Read Giga Energy Signs $1B, 10-Year Lease for 60MW Hunt County Data Center
Giga Energy has signed a 10-year lease worth about $1 billion at its Project Clay data center in Hunt County, Texas. The agreement, [announced](https://www.gigaenergy.com/news/giga-news-hunt-county...

Giga Energy Signs $1B, 10-Year Lease for 60MW Hunt County Data Center

November 18, 2026 Dallas

Giga Energy has signed a 10-year lease worth about $1 billion at its Project Clay data center in Hunt County, Texas. The agreement, announced on November 17, covers 60MW of capacity for an undisclosed U.S.-based AI cloud provider. Giga Energy develops, owns, and operates the campus, Reuters...

Read more
Read Loudoun County Adopts 12-Month Pause on Data Center and Substation Approvals
Loudoun County supervisors adopted a resolution on Nov. 17 to halt board action on data center and substation applications for up to 12 months. The vote was 7-1, with Supervisor Kristen Umstattd op...

Loudoun County Adopts 12-Month Pause on Data Center and Substation Approvals

November 18, 2026 Ashburn: Data Center Alley

Loudoun County supervisors adopted a resolution on Nov. 17 to halt board action on data center and substation applications for up to 12 months. The vote was 7-1, with Supervisor Kristen Umstattd opposed and Supervisor Caleb Kershner abstaining, according to Loudoun Now. The pause runs from Sept....

Read more
Read Equinix Affiliate Files for $500M DA13 Data Center in Dallas
An affiliate of [Equinix](https://baxtel.com/data-centers/equinix) has filed with the Texas Department of Licensing and Regulation to build DA13, a $500 million data center in Dallas. The applicati...

Equinix Affiliate Files for $500M DA13 Data Center in Dallas

November 16, 2026 Dallas

An affiliate of Equinix has filed with the Texas Department of Licensing and Regulation to build DA13, a $500 million data center in Dallas. The application puts a four-story, 372,445-square-foot building at 1520 West Mockingbird Lane, in an industrial area near Love Field, as Data Center...

Read more
Read New Jersey Senate Passes 38-0 Bill Banning Data Center NDAs
The New Jersey Senate voted 38-0 on October 22 to make nondisclosure agreements around data center projects unenforceable in the state. [Senate Bill 4304](https://www.njleg.state.nj.us/bill-search/...

New Jersey Senate Passes 38-0 Bill Banning Data Center NDAs

November 09, 2026 New Jersey

The New Jersey Senate voted 38-0 on October 22 to make nondisclosure agreements around data center projects unenforceable in the state. Senate Bill 4304 has moved to the Assembly, where it was referred to the Science, Innovation and Technology Committee. The bill bars data center applicants and...

Read more
Read ZutaCore Unveils Two-Phase Matrix Flow Boiling for AI Cold Plates
ZutaCore unveiled Two-Phase Matrix Flow Boiling, the cooling architecture inside its OmniTherm cold plate family, at OCP Global Summit 2026 on Oct. 13. The Foster City, California, company builds w...

ZutaCore Unveils Two-Phase Matrix Flow Boiling for AI Cold Plates

October 26, 2026 San Francisco Bay Area

ZutaCore unveiled Two-Phase Matrix Flow Boiling, the cooling architecture inside its OmniTherm cold plate family, at OCP Global Summit 2026 on Oct. 13. The Foster City, California, company builds waterless, direct-to-chip two-phase liquid cooling for AI and high-performance computing servers. The...

Read more
Read Fireworks Reserves $94.4M Nvidia B300 Capacity at Forum Edge AI Dallas Site
Fireworks has reserved three years of Nvidia B300 GPU capacity at Forum Edge AI's powered data center in Dallas. The 36-month agreement carries a combined total contract value of approximately $94....

Fireworks Reserves $94.4M Nvidia B300 Capacity at Forum Edge AI Dallas Site

October 26, 2026 Dallas

Fireworks has reserved three years of Nvidia B300 GPU capacity at Forum Edge AI's powered data center in Dallas. The 36-month agreement carries a combined total contract value of approximately $94.4 million, Forum Edge AI said on Oct. 26, reflecting GPU capacity and associated CPU management...

Read more
Read Uniserve Targets Q4 2026 Launch for 1MW Vancouver Data Center
[Uniserve Communications](https://baxtel.com/data-centers/uniserve-communications) will open a new Vancouver data center in the fourth quarter of 2026, starting with 1MW of capacity. The roughly 10...

Uniserve Targets Q4 2026 Launch for 1MW Vancouver Data Center

October 22, 2026 Vancouver

Uniserve Communications will open a new Vancouver data center in the fourth quarter of 2026, starting with 1MW of capacity. The roughly 10,000-square-foot VAN-2 facility at 369 Terminal Avenue sits beside the operator's existing site and will support up to 30kW per rack, Uniserve said in an...

Read more
Read Amazon Drops 800,000 Sq Ft Data Center Campus In Loudoun County Deal
Amazon Data Services has withdrawn its application to build four data centers on the former George Washington University campus in Ashburn, Virginia, ending a months-long standoff with Loudoun Coun...

Amazon Drops 800,000 Sq Ft Data Center Campus In Loudoun County Deal

October 21, 2026 Ashburn: Data Center Alley

Amazon Data Services has withdrawn its application to build four data centers on the former George Washington University campus in Ashburn, Virginia, ending a months-long standoff with Loudoun County. Officials announced the agreement, called Project Potomac Promise, at the Oct. 20 Board of...

Read more
Read LightEdge Considers Data Center Project Near Des Moines, Iowa
LightEdge plans to develop a colocation data center on ten acres in Boone Business Park, Iowa, about 48 miles northwest of Des Moines.
The Boone County Economic Growth Corporation has signed a let...

LightEdge Considers Data Center Project Near Des Moines, Iowa

October 16, 2026 Iowa

LightEdge plans to develop a colocation data center on ten acres in Boone Business Park, Iowa, about 48 miles northwest of Des Moines. The Boone County Economic Growth Corporation has signed a letter of intent for the land sale. The city’s planning commission has approved the site plan for...

Read more
Read 2026 Is the Year Texas Passes Virginia in Data Center Capacity
[Texas](https://baxtel.com/data-center/texas) now has more data center capacity operating and under construction than [Virginia](https://baxtel.com/data-center/virginia). Baxtel tracks 28.3 GW buil...

2026 Is the Year Texas Passes Virginia in Data Center Capacity

October 13, 2026 Dallas

Texas now has more data center capacity operating and under construction than Virginia. Baxtel tracks 28.3 GW built or building in Texas, against 17.8 GW in Virginia. On capacity already online, Virginia still leads, 12.3 GW to 11.1 GW. If projects scheduled for this year deliver on time, Texas...

Read more
Read New Jersey Fines DataOne $1.07M Over Unpermitted Vineland Generators
Newly obtained public records show that a 300-megawatt data center under construction in Vineland, New Jersey, ran 62 unpermitted natural gas generators for nearly a year and released an estimated ...

New Jersey Fines DataOne $1.07M Over Unpermitted Vineland Generators

October 04, 2026 New Jersey

Newly obtained public records show that a 300-megawatt data center under construction in Vineland, New Jersey, ran 62 unpermitted natural gas generators for nearly a year and released an estimated 140 tons of smog-forming nitrogen oxides before state regulators intervened, according to an...

Read more
Read NetworkOcean Runs Solar-Powered GPU Data Center on San Francisco Bay
San Francisco startup NetworkOcean says it has become the first company to run customer AI workloads from a solar-powered floating data center. The company operated a single Nvidia H100 GPU powered...

NetworkOcean Runs Solar-Powered GPU Data Center on San Francisco Bay

October 03, 2026 San Francisco Bay Area

San Francisco startup NetworkOcean says it has become the first company to run customer AI workloads from a solar-powered floating data center. The company operated a single Nvidia H100 GPU powered by a 20kW solar array during a trial in San Francisco Bay. The customer was not disclosed....

Read more
Read PowerHouse Files Plans for 300MW Data Center Campus Near Dallas-Fort Worth
PowerHouse Data Centers is planning a new campus near Fort Worth, Texas. First reported by NBC, engineering firm Kimley-Horn has filed plans for a data center on about 88 acres in Westlake, north o...

PowerHouse Files Plans for 300MW Data Center Campus Near Dallas-Fort Worth

August 07, 2026 Dallas

PowerHouse Data Centers is planning a new campus near Fort Worth, Texas. First reported by NBC, engineering firm Kimley-Horn has filed plans for a data center on about 88 acres in Westlake, north of Fort Worth. The proposed site is at 13580 Denton Highway, near US Highway 377 and Westport...

Read more
Read Data Centre Developer Sues New Jersey Town for $300m
Data centre developer Hexa Builders is seeking $300 million in damages from Monroe Township, New Jersey, after officials rejected its proposed 1 million sq ft data centre in May. The lawsuit, filed...

Data Centre Developer Sues New Jersey Town for $300m

July 30, 2026 New Jersey

Data centre developer Hexa Builders is seeking $300 million in damages from Monroe Township, New Jersey, after officials rejected its proposed 1 million sq ft data centre in May. The lawsuit, filed in New Jersey Superior Court, alleges the township council and planning board violated multiple...

Read more
Read 46-Acre Data Center Campus Planned in Maquoketa, Iowa
An unnamed company is planning a data center campus on a 46-acre site off Highway 61, south of Maquoketa in eastern Iowa, according to local media reports from WQAD News 8 and KWQC 6.

Maquoketa,...

46-Acre Data Center Campus Planned in Maquoketa, Iowa

July 07, 2026 Iowa

An unnamed company is planning a data center campus on a 46-acre site off Highway 61, south of Maquoketa in eastern Iowa, according to local media reports from WQAD News 8 and KWQC 6. Maquoketa, in eastern Iowa's Jackson County, is being considered for a small- to mid-sized data center campus...

Read more
Read New Jersey Lawmakers Approve Bill Creating Large Load Data Center Tariff
New Jersey lawmakers have passed a bill directing the state’s Board of Public Utilities to create a dedicated tariff for data centers with capacities of 50MW or more, aimed at protecting other rate...

New Jersey Lawmakers Approve Bill Creating Large Load Data Center Tariff

July 03, 2026 New Jersey

New Jersey lawmakers have passed a bill directing the state’s Board of Public Utilities to create a dedicated tariff for data centers with capacities of 50MW or more, aimed at protecting other ratepayers from rising costs linked to new developments. The legislation, S731, replaces an earlier...

Read more
Read 900-Acre Data Center Proposed for Salix, Iowa
A 900-acre data center campus could be developed in Salix, Iowa, as MidAmerican evaluates a recently annexed site for the project. In a June 8 letter to the Salix City Council, the energy company s...

900-Acre Data Center Proposed for Salix, Iowa

June 29, 2026 Iowa

A 900-acre data center campus could be developed in Salix, Iowa, as MidAmerican evaluates a recently annexed site for the project. In a June 8 letter to the Salix City Council, the energy company said the 900-acre parcel, bounded by Old Highway 75, 260th Street, and Charles Avenue, is being...

Read more
Read Iowa Data Center with 1.6MW Capacity Hits Market for $4M
A 1.6MW data center in Ames, Iowa, has been put on the market for $4 million. The 15,510 sq ft (1,440 sqm) facility sits on a 63,655 sq ft (5,915 sqm) site at 1205 Buckeye Avenue and includes two d...

Iowa Data Center with 1.6MW Capacity Hits Market for $4M

June 15, 2026 Iowa

A 1.6MW data center in Ames, Iowa, has been put on the market for $4 million. The 15,510 sq ft (1,440 sqm) facility sits on a 63,655 sq ft (5,915 sqm) site at 1205 Buckeye Avenue and includes two data halls and two diesel generators. Built in 1990, the data center is owned by Employers Mutual...

Read more
Read DataBank Raises $2bn for Dallas Data Center Buildout
DataBank Raises $2bn for Dallas Data Center Buildout

DataBank Raises $2bn for Dallas Data Center Buildout

April 22, 2026 Dallas

US data center firm DataBank has secured new financing to support the build-out of three data centers in Dallas, Texas. The company this week announced it has obtained a $2 billion loan to fund construction of the first three facilities at its new Red Oak campus. DataBank said the deal represents...

Read more
Read Local Officials Reject Proposed Data Center in New Brunswick, New Jersey
Local Officials Reject Proposed Data Center in New Brunswick, New Jersey

Local Officials Reject Proposed Data Center in New Brunswick, New Jersey

February 21, 2026 New Jersey

Local authorities in New Brunswick, New Jersey, voted on Wednesday against allowing the construction of a data center on a plot of land slated for redevelopment, instead requiring that a park be built on the site. The New Brunswick City Council was reviewing a proposal for the Jersey-Sandford...

Read more