miles | Digital Realty: FRA12 |
FRA12 provides approximately 1,100 square meters of equipped space. The capital expenditure associated with FRA12 is approximately €19 million.
|
| 12.66 miles | Digital Realty: FRA7 |
|
| 12.66 miles | Digital Realty: FRA13 |
FRA13 was constructed in two phases, providing 4,800 sqm of equipped space. The capital expenditure associated with FRA13 was approximately €90 million.
|
| 12.66 miles | Digital Realty: FRA9 |
Digital Realty's FRA9 is located within the Frankfurt Campus.
|
| 12.67 miles | Digital Realty: FRA11 |
|
| 12.68 miles | Digital Realty: FRA10 |
|
| 12.68 miles | Digital Realty: FRA3 |
Digital Realty, formerly Interxion, has been operating its third data center in Frankfurt, Germany, FRA3, since 2000.
|
| 12.69 miles | Hyperscale Data Center Request Dataset | |
| 12.70 miles | Digital Realty: FRA8 |
FRA 8 was built in four phases, with each phase providing approximately 900 square meters of equipped space. The facility was commissioned in 2014.
|
| 12.70 miles | Digital Realty: FRA4 |
|
| 12.70 miles | Digital Realty: FRA15 |
FRA15 was built in four phases, providing in total 9,600 square meters of equipped space. The capital expenditure was expected to be around €175 million for the full build-out.
|
| 12.72 miles | Digital Realty: FRA14 |
FRA14 was constructed in two phases with 5,000 sqm of equipped space. The total capital expenditure associated with FRA14 was €76 million.
|
| 12.75 miles | Equinix Frankfurt FR1 | |
| 12.79 miles | NTT Frankfurt 2 |
|
| 12.81 miles | FirstColo: Frankfurt Hanauer (AOC) |
The firstcolo data center AOC, located on Hanauer Landstraße in Frankfurt am Main, offers a capacity of 390 racks, accommodating approximately 7,500 server systems.
|
| 12.88 miles | CyrusOne Frankfurt I |
|
| 12.88 miles | CyrusOne Frankfurt II |
The facility was previously known as Zenium Frankfurt Two.
|
| 12.89 miles | Digital Realty FRA32 | |
| 12.89 miles | Digital Frankfurt Sossenheim |
Located within an established data centre hub to the north west of Frankfurt, Digital Frankfurt – Wilhelm Fay Strasse provides a campus of 3 buildings, totaling 180,000 sqft. of net technical space. Each building provides 6 data suites of 10,000 sqft (Net space), together with 60,000 sq. ft. of ancillary space including dedicated offices, de-box rooms, test rooms and dedicated plant areas.
|
| 12.89 miles | Digital Realty FRA31 | |
| 12.90 miles | Aroundtown: Frankfurt |
German real estate company Aroundtown aims to repurpose the "tricubes" building at Wilhelm-Fay-Straße 30-34, a four-story office complex built in 2003 that previously housed IBM.
|
| 12.90 miles | CyrusOne Frankfurt FRA3 |
|
| 12.92 miles | Cyrusone FRA6 |
FRA6 will offer a total IT capacity of 72MW over four floors, with each level delivering 18MW.
|
| 12.94 miles | CyrusOne Frankfurt IV | |
| 12.96 miles | Colt Frankfurt West |
Colt's new data center in Sossenheim is under construction and will be delivered in Q4 2021
|
| 12.96 miles | Digital Realty FRA29 | |
| 13.03 miles | Colt Frankfurt Three |
|
| 13.12 miles | NorthC: Frankfurt |
European data center firm NorthC has acquired a plot of land in Frankfurt and commenced the development of a new data center.
|
| 13.12 miles | NorthC: Frankfurt II |
European data center company NorthC is expanding its presence in Germany by building a second facility in Frankfurt, set to open in 2026.
|
| 13.12 miles | Crypto Mining Data Center Request Dataset |
Northern Data AG’s Frankfurt am Main data center was launched in December 2020,
|
| 13.12 miles | Edged Energy: Frankfurt |
Edged Energy plans to build a data center in Frankfurt, Germany.
|
| 13.38 miles | Vantage: FRA1 Bldg 3 | |
| 13.41 miles | Keppel Maincubes Frankfurt |
|
| 13.41 miles | maincubes FRA01 |
The IT area is 4,200sqm, on three levels with two IT rooms of 700 sqm each
|
| 13.41 miles | Vantage: FRA1 Bldg 2 |
Vantage's second building FRA12 is located at its Offenbach data center campus in Frankfurt, Germany.
|
| 13.44 miles | Vantage FRA1 |
The facility was acquired from Etix Everywhere in 2020. Vantage announced that it had acquired full ownership of the first data center, buying out its joint venture partners Energieversorgung Offenbach (EVO) and DataCenter-Group (DCG).
|
| 13.65 miles | euNetworks Frankfurt | |
| 14.03 miles | NorthC: Frankfurt III |
The NorthC Frankfurt 3 data center is a strategic colocation facility situated in the heart of Frankfurt's digital district.
|
| 14.14 miles | Equinix FR16 | |
| 14.15 miles | NewTelco Frankfurt (Rebstöckerstrasse) | |
| 14.15 miles | CloudHQ: FRA-02 |
CloudHQ, a hyperscale data center developer and operator in the United States and Europe, is currently constructing a 1.2 million sqft (108k sqm), hyperscale data center campus in Offenbach, Germany, a city which borders Frankfurt to the southeast.
|
| 14.19 miles | CloudHQ: Offenbach Campus |
CloudHQ, a hyperscale data center developer and operator in the United States and Europe, is currently constructing a 1.2 million sqft (108k sqm), hyperscale data center campus in Offenbach, Germany, a city which borders Frankfurt to the southeast.
|
| 14.22 miles | ITENOS Frankfurt | |
| 14.22 miles | Equinix Frankfurt FR5 |
|
| 14.23 miles | Hyperscale Data Center Request Dataset | |
| 14.25 miles | INAP FRA Gutleutstraße 310 | |
| 14.26 miles | Equinix Frankfurt FR7 | |
| 14.42 miles | Telehouse: Frankfurt Campus |
A major 2026 expansion is planned for the Telehouse campus, bringing the total number of facilities to six.
|
| 14.42 miles | Telehouse: FRA Bldg-C |
This facility is part of Telehouse Germany's Frankfurt campus.
|
| 14.42 miles | Verizon Frankfurt | |
| 14.45 miles | Telehouse: FRA Bldg-D |
This facility is part of Telehouse Germany's Frankfurt campus.
|
| 14.45 miles | Telehouse: FRA Bldg-M |
This facility is part of Telehouse Germany's Frankfurt campus.
|
| 14.45 miles | Telehouse: FRA Bldg-B |
This facility is part of Telehouse Germany's Frankfurt campus.
|
| 14.47 miles | Telehouse: FRA Bldg-N |
This facility is part of Telehouse Germany's Frankfurt campus.
|
| 14.76 miles | Equinix Frankfurt FR4 FR6 |
|
| 14.79 miles | Aruba: Germany DE1 |
The data center is equipped with autonomous power generators with underground fuel tanks able to provide energy to the entire data center even at full capacity.
|
| 14.82 miles | Equinix Frankfurt FR8 |
Located in the Lärchenstrasse Campus, FR8 data center provides secure, resilient colocation services covered by 100% renewable energy.
|
| 14.96 miles | FKQ I Data Center | |
| 15.17 miles | CyrusOne Frankfurt FRA7 |
Construction is currently underway for the FRA7 data center campus, with first phase expected to be operational by Q2 2026.
|
| 15.30 miles | Hyperscale Data Center Request Dataset |
In 2020, Google acquired 11.6 hectares of land in Zum Fliegerhorst, Germany.
|
| 15.39 miles | STACK FRAL1 |
In 2022, STACK acquired the 17-acre site from Coca-Cola Europacific Partners Deutschland GmbH (CCEP DE), who operated a bottling and distribution plant at the location for more than 50 years.
|
| 15.44 miles | Digital Lyoner Strasse 28 |
|
| 15.44 miles | Rackspace Frankfurt FRA1 |
Rackspace maintains a small data center in Frankfurt
|
| 16.62 miles | CloudHQ: FRA05 |
The facility will be located at CloudHQ's Höchst Campus (FRA03) in Frankfurt, Germany.
|
| 16.71 miles | CloudHQ: FRA04 |
The facility will be located at CloudHQ's Höchst Campus (FRA03) in Frankfurt, Germany.
|
| 16.74 miles | CloudHQ: Hochst Campus FRA03 |
CloudHQ's second Frankfurt-area campus is strategically located west of the Frankfurt metro, on the Höchst campus.
|
| 16.80 miles | CyrusOne Frankfurt V |
CyrusOne has broken ground on its fifth data center in Frankfurt, FRA5. FRA5 is located in Hanau, 25km east of Frankfurt's city center.
The facility will span 18,000 sqm (193,750 sq ft) across two buildings. |
| 17.02 miles | EdgeConneX: Heusenstamm |
EdgeConneX plans a €600 million investment in Heusenstamm, near Frankfurt, Germany, to build two data centers.
|
| 17.48 miles | Hyperscale Data Center Request Dataset |
Google has opened its first data centre in Hanau, Germany.
|
| 17.78 miles | Goodman: FRA02-B |
This facility is part of Goodman Group's Frankfurt II campus in Frankfurt.
|
| 17.85 miles | Goodman: FRA II Campus |
The former printing plant of the German newspaper Frankfurter Rundschau is being transformed into a state-of-the-art powered shell data centre campus situated just south of Frankfurt.
|
| 18.32 miles | Data4: Frankfurt |
French data center firm Data4 is building a huge campus in Hanau, Germany.
|
| 18.37 miles | Data4: Frankfurt DC2 |
This data center is a part of Data4's Frankfurt Campus in Germany.
|
| 18.41 miles | Data4: Frankfurt DC3 |
This data center is a part of Data4's Frankfurt Campus in Germany.
|
| 18.44 miles | Data4: Frankfurt DC7 |
This data center is a part of Data4's Frankfurt Campus in Germany.
|
| 18.45 miles | Data4: Frankfurt DC4 |
This data center is a part of Data4's Frankfurt Campus in Germany.
|
| 18.48 miles | Data4: Frankfurt DC5 |
This data center is a part of Data4's Frankfurt Campus in Germany.
|
| 18.50 miles | Data4: Frankfurt DC8 |
This data center is a part of Data4's Frankfurt Campus in Germany.
|
| 18.53 miles | Data4: Frankfurt DC6 |
This data center is a part of Data4's Frankfurt Campus in Germany.
|
| 18.72 miles | Keppel Kelsterbach |
The data centre has a total lettable area of approximately 540,869 sqft, and fully leased on a triple-net basis until the end of 2025.
|
| 18.90 miles | NTT Frankfurt 4 |
|
| 19.81 miles | Digital Realty: FRA 34 |
Digital Realty's FRA33 and FRA34 facilities are situated within Digital's new campus on Kastengrund (known as Digital Park Hattersheim).
|
| 19.84 miles | maincubes: FRA04 |
Located in the Rhine-Main metropolitan area, south of Frankfurt in Dietzenbach, FRA04 will provide approximately 12,500 square meters (134,548 sq ft) of whitespace.
|
| 19.85 miles | EdgeConneX: Frankfurt EDCFRA01 |
The EdgeConneX EDCFRA01 data center in Dietzenbach is a high-density facility currently under construction on a 3.6-hectare campus.
|
| 19.92 miles | Digital Realty: Hattersheim FRA33 |
Digital Realty's FRA33 and FRA34 facilities are situated within Digital's new campus on Kastengrund (known as Digital Park Hattersheim).
|
Firstcolo establishes itself as a dedicated B2B data center operator. The company prioritizes high availability and secure IT solutions, encompassing IT outsourcing, managed hosting, DDoS protection, and network security. Leveraging a diverse range of manufacturers, Firstcolo delivers IT projects tailored to client budgets and needs. They provide premium data center space, hardware, and IT components within their own high-performance facilities. Clients benefit from a flexible, scalable infrastructure, exceeding industry standards, to support their IT projects, server, storage, and backup systems, ensuring long-term availability and quality.
October 27, 2022
Frankfurt
August 08, 2022
Frankfurt
May 17, 2022
Frankfurt
May 14, 2021
Frankfurt
Mar 12, 2026
Eric Bell
World
Feb 05, 2026
Eric Bell
World
Jan 15, 2026
Eric Bell
Applied Digital
Jan 05, 2026
Eric Bell
Dallas
Sep 04, 2025
Eric Bell
Texas