Quantum HPC: Norton DC

Latest Podcast 3700 Limestone Dr
Withdrawn
Project cancelled before construction
Operated by: Quantum HPC

Quantum HPC: Norton DC

Short Code: Project Triton
Utility Provider: Ohio Edison (FirstEnergy)
Lot Size: 92 acres

A proposal to build Project Triton, a data center, at a former mine in Norton City, Ohio, was canceled following strong opposition from local community groups. The developer, Quantum HPC, had planned a 485,000-square-foot center and a 157,000-square-foot power yard with six natural gas turbines on the 90-acre site off South Cleveland-Massillon Road. The property was the former PPG Industries limestone mine, which closed about 50 years ago.

Map and Nearby Locations

3700 Limestone Dr
Quantum HPC Sites
Nearby Facilities

Sites within 15 miles of Quantum HPC: Norton DC

Distance Site About
7.19 miles Ark: Akron
8.08 miles AT&T: 50 W Bowery St
AT&T's central office on West Bowery Street in downtown Akron, Ohio, is a seven-story telephone exchange that AT&T leases back after a 2025 sale.
8.31 miles FairlawnGig: Fairlawn
FairlawnGig, the City of Fairlawn's municipal broadband utility, runs a small colocation data center inside the city's service department building in Fairlawn, Ohio.
8.63 miles Cogent: Akron
Cogent Communications' Akron data center is a two-story telecom building in downtown Akron, Ohio, that Cogent offers for sale, net lease or wholesale colocation.
9.00 miles Lumen Akron 2
9.39 miles HPC Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
9.41 miles Crypto Mining Data CenterInterested in this information?Contact us Data center facility details are available on request.Interested in this information?Contact us
16.84 miles Ark: Canton
The facility is a colocation data center delivering 1.5 Megawatts of existing capacity expandable to 3.0 Megawatts.
17.29 miles LEG Centrum: Massillon
LEG Centrum proposes a data center on the former Standards Testing Laboratories site on Harsh Avenue SE in Massillon, Ohio, pending a rezoning.
17.71 miles BitDeer: Massillon, OH
Bitdeer's fully operational cryptocurrency mining campus in Massillon, Ohio, featuring multiple purpose-built mining buildings and a dedicated electrical substation connected to FirstEnergy's transmission network. The facility underwent phased development and energization throughout 2025 and 2026, including the reconstruction of two fire-damaged buildings, before reaching full operational capacity in October 2026.
18.83 miles Cleveland Clinic Brecksville
Cleveland Clinic's primary enterprise data center, built in Brecksville, Ohio, and in service since January 2012.

Operating Company

Operated by: Quantum HPC
0
Facilities
0
Markets

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.