Dermody: Social Circle 1

Latest Podcast 5023 E Hightower Trl
Planned
Future facility in planning stage
Operated by:

Dermody: Social Circle 1

Year Planned: 2028
Utility Provider: Georgia Power
Lot Size: 96 acres

The first of four planned data center buildings on Dermody Properties' East Hightower Trail campus in Social Circle, Walton County, Georgia.

  • Site: 5023 E Hightower Trl, part of a 96-acre Light Industrial tract.
  • Building: About 250,000 sq ft.
  • Approvals: Special-use permit approved November 18, 2025.
  • Status: Dermody says the end user is under a non-disclosure agreement.

Map and Nearby Locations

5023 E Hightower Trl
Dermody Properties Sites
Nearby Facilities

Dermody: Social Circle 1 Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Dermody: Social Circle 1

Distance Site
0.18 miles Dermody: Social Circle Expansion
1.06 miles Sailfish: Social Circle 1
1.15 miles Sailfish: Social Circle Expansion
1.58 miles WSG Land: Malcom Park
1.66 miles Atlas Development: Social 3
1.75 miles Atlas Development: Social 4
1.86 miles Atlas Development: Social 2
2.07 miles WSG Land: Project Axis
2.14 miles Atlas Development: Social 1
3.08 miles BetaInterested in this information?Contact us
3.13 miles Valley OneInterested in this information?Contact us
3.15 miles Plaza OneInterested in this information?Contact us
3.22 miles Cloud PointInterested in this information?Contact us
3.24 miles West HubInterested in this information?Contact us
3.43 miles TPA Group: Strouds Creek
3.58 miles TPA Group: Social Circle Expansion
3.88 miles TPA Group: Social Circle 1
7.62 miles Gregory 5
7.64 miles Gregory 1
7.67 miles Gregory 4
7.74 miles Gregory 2
7.81 miles Gregory 3
7.84 miles Serverfarm: Covington, GA
7.90 miles Center ProInterested in this information?Contact us
7.92 miles CentralInterested in this information?Contact us
7.95 miles StationInterested in this information?Contact us
8.05 miles RidgeInterested in this information?Contact us
8.10 miles Prime CampusInterested in this information?Contact us
8.16 miles Hyperscale Data CenterInterested in this information?Contact us
19.88 miles Grindcap: Project Rockforge

Dermody: Social Circle 1 Data Center Photos See all

Map produced by TAG, the Technology Association of Georgia.
Map of Georgia's Data Centers
Source: Baxtel

Map produced by TAG, the Technology Association of Georgia.

Operating Company

Operated by:

Reno, Nevada-based industrial real estate investor and developer. Through Dermody PL Acquisition Co., LLC it won approval in 2025 for a four-building data center campus in Social Circle, Georgia.

0
Facilities
0
Markets

News See all

Read DC BLOX Files For Third Atlanta West Building, 80MW Due In 2029
DC BLOX filed a development of regional impact notice for a third building at its Atlanta West campus in Georgia, [Data Center Dynamics reported](https://www.datacenterdynamics.com/en/news/dc-blox-...

DC BLOX Files For Third Atlanta West Building, 80MW Due In 2029

November 19, 2026 DC BLOX

DC BLOX filed a development of regional impact notice for a third building at its Atlanta West campus in Georgia, Data Center Dynamics reported. The filing with the Georgia Department of Community Affairs covers ATL1-C, a 500,000-square-foot data center at 1800 North River Road in Douglasville....

Read more
Read Microsoft Files for 422MW Three-Building Data Center Campus in Rome, Georgia
Microsoft filed for state review on October 20 of a three-building data center campus in Rome, Georgia, with 422MW of planned capacity. The [Development of Regional Impact application](https://dca....

Microsoft Files for 422MW Three-Building Data Center Campus in Rome, Georgia

November 18, 2026 Microsoft Azure

Microsoft filed for state review on October 20 of a three-building data center campus in Rome, Georgia, with 422MW of planned capacity. The Development of Regional Impact application covers 349 acres at 0 Huffaker Road and 1,659,000 square feet of floor space. Microsoft owns the land, bought in...

Read more
Read Equifax to Decommission Data Center outside Atlanta
Equifax to Decommission Data Center outside Atlanta

Equifax to Decommission Data Center outside Atlanta

September 12, 2025 Atlanta

The City of Alpharetta last week announced that Equifax was investing $25 million to expand its Alpharetta campus, located in Fulton County. The expansion includes the renovation of the third floor of the JV White 1 building, converting it from a data center into collaborative office space. “The...

Read more
Read Atlanta City Council members propose new bill to block data center developments
Atlanta City Council members propose new bill to block data center developments

Atlanta City Council members propose new bill to block data center developments

May 10, 2024 Atlanta

Atlanta City Councilmen Jason Dozier and Matt Westmoreland have introduced bills to block data center developments around certain areas of the Georgia city near transit stops and the Beltline. “Excited to introduce legislation alongside Matt Westmoreland to address the rapid growth of data...

Read more
Read Edged Energy begins work on Atlanta data center
Edged Energy begins work on Atlanta data center

Edged Energy begins work on Atlanta data center

July 04, 2023 Atlanta

Construction on Edge Energy's Atlanta, Georgia data center is underway, with the company commencing work on July 1st. Located at Tilford Yard, the company bought the 158 acre-site back in July 2021; 70 acres will be dedicated to data center development. In January 2023, it filed a building...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Quotes
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.