Prime Data Centers plans seven one-story data center buildings on pre-graded pads in the Starpointe Business Park in Hanover Township, Washington County, on land it has under contract from ALTIAN Development. The campus would run on its own natural gas power plant with a battery microgrid, independent of the grid, with Generate Capital as its power partner. Prime plans to start in early 2027 and to build each building in 14 to 16 months.
Hanover Township's conditional use hearings ran through November 2026, and the state DEP is reviewing the power plant's air permit application.
Site History
-
November 2026: Conditional use hearings conclude, and a local referendum measure fails.
-
September 2026: Prime presents the plans at township hearings.
-
April 2026: Prime files its air permit application with the state DEP.