TPA Group: Strouds Creek

Latest Podcast 1196 Lakewood Dr
In Doubt
The development is facing regulatory or community opposition
Operated by:

TPA Group: Strouds Creek

Lot Size: 981 acres

The Georgia Historic Heartland Megasite is a planned data center park on about 981 acres off Lakewood Drive in Social Circle, Newton County, Georgia, about half a kilometer north of TPA Group's I-20 tract. GA Strouds Creek Land, LLC applied, represented by TPA Group's team.

  • Plan: 12 one-story buildings totaling about 2.5 million sq ft.
  • Approvals: In November 2025 the city annexed 684 of the 981 acres, rezoned them and granted a data center special-use permit.
  • Status: On September 21, 2026 the Georgia Department of Community Affairs decertified Social Circle for one year over the annexation.

Map and Nearby Locations

1196 Lakewood Dr
TPA Group, LLC Sites
Nearby Facilities

Sites within 15 miles of TPA Group: Strouds Creek

Distance Site About
1.37 miles TPA Group: Social Circle 1
First planned building of TPA Group's Social Circle Technology Park, a nine-building data center campus off SR 11 in Social Circle, Georgia.
1.37 miles TPA Group: Social Circle Expansion
2.15 miles WSG Land: Project Axis
Entitled data center tract of about 221 acres on Mill Road in Social Circle, Georgia, owned by WSG Land and marketed by 3Rivers Development as Project Axis. The city granted a data center special-use permit in September 2025; no end user has been named.
3.10 miles PrimeInterested in this information?Contact us
The first phase of the data center broke ground in 2018 with a 970,000 sq ft data center space. The second phase is a three-building expansion that added 1.5 million sq ft to the existing two-building campus in 2023.
3.12 miles PlusInterested in this information?Contact us
The first phase of the data center broke ground in 2018 with a 970,000 sq ft data center space. The second phase is a three-building expansion that added 1.5 million sq ft to the existing two-building campus in 2023.
3.35 miles Dermody: Social Circle Expansion
Second through fourth planned data center buildings on Dermody Properties' 96-acre East Hightower Trail campus in Social Circle, Georgia, with a new on-site electrical substation.
3.43 miles Dermody: Social Circle 1
First of four planned 250,000 sq ft data center buildings on Dermody Properties' 96-acre East Hightower Trail campus in Social Circle, Georgia. The city granted the data center special-use permit in November 2025.
3.48 miles Ridge PrimeInterested in this information?Contact us
The first phase of the data center broke ground in 2018 with a 970,000 sq ft data center space. The second phase is a three-building expansion that added 1.5 million sq ft to the existing two-building campus in 2023.
3.59 miles Global ValleyInterested in this information?Contact us
The first phase of the data center broke ground in 2018 with a 970,000 sq ft data center space. The second phase is a three-building expansion that added 1.5 million sq ft to the existing two-building campus in 2023.
3.67 miles WSG Land: Malcom Park
Entitled data center tract of about 235 acres on Fairplay Drive at Social Circle Parkway in Social Circle, Georgia, owned by WSG Land and marketed by 3Rivers Development as Malcom Park. It forms the western end of the Roy Malcom Road data center complex.
3.70 miles Point GammaInterested in this information?Contact us
The first phase of the data center broke ground in 2018 with a 970,000 sq ft data center space. The second phase is a three-building expansion that added 1.5 million sq ft to the existing two-building campus in 2023.
3.80 miles Sailfish: Social Circle 1
First planned building of Sailfish Investors' four-building data center campus at 1705 Amber Stapp Studdard Road in Social Circle, Georgia. The city approved the site in January 2025, but the project has stalled and local officials say it appears abandoned.
4.02 miles Atlas Development: Social 4
Planned two-building data center on 123 acres at 1402 Roy Malcom Road in Social Circle, Georgia, the middle tract of Atlas Development's Roy Malcom Road complex. The city annexed and rezoned it for data center use in April 2026, with buildings limited to one story.
4.05 miles Sailfish: Social Circle Expansion
Second through fourth planned buildings of Sailfish Investors' Social Circle, Georgia data center campus off Amber Stapp Studdard Road and Social Circle Parkway. The project has stalled and appears abandoned.
4.28 miles Atlas Development: Social 2
Building 2 of Atlas Development's planned data center campus on Roy Malcom Road in Social Circle, Georgia, on the Hawkins Academy tract approved for data center use in November 2025 with buildings limited to one story.
4.29 miles Atlas Development: Social 3
Building 3 of Atlas Development's planned data center campus on Roy Malcom Road in Social Circle, Georgia, on the Hawkins Academy tract approved for data center use in November 2025 with buildings limited to one story.
4.30 miles Atlas Development: Social 1
Building 1 of Atlas Development's planned data center campus on Roy Malcom Road in Social Circle, Georgia, on the Hawkins Academy tract approved for data center use in November 2025 with buildings limited to one story.
4.30 miles Gregory 5
This facility is part of Universal Planning LLC's Gregory Road Data Center Campus in Covington.
4.35 miles Gregory 4
This facility is part of Universal Planning LLC's Gregory Road Data Center Campus in Covington.
4.35 miles Gregory 1
Universal Planning LLC is proposing a data center campus, named the Gregory Road Data Center, in Covington, Newton County.
4.41 miles Serverfarm: Covington, GA
The project involves converting an existing 498,960-square-foot warehouse/distribution facility situated on a 97-acre site at Hazelbrand Road.
4.44 miles Gregory 2
This facility is part of Universal Planning LLC's Gregory Road Data Center Campus in Covington.
4.49 miles Gregory 3
This facility is part of Universal Planning LLC's Gregory Road Data Center Campus in Covington.
4.51 miles South HubInterested in this information?Contact us
This facility is part of Amazon's 430-acre data center campus near Alcovy Road in Covington.
4.53 miles West StationInterested in this information?Contact us
Amazon is developing a new data center campus on 430 acres in Covington, Georgia.
4.57 miles East CenterInterested in this information?Contact us
This facility is part of Amazon's 430-acre data center campus near Alcovy Road in Covington.
4.66 miles Metro RidgeInterested in this information?Contact us
This facility is part of Amazon's 430-acre data center campus near Alcovy Road in Covington.
4.71 miles RidgeInterested in this information?Contact us
This facility is part of Amazon's 430-acre data center campus near Alcovy Road in Covington.
4.98 miles Metro HubInterested in this information?Contact us
Amazon plans to expand its data center footprint in Covington.
17.89 miles DC BLOX: ATL2-A
DC Blox, a US data center operator, has started construction on a new data center campus outside Atlanta, Georgia.
17.97 miles DC BLOX: ATL2-D
This facility is a part of DC Blox's Atlanta East Campus in Rockdale County, GA.
17.97 miles DC BLOX: ATL2-C
This facility is a part of DC Blox's Atlanta East Campus in Rockdale County, GA.
18.05 miles DC BLOX: ATL2-B
DC BLOX: ATL2-B is one of the expansion buildings at DC BLOX's Atlanta East hyperscale campus in Conyers, Rockdale County, about 24 miles east of downtown Atlanta. The 72-acre campus is designed for about 748,000 sq ft across four data center buildings at full buildout, targeting Uptime Tier 3.
18.24 miles Strategic Real Estate Partners, Conyers, GA
Strategic Real Estate Partners plans to build a three-building data center campus in Conyers, a suburb about 20 miles southeast of Atlanta. The site will feature 837,500 sq ft (77,806 sqm) of data center space across three buildings.

TPA Group: Strouds Creek Data Center Photos See all

Map produced by TAG, the Technology Association of Georgia.
Map of Georgia's Data Centers
Source: Baxtel

Map produced by TAG, the Technology Association of Georgia.

Operating Company

Operated by:

TPA Group is a private real estate investment firm based in Atlanta. The company invested, acquired, developed, and sold more than 300 sites totaling more than $30 billion in investment across the US – including industrial, residential, office, business parks, and retail sites.

0
Facilities
0
Markets

News See all

Read Equifax to Decommission Data Center outside Atlanta
Equifax to Decommission Data Center outside Atlanta

Equifax to Decommission Data Center outside Atlanta

September 12, 2025 Atlanta

The City of Alpharetta last week announced that Equifax was investing $25 million to expand its Alpharetta campus, located in Fulton County. The expansion includes the renovation of the third floor of the JV White 1 building, converting it from a data center into collaborative office space. “The...

Read more
Read Atlanta City Council members propose new bill to block data center developments
Atlanta City Council members propose new bill to block data center developments

Atlanta City Council members propose new bill to block data center developments

May 10, 2024 Atlanta

Atlanta City Councilmen Jason Dozier and Matt Westmoreland have introduced bills to block data center developments around certain areas of the Georgia city near transit stops and the Beltline. “Excited to introduce legislation alongside Matt Westmoreland to address the rapid growth of data...

Read more
Read Edged Energy begins work on Atlanta data center
Edged Energy begins work on Atlanta data center

Edged Energy begins work on Atlanta data center

July 04, 2023 Atlanta

Construction on Edge Energy's Atlanta, Georgia data center is underway, with the company commencing work on July 1st. Located at Tilford Yard, the company bought the 158 acre-site back in July 2021; 70 acres will be dedicated to data center development. In January 2023, it filed a building permit...

Read more
Read NCR Resume Additional Services After a Ransomware Breach
NCR Resume Additional Services After a Ransomware Breach

NCR Resume Additional Services After a Ransomware Breach

April 28, 2023 Atlanta

After a ransomware assault caused a data center outage that disrupted its Aloha cloud-based services and Counterpoint apps, NCR is making progress toward restoring services. For the subset of CMC customers who were impacted by the incident, online ordering has resumed and NCR's Command Center...

Read more
Read A new data center is planned for Tilford Yard
A new data center is planned for Tilford Yard

A new data center is planned for Tilford Yard

January 23, 2023 Atlanta

According to reports, a new data center is planned for Tilford Yard, on Atlanta’s Westside, under the project name Edged. This announcement comes following the filing of a building permit for a nearly 210,000-square-foot, two-level data center.Further to this, records show that Endeavour, the...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts

Ready to Level up Your
Data Center Strategy?