Decimal Digital: Monroeville Mine

Latest Podcast 17 Fort Monroe Industrial Pkwy
Operational
Fully operational facility
Operated by:

Decimal Digital: Monroeville Mine

Utility Provider: Village of Monroeville (municipal electric)
Ownership: Decimal Digital does not own the building.
░░░░ Request Dataset MW
Operational Power

This bitcoin mine runs mining containers on a yard in the Fort Monroe Industrial Park in Monroeville, Huron County. Gray Matter Holdings developed it. A court-appointed receiver now controls the operation, and Decimal Digital runs it. The village supplies power through its municipal electric system under a contract that ran to October 2026.

Map and Nearby Locations

17 Fort Monroe Industrial Pkwy
Decimal Digital Sites
Nearby Facilities

Sites within 15 miles of Decimal Digital: Monroeville Mine

Distance Site About
0.28 miles Decimal Digital: Project Eagle Ridge
Decimal Digital plans Project Eagle Ridge, a single-hall AI data center on 48 acres it owns in the Fort Monroe Industrial Park in Monroeville, Ohio.
6.68 miles AVAIO: Project Andromeda
AVAIO Digital proposed Project Andromeda, a four-building data center campus on 146 acres in Oxford Township, Erie County, Ohio. Township trustees tabled it in 2026.
12.71 miles Aligned: Cleveland NEO-01
NEO-01 is the first building on Aligned Data Centers' four-building Northeast Ohio campus in Perkins Township, south of Sandusky. Its first phase went live in January 2026.

Operating Company

Operated by:

Decimal Digital, which also operates as Decimal Group, is a privately held company based in Summit, New Jersey, led by CEO Roshan Shah. It develops AI data center sites for institutional investors, from land purchase through power procurement, permitting and construction management. It also develops and runs bitcoin mining facilities.

In Ohio, the company owns 47.69 acres in the Fort Monroe Industrial Park in Monroeville through Decimal Digital AI LLC, where it proposes an AI data center called Project Eagle Ridge. It also runs a bitcoin mining operation in the same industrial park for a court-appointed receiver.

Decimal Digital History:

  • In November 2025, the Monroeville village council approved power study agreements for Project Eagle Ridge.
  • In August 2025, Decimal Digital AI LLC bought 47.69 acres in the Fort Monroe Industrial Park in Monroeville, Ohio.
0
Facilities
0
Markets

News See all

Read Cleveland Extends Data Center Moratorium Through January 29, 2027
Cleveland City Council voted on the night of Oct. 19 to extend the city's moratorium on new data centers through Jan. 29, 2027, or until council enacts permanent rules. The extension keeps zoning p...

Cleveland Extends Data Center Moratorium Through January 29, 2027

October 21, 2026 Cleveland

Cleveland City Council voted on the night of Oct. 19 to extend the city's moratorium on new data centers through Jan. 29, 2027, or until council enacts permanent rules. The extension keeps zoning permits and occupancy certificates frozen for new standalone data centers and also covers...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.