Site: OneNeck Denver

Company: OneNeck
Metro: Denver
State: Colorado (CO)
Country: United States
Region: North America
Region: Americas
Address: 8675 Concord Center Drive, Englewood, Colorado
Utility Provider: Xcel Energy
Gross SqFt: 35,000
Total Power: 1.6 Megawatts

The datacenter was built in 2015 at a cost of $20 million. Phase I provides 35,000 Square Feet, but facility can be built out to 160,000 Square Feet over 5 phases.

Building:


  • Utility Feeds:Two 2500 kVA utility transformers
  • Critical Load:1600 kW
  • Generators: Four 1.5 mW
  • UPS: 2N
  • Entrance Facilities: Quadruple entrances to two telecommunications rooms

Carriers: TDS, Comcast, CenturyLink, Level3/TW Telecom, Zayo

Map and Nearby Locations:

8675 Concord Center Drive, Englewood, Colorado

SITES within 15 miles of OneNeck Denver

Show SqM



Distance Site name SqFt MW
0.15 miles Cyxtera Denver DN3 85,660 7.20
0.15 miles 8534 Concord - Digital Realty 85,660
0.32 miles Flexential Denver (Compark) 140,000 18.00
0.34 miles EdgeConneX Denver 125,300 21.00
0.36 miles TerraCom Direct Denver
1.33 miles Equinix Denver DE2 107,000
1.61 miles XO Denver 0.69
1.84 miles zColo Latisys 393 Inverness 53,289 5.20
2.33 miles zColo Denver Centennial 81,900 10.00
2.47 miles Flexential Denver (Arapahoe) 21,374 2.55
OneNeck Corporate History