P5 is the sixth of seven buildings on Ark's Spring Park campus near Corsham, on the eastern corner of the site. Wiltshire Council approved it in May 2024 as one data centre in two blocks of three floors of data halls joined by an enclosed bridge: P5 North, holding modules M1 to M4, and P5 South, holding M5 and M6. That consent merged two earlier approvals, P5 North (2021) and P5 South (2023). The P5 South plot is the former Hawthorn Works, once home to the plastics moulder Stephens Plastics.
Ark dates the start of development to November 2025. The old factory buildings on the P5 South plot were demolished in early 2026, and the building control notice for the new data centre took effect in October 2026. Ark has signed an occupier for P5 South and has applied to redesign that block for it, as a smaller building with liquid cooling equipment and without the link bridge; the change is still under consultation. P5 will draw on SQ19, a dedicated 30 MVA substation and generator compound with two new 33 kV circuits, completed in October 2023.
Site History
- 2026: building control notice for the P5 data centre valid (October); redesign of P5 South for a signed occupier submitted (October); old buildings on the P5 South plot demolished (early 2026).
- 2025: start of development (November); pre-commencement conditions discharged (March and April).
- 2024: combined P5 scheme approved (May); 16 standby generators at SQ19 permitted (November).
- 2023: SQ19 substation, switch room and generator farm completed (October); P5 South approved (September).
- 2021: P5 North approved (April).