FCDC: Mäntsälä 1

Latest Podcast Gneissitie 3
Under Construction
New facility under construction
Operated by:

FCDC: Mäntsälä 1

Year Planned: 2028
Utility Provider: Nivos
Ownership: FCDC Corp Oy developed by fcdc through kiinteistö oy mäntsälän gneissitie 3; verne operates the data center. the building.

Sites leasing space from FCDC Corp Oy:

Site History

  • In June 2026, construction of the first phase began.
  • In May 2025, Mäntsälä granted the building permit for the data center and its substation.

Project Profile

  • Developer: FCDC Corp Oy
  • Operator: Verne

Map and Nearby Locations

Gneissitie 3
FCDC Corp Oy Sites
Nearby Facilities

FCDC: Mäntsälä 1 Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of FCDC: Mäntsälä 1

Distance Site About
0.02 miles Verne: Mäntsälä DC05
Verne has started construction of a purpose-built data centre campus in Mäntsälä’s Kapuli industrial area. The AI and high-performance computing facility uses renewable electricity supplied through Nivos and offers its waste heat for local heating projects.
0.07 miles Verne: Mäntsälä DC06
0.18 miles Verne: Mäntsälä FI-VDC03
Verne has started construction of a purpose-built data centre campus in Mäntsälä’s Kapuli industrial area. The AI and high-performance computing facility is planned to begin operating in 2027, using renewable electricity supplied through Nivos and offering its waste heat for local heating projects
0.24 miles Nebius Mäntsälä 2
Nebius is developing a second data center in Mäntsälä's Kapuli business district on a separate site from its existing facility.
0.25 miles FCDC: Mäntsälä 2
FCDC is developing a data center building at Graniittitie 6 in the Kapuli business area of Mäntsälä, on a plot leased from the municipality, for a single operator.
0.95 miles Nebius: Mäntsälä Finland
The data center was originally acquired from Yandex, which purchased the land in 2013 and opened it in 2014 as the company's first 'greenfield' project.
11.62 miles Prime: Järvenpää, Finland
US-based operator Prime Data Centers has announced plans for a significant expansion into Finland, targeting a 12-hectare site in the Vähänummi industrial area of Järvenpää.
13.56 miles QTS: Jokela, Tuusula
QTS plans a two-building data center campus in the western employment area of Jokela, Tuusula, on a 16.8-hectare site along Vallunlenkki.
19.68 miles FCDC: Kerava
FCDC plans a data center campus of five buildings in the Alikerava area of southern Kerava, between the Lahti motorway and the Keravanjoki river.

Operating Company

Operated by:

Fincap DC Corp was founded in 2023. According to Joonas Viita-aho, despite its name, the company is not part of the Fincap Group. The Fincap Group is an investment company, where in addition to Janne Kotamäki, investor and football influencer Raimo Sarajärvi is also responsible .

0
Facilities
0
Markets

News See all

Read Hyperco To Develop two 50MW Facilities in Helsinki, Finland
Baxtel

Hyperco To Develop two 50MW Facilities in Helsinki, Finland

December 14, 2022 Helsinki

Hyperco has announced its plan to expand its data center presence in New Zealand with two new data center campus developments. The Nordic data center company said it would develop the facilities in Helsinki, Finland, with each having an initial capacity of 50MW. The company did not reveal the...

Read more
Read Hyperco Acquires Equinix and Thales-Occupied Data Center in Helsinki, Finland
Baxtel

Hyperco Acquires Equinix and Thales-Occupied Data Center in Helsinki, Finland

June 16, 2022 Helsinki

Hyperco has made its first acquisition as it takes over a property belonging to TS-Yhtyma. The company paid more than €35 million ($36.4m) for the property. The building is located at Myllynkivenkuja 4 in Vantaa, Helsinki, Finland. Thales and Equinix are also occupying the property. The building...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts

Ready to Level up Your
Data Center Strategy?