Piqua 1 is the first of two planned data center buildings, about 350,000 sq ft, on Meta's campus at the northeast corner of Farrington Road and Washington Road in Piqua, Ohio. Meta's affiliate J5 LLC (dba Shaytura LLC) bought the land from The Piqua Land Company II in December 2025 and January 2026.
The building sits on the south half of the property, beside the site's first access road and the temporary construction substation on Washington Road. Crews cleared the farm buildings from the land in mid-2026. In November 2026 Piqua voters approved a charter amendment banning data centers larger than 25 MW, and the project's future is uncertain.
Site History
-
November 2026: Piqua voters approve a charter ban on data centers over 25 MW. Meta says it will work with local officials to decide the future of its investment.
-
July 2026: J5 signs a construction power agreement with the City of Piqua.
-
January 2026: J5 and the city sign the development agreement.
-
December 2025: J5 buys the land from The Piqua Land Company II.