Data Center Campus
Ark Data Centres' Spring Park campus on Westwells Road near Corsham, Wiltshire, is Ark's head office and the base of its Crown Hosting joint venture with the UK government. First built in 2010, with expansions planned through 2029.
Spring Park is Ark Data Centres' founding campus and head office, on Westwells Road at Hawthorn, between Corsham and Neston in Wiltshire. It sits across the road from MOD Corsham, and it has been built up on former industrial land: the higher northern part of the site held a factory building known as SQ2, since demolished, and the lower southern part is the former Hawthorn Works, once home to the plastics moulder Stephens Plastics. In 2026 Ark won consent to extend the campus onto a field south of Westwells Road.
Since 2015 the campus has been the base of Crown Hosting Data Centres, Ark's joint venture with the Cabinet Office, which provides colocation to government departments and other public sector bodies. Ark Estates Spring Park Limited owns the land and Ark Data Centres runs the buildings.
The campus takes its grid supply over 33 kV circuits from the Norrington bulk supply point, arranged as independent resilient systems: two 40 MVA supplies serving the oldest buildings, three 24 MVA supplies into a 48 MVA substation, and SQ19, a 30 MVA substation and generator compound with two further circuits built for the newest phase. Standby power comes from about 70 HVO-fuelled generators under a single Environment Agency permit, including a shared high-voltage generator farm and the SQ19 compound.
Buildings
| Site | Operator | Status | Operational | Building Size | Built |
|---|---|---|---|---|---|
| Ark: Spring Park SQ17 | Ark Data Centres (UK) |
Operational
|
░░░ Request Dataset MW | — | 2010 |
| Ark: Spring Park P1 | Ark Data Centres (UK) |
Operational
|
░░░ Request Dataset MW | — | 2011 |
| Ark: Spring Park P2 | Ark Data Centres (UK) |
Operational
|
░░░ Request Dataset MW | — | 2015 |
| Ark: Spring Park P3 | Ark Data Centres (UK) |
Operational
|
░░░ Request Dataset MW | ░░░░░░ Request Dataset SqFt | 2019 |
| Ark: Spring Park P4 | Ark Data Centres (UK) |
Operational
|
░░░░ Request Dataset MW | ░░░░░░░ Request Dataset SqFt | 2021 |
| Ark: Spring Park P5 | Ark Data Centres (UK) |
Under Construction
|
— | — | 2028 |
| Ark: Spring Park P6 | Ark Data Centres (UK) |
Planned
|
— | — | 2029 |