Pennsylvania Digital I (PAX-1) is a data center campus that PowerHouse Data Centers and Pennsylvania Data Center Partners are building on about 694 acres along Country Club Road in Middlesex Township, Cumberland County, north of Carlisle. The plan has three campuses and 16 buildings totaling about 4.5 million square feet, each campus with its own substation. PPL is building a new 500/138 kV switching station for the site. Carlisle Development Partners bought the land for $44 million in July 2025. Middlesex Township approved the first building plans in spring 2026, and site work and blasting are under way. Residents' zoning and stormwater appeals are pending.

Site History

  • September 2026: A county court declines to halt construction.
  • May 2026: Middlesex supervisors approve the first building plans.
  • March 2026: Phase 1A plans are approved.
  • July 2025: Carlisle Development Partners buys four parcels for $44 million.
  • May 2025: Middlesex Township adopts a data center overlay.

Map and Nearby Locations

250 Country Club Rd
PowerHouse Data Centers Sites
Nearby Facilities

PowerHouse: PAX-1 Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of PowerHouse: PAX-1

Distance Site About
0.33 miles PowerHouse: PAX-1 Expansion
Later phases of the PowerHouse and Pennsylvania Data Center Partners PAX-1 campus in Middlesex Township, Cumberland County.
12.32 miles Verizon: Harrisburg 210 Pine St
Verizon's Harrisburg central office at 210 Pine Street is a multi-story telephone building that houses the area's host switch.
12.97 miles Fairview Crossroads
A $500 million, 750,000-square-foot data center may be built in Fairview Township, Pennsylvania.
13.68 miles MRP Industrial: Watts Township Campus
Industrial real estate developer MRP Industrial is exploring the construction of a massive 288-acre data center campus in Perry County, Pennsylvania, pivoting away from its previous plans to develop a logistics hub at the site.
14.55 miles Alerify: Harrisburg, PA
Pennsylvania-based Alerify has partnered with Zadara to launch a sovereign AI cloud platform.
15.89 miles Verizon: Harrisburg
Former XO site
16.44 miles Corscale: Highlands West
Corscale's Highlands West is a three-building data center campus planned on the former Dauphin Highlands Golf Course in Swatara Township, near Harrisburg.
17.12 miles Corscale: Highlands East
Corscale's Highlands East is a two-building data center campus planned off Highland Street in Lower Swatara and Swatara townships, near Harrisburg.

PowerHouse: PAX-1 Data Center Photos See all

Rendering of Pennsylvania Digital I (PAX1) Campus
Source: PowerHouse Data Centers

Operating Company

Operated by:

PowerHouse Data Centers, wholly owned and operated by American Real Estate Partners (AREP), is a pioneering developer and owner of next-generation data centers, providing sophisticated real estate solutions for hyperscalers that meet their market, data, utility, and space demands. PowerHouse is an established leader in world-class data center development, with 118 data centers underway or in planning, representing over 32 million square feet and 8.1 GW in eight major Tier I and Tier II markets. PowerHouse’s full suite of development services integrates asset strategy, fast-track approvals, infrastructure, on-site power procurement, and sustainable building practices into every project.

0
Facilities
0
Markets

News See all

Read Big Watt, PowerHouse Win Taylor Approval for 1GW Texas Data Center Campus
Taylor City Council voted 5-0 on Oct. 8 to approve a development agreement with Big Watt Digital and PowerHouse Data Centers for the Taylor Technology Campus, a 664-acre hyperscale project immediat...

Big Watt, PowerHouse Win Taylor Approval for 1GW Texas Data Center Campus

October 15, 2026 PowerHouse Data Centers

Taylor City Council voted 5-0 on Oct. 8 to approve a development agreement with Big Watt Digital and PowerHouse Data Centers for the Taylor Technology Campus, a 664-acre hyperscale project immediately east of the city that could reach one gigawatt of capacity. The joint venture announced the...

Read more
Read Big Watt, PowerHouse Win Approval for 1GW Behind-the-Meter Texas Campus
Taylor City Council voted 5-0 on Oct. 8 to approve a development agreement with Big Watt Digital and PowerHouse Data Centers for Taylor Technology Campus, a 664-acre data center and power project e...

Big Watt, PowerHouse Win Approval for 1GW Behind-the-Meter Texas Campus

October 15, 2026 PowerHouse Data Centers

Taylor City Council voted 5-0 on Oct. 8 to approve a development agreement with Big Watt Digital and PowerHouse Data Centers for Taylor Technology Campus, a 664-acre data center and power project east of the city that could reach one gigawatt of capacity. In a joint press release, the partners...

Read more
Read Taylor Approves 1GW Gas-Fired Data Center Campus for Big Watt, PowerHouse
Taylor City Council voted 5-0 on Oct. 8 to annex and approve a development agreement for Taylor Technology Campus, a 664-acre hyperscale project east of Taylor that Big Watt Digital and PowerHouse ...

Taylor Approves 1GW Gas-Fired Data Center Campus for Big Watt, PowerHouse

October 15, 2026 PowerHouse Data Centers

Taylor City Council voted 5-0 on Oct. 8 to annex and approve a development agreement for Taylor Technology Campus, a 664-acre hyperscale project east of Taylor that Big Watt Digital and PowerHouse Data Centers say could support up to one gigawatt. The partners announced the approval in a Business...

Read more
Read PowerHouse Completes Structure of First Irving Data Center in Texas
PowerHouse Completes Structure of First Irving Data Center in Texas

PowerHouse Completes Structure of First Irving Data Center in Texas

March 30, 2026 PowerHouse Data Centers

US operator PowerHouse has topped out a new data center in Dallas, Texas. The company announced the topping out of the first building at its Irving campus over the weekend."Reaching this point is the result of strong coordination across teams on-site. Thank you to Brasfield & Gorrie, LLC...

Read more
Read PowerHouse Data Centers leases data center to unnamed hyperscaler at Arcola campus in Virginia
PowerHouse Data Centers leases data center to unnamed hyperscaler at Arcola campus in Virginia

PowerHouse Data Centers leases data center to unnamed hyperscaler at Arcola campus in Virginia

January 15, 2026 PowerHouse Data Centers

PowerHouse Data Centers has signed an unnamed hyperscaler at its PowerHouse Arcola campus in Loudoun County, Virginia. The lease is described as long-term, though it has not been stated if the hyperscaler will take up all the capacity at the campus. "PowerHouse Arcola's lease execution...

Read more
Read More News

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.