Switch: Big Beaver PIT01

Latest Podcast 201 Penndale Road
Planned
Future facility in planning stage
Operated by:

Switch: Big Beaver PIT01

Year Planned: 2028
Utility Provider: Penn Power (FirstEnergy Pennsylvania Electric Co.)
Floors: 1
Lot Size: 383 acres

PIT01 is building 1 of 3 in Switch's preliminary plan for its Big Beaver campus on the former Pittsburgh International Race Complex in Big Beaver Borough, Beaver County. It is the southernmost building, next to the planned Switch substation. Switch plans three similar buildings with air-cooled closed-loop chillers and diesel backup generators, plus pads for two future buildings. A new FirstEnergy substation fed from the Hoytdale switching station on existing 345 kV lines will serve the campus. Switch has said the first building could open as soon as January 2028, with all three live by January 2030. The borough must decide on the preliminary plan by December 2026.

Site History

  • October 2026: Switch extends the borough's decision deadline to December 18, 2026.
  • September 2026: Switch submits revised plans.
  • July 2026: Switch files the preliminary land development plan.
  • May 2026: Switch announces the Big Beaver campus.

Map and Nearby Locations

201 Penndale Road
Switch Sites
Nearby Facilities

Switch: Big Beaver PIT01 Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Switch: Big Beaver PIT01

Distance Site About
0.09 miles Switch: Big Beaver PIT02
Switch plans PIT 02 as the second of three data center buildings proposed at its Big Beaver campus in Pennsylvania.
0.19 miles Switch: Big Beaver PIT03
Switch plans PIT 03 as the third building at its proposed Big Beaver data center campus on the former Pittsburgh-area racetrack.
0.33 miles Switch: Big Beaver Future Buildings
Switch has reserved space for two future data center buildings at its Big Beaver campus on the former Pittsburgh International Race Complex in Beaver County.
10.87 miles Stonebridge: Lawrence County
Maryland-based developer Stonebridge Associates has proposed a $15 billion, 16-building hyperscale data center campus on a 569-acre site in Lawrence County, Pennsylvania.
12.58 miles Saadia: Union Township, PA
Saadia Holdings proposes a small data center off Route 422 near the Shenango River in Union Township, Lawrence County.
14.72 miles Aligned: Shippingport PIT-03
PIT-03 is the third of three planned buildings at Aligned Data Centers' Shippingport campus on the former Bruce Mansfield power plant site in Beaver County.
14.82 miles Aligned: Shippingport PIT-02
PIT-02 is the second of three planned buildings at Aligned Data Centers' Shippingport campus on the former Bruce Mansfield power plant site in Beaver County.
15.20 miles Aligned: Shippingport PIT-01
Aligned Data Centers is building a three-building AI campus on the former Bruce Mansfield power plant site in Shippingport, Beaver County, powered on site.
15.40 miles Misty Hollow Energy and Data Campus
Misty Hollow Energy and Data Campus is a proposed data center campus with its own gas power station on a former farm in Forward Township, Butler County.
15.64 miles Big Digital Energy: Midland, PA
Big Digital Energy, formerly Mawson Infrastructure Group, runs a Bitcoin mining data center in modular units on leased land in Midland, Beaver County.
15.95 miles Energy Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us

Operating Company

Operated by:

Switch, the technology infrastructure corporation headquartered in Las Vegas, Nevada is built on the intelligent and sustainable growth of the internet. Switch founder and CEO Rob Roy has developed more than 500 issued and pending patent claims covering data center designs that have manifested into the company’s world-renowned data centers.

Switch has PRIME campuses located in Las Vegas and Tahoe Reno, Nevada; Grand Rapids, Michigan; and Atlanta, Georgia.

0
Facilities
0
Markets

News See all

Read Switch Files Plans for 176-Acre Apex Data Center Campus in North Las Vegas
Switch has submitted a letter of intent to North Las Vegas officials for a roughly 175-acre data center campus at Apex Industrial Park, the first formal development proposal for a land position the...

Switch Files Plans for 176-Acre Apex Data Center Campus in North Las Vegas

September 26, 2026 Switch

Switch has submitted a letter of intent to North Las Vegas officials for a roughly 175-acre data center campus at Apex Industrial Park, the first formal development proposal for a land position the company has quietly assembled along the US-93 corridor since the start of the year. KTNV Las Vegas...

Read more
Read Switch Files Plans For Data Center Campus At Former Pittsburgh Race Track
Switch has filed plans for a new three-building data center campus in Big Beaver Borough, near Pittsburgh, Pennsylvania. The proposed Big Beaver Data Center/Switch Pit 01-03 will feature three faci...

Switch Files Plans For Data Center Campus At Former Pittsburgh Race Track

August 24, 2026 Switch

Switch has filed plans for a new three-building data center campus in Big Beaver Borough, near Pittsburgh, Pennsylvania. The proposed Big Beaver Data Center/Switch Pit 01-03 will feature three facilities, each covering 201,690 sq ft (18,737 sqm). Planning documents indicate a combined backup...

Read more
Read Iron County, Utah Data Center Proposal Gets Green Light
Plans for a 640-acre data center in Iron County, Utah, have been approved by local authorities. The Iron County Planning Commission voted in favor of the proposal during a meeting on June 4.

The...

Iron County, Utah Data Center Proposal Gets Green Light

June 13, 2026 Switch

Plans for a 640-acre data center in Iron County, Utah, have been approved by local authorities. The Iron County Planning Commission voted in favor of the proposal during a meeting on June 4. The Antelope Data Center campus will include five buildings totaling around 1.35 million sq ft (125,000...

Read more
Read Switch Expands Debt Facility to $9.5B to Fund AI Data Center Expansion
Data center firm Switch has increased its available debt capacity to $9.5 billion. The company now has access to a more than $6 billion corporate revolving credit facility, alongside an expanded $3...

Switch Expands Debt Facility to $9.5B to Fund AI Data Center Expansion

June 10, 2026 Switch

Data center firm Switch has increased its available debt capacity to $9.5 billion. The company now has access to a more than $6 billion corporate revolving credit facility, alongside an expanded $3.5 billion syndicated uncommitted performance letter of credit facility (LCF). In April, Switch...

Read more
Read Switch Plans New Data Center Campus Near Pittsburgh
Switch Plans New Data Center Campus Near Pittsburgh

Switch Plans New Data Center Campus Near Pittsburgh

May 01, 2026 Switch

US data center firm Switch is planning a new campus outside Pittsburgh, Pennsylvania. The company this week announced plans for a 382-acre development in Big Beaver Borough, Beaver County. The site is located around 40 miles (64km) northwest of Pittsburgh, near the Ohio state border. Full details...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.