Go to PodcastLancium owns the land and the electrical infrastructure at its Clean Campus in north Abilene, Taylor County. The City of Abilene annexed more than 800 acres for the project in 2021.
Crusoe leases land from Lancium and builds the data centers. Eight Stargate buildings serve Oracle and OpenAI. Two more buildings, on land Lancium bought in 2025, serve Microsoft.
The campus connects to the ERCOT grid through AEP Texas, with a 138 kV substation and a 345 kV substation on site. An on-site natural-gas plant supports the first eight buildings. A second gas plant is planned for the Microsoft buildings.
| Distance | Site | About |
|---|---|---|
| 0.24 miles | Crusoe: Abilene 6 |
This building will be part of the second phase of Crusoe's data center complex currently under construction at the Lancium Clean Campus in Abilene, Texas.
|
| 0.30 miles | Crusoe: Abilene 7 |
This building will be part of the second phase of Crusoe's data center complex currently under construction at the Lancium Clean Campus in Abilene, Texas.
|
| 0.39 miles | Crusoe: Abilene 5 |
This building will be part of the second phase of Crusoe's data center complex currently under construction at the Lancium Clean Campus in Abilene, Texas.
|
| 0.44 miles | Crusoe: Abilene 8 |
This building will be part of the second phase of Crusoe's data center complex currently under construction at the Lancium Clean Campus in Abilene, Texas.
|
| 0.53 miles | Core ValleyInterested in this information?Contact us | Data center facility details are available on request.Interested in this information?Contact us |
| 0.53 miles | Crusoe: Abilene 1 |
The first phase will see a 998,000 square foot facility designed to handle huge AI workloads, supporting up to 100,000 GPUs per building.
|
| 0.56 miles | Crusoe: Abilene 4 |
This building will be part of the second phase of Crusoe's data center complex currently under construction at the Lancium Clean Campus in Abilene, Texas.
|
| 0.68 miles | CampusInterested in this information?Contact us | Data center facility details are available on request.Interested in this information?Contact us |
| 0.68 miles | Crusoe: Abilene 2 |
This facility is part of Crusoe Energy's Lancium Clean Compute Campus in West Texas.
|
| 0.70 miles | Crusoe: Abilene 9 |
Crusoe is building two data center buildings, numbered 9 and 10, on the Lancium campus in Abilene for Microsoft. Each building is about 738,000 square feet.
|
| 0.74 miles | Crusoe: Abilene 3 |
Construction is underway for the second phase of Crusoe's data center complex at the Lancium Clean Campus in Abilene, Texas.
|
| 0.86 miles | Cloud HubInterested in this information?Contact us | Data center facility details are available on request.Interested in this information?Contact us |
| 0.88 miles | Crusoe: Abilene 10 |
Crusoe is building two data center buildings, numbered 9 and 10, on the Lancium campus in Abilene for Microsoft. Each building is about 738,000 square feet.
|
| 5.74 miles | Duos: Abilene Edge DC |
The Duos Edge data center sits at the Region 14 Education Service Center campus in Abilene, Texas.
|
| 13.56 miles | Vantage: Frontier 4 |
This facility is part of Vantage's Frontier data center campus in Shackelford County, Texas.
|
| 13.83 miles | Global RidgeInterested in this information?Contact us | Data center facility details are available on request.Interested in this information?Contact us |
| 13.85 miles | Vantage: Frontier 5 |
This facility is part of Vantage's Frontier data center campus in Shackelford County, Texas.
|
| 13.95 miles | Vantage: Frontier 6 |
This facility is part of Vantage's Frontier data center campus in Shackelford County, Texas.
|
| 13.99 miles | Park PlusInterested in this information?Contact us | Data center facility details are available on request.Interested in this information?Contact us |
| 14.04 miles | East ParkInterested in this information?Contact us | Data center facility details are available on request.Interested in this information?Contact us |
| 14.18 miles | Vantage: Frontier 7 |
This facility is part of Vantage's Frontier data center campus in Shackelford County, Texas.
|
| 14.19 miles | Vantage: Frontier 2 |
This facility is part of Vantage's Frontier data center campus in Shackelford County, Texas.
|
| 14.22 miles | Valley AlphaInterested in this information?Contact us | Data center facility details are available on request.Interested in this information?Contact us |
| 14.25 miles | Edge PlazaInterested in this information?Contact us | Data center facility details are available on request.Interested in this information?Contact us |
| 14.40 miles | Vantage: Frontier 8 |
This facility is part of Vantage's Frontier data center campus in Shackelford County, Texas.
|
| 14.44 miles | AlphaInterested in this information?Contact us | Data center facility details are available on request.Interested in this information?Contact us |
| 14.46 miles | South CenterInterested in this information?Contact us | Data center facility details are available on request.Interested in this information?Contact us |
| 14.49 miles | Vantage: Frontier 1 |
Vantage Data Centers is making its largest investment ever, with plans to spend over $25 billion to build a massive data center campus called "Frontier" in Shackelford County, Texas.
|
| 14.62 miles | Vantage: Frontier 9 |
This facility is part of Vantage's Frontier data center campus in Shackelford County, Texas.
|
| 14.66 miles | Station UltraInterested in this information?Contact us | Data center facility details are available on request.Interested in this information?Contact us |
| 14.67 miles | Tower TwoInterested in this information?Contact us | Data center facility details are available on request.Interested in this information?Contact us |
| 14.71 miles | Vantage: Frontier 3 |
This facility is part of Vantage's Frontier data center campus in Shackelford County, Texas.
|
| 14.88 miles | Vantage: Frontier 10 |
This facility is part of Vantage's Frontier data center campus in Shackelford County, Texas.
|
| 14.98 miles | Station ThreeInterested in this information?Contact us | Data center facility details are available on request.Interested in this information?Contact us |
| 17.39 miles | Bolt: Project North |
Project North is Bolt Data & Energy's proposed AI data center campus with its own power generation on the Buck Nail Ranch, about 15 miles west of Albany in Shackelford County, Texas.
|
Mar 12, 2026 Eric Bell World
Go to Podcast
Jan 15, 2026 Eric Bell Applied Digital
Go to Podcast
Jan 05, 2026 Eric Bell Dallas
Go to Podcast
Sep 04, 2025 Eric Bell Texas
Go to PodcastTell us what you're looking for. We respond within one business day.